Red flags

  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 36 months from the original
23 of 86Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 126 documents Report an error

CHAYTANYA NAGARI is a Plotted project by RAJESH MOTGHARE in Nagpur, Maharashtra, registered with MahaRERA as P50500024757 on 2 Mar 2020. Possession is promised by 31 Dec 2026. The completion date has moved by 36 months from the original filing. 63 of the 86 units on this registration are recorded sold or booked.

At a glance

Project

  • NameCHAYTANYA NAGARI
  • TypePlotted
  • Location
    • KALMESHWAR ROAD
    • VILLAGE PARDI
    • KALMESHWAR ROAD
    • Pardi
    • Nagpur (Rural)
    • Nagpur
    • 441501
  • Pincode441501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500024757
  • ReraGenie IDRG-MH-42127

Builder

  • NameRAJESH MOTGHARE
  • Entity typeIndividual

Key dates

this monthRegisteredMar 2020First promiseDec 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on2 Mar 2020
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2023)
  • BuildingsNot stated in filing
  • Documents filed126 files

Current status

73%63 of 86 units booked

Figures as on 16 Jul 2026, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 16 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area11,628 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on2 Feb 2026

Approvals and building plan

Sanctioning authorityDistrict Officer Office in Nagpur (Nagpur Division)

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRAMDASPETH , NAGPUR

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectEKVEERA ARCHITECHS
ArchitectRAVEENA MOTGHARE
EngineerKIRAN SHIVANKAR
EngineerAspect Designs
Chartered AccountantAMOL SHEGAONKAR
Chartered AccountantNAHUSH PRAVIN SAHASTRABUDDHE
Chartered AccountantA M Dabke & Associates
PartnerRole in project
RAJESH MADHUKARRAO MOTGHARE-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50500018411Dec 2023 → Dec 2025

Reason as filed by the promoterwe have already received 80% RL, due to covid and due to some issues with contractor the project got delayed. but we will complete the project within extended due date

EA19022619908Dec 2023 → Dec 2026

Reason as filed by the promoterThe delay in the project is primarily due to unforeseen circumstances affecting the timely execution of critical construction activities. Delays in obtaining statutory approvals, temporary shortages in construction materials and labour, and coordination challenges among contractors led to interruptions in the scheduled work. As these activities were interdependent, the impact on one stage affected subsequent stages, resulting in an overall extension of the project timeline.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Feb 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Oct 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Feb 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Feb 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed126

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 126 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 June-26 Chaityanya Nagri.pdf16 Jul 2026
Withdrawal Update Form 2File: Form 2 June-26 Chaityanya Nagri.pdf16 Jul 2026
Withdrawal Update Form 3File: Form 3 June-2026 Chaitanya Nagri.pdf16 Jul 2026
Withdrawal Update Form 1File: Form 1 June-26.pdf9 Jul 2026
Withdrawal Update Form 1File: Form 1 June-26.pdf9 Jul 2026
Withdrawal Update Form 2File: Form 2 June-2026 Chaitanya Nagari.pdf9 Jul 2026
Withdrawal Update Form 2File: Form 2 June-2026 Chaitanya Nagari.pdf9 Jul 2026
Withdrawal Update Form 3File: Form 3 June-2026 Chaitanya Nagri (1).pdf9 Jul 2026
Withdrawal Update Form 3File: Form 3 June-2026 Chaitanya Nagri (1).pdf9 Jul 2026
Withdrawal Update Form 1File: Form 1 Mar-26.pdf11 Jun 2026
Withdrawal Update Form 1File: Form 1 Mar-26.pdf11 Jun 2026
Withdrawal Update Form 2File: Form 2 Mar-26.pdf11 Jun 2026
Withdrawal Update Form 2File: Form 2 Mar-26.pdf11 Jun 2026
Withdrawal Update Form 3File: Form 3 Mar-26.pdf11 Jun 2026
Withdrawal Update Form 3File: Form 3 Mar-26.pdf11 Jun 2026
Form 2A (FY 2025-2026)File: Form 2A Chaitanya Ngari 2026.pdf3 May 2026
Withdrawal Update Form 1File: Form 1 Sep-25.pdf19 Feb 2026
Withdrawal Update Form 1File: Form 1 Sep-25.pdf19 Feb 2026
Withdrawal Update Form 1File: Form 1 Sep-25.pdf19 Feb 2026
Withdrawal Update Form 1File: Form 1 Sep-25.pdf19 Feb 2026
Withdrawal Update Form 1File: Form 1 Sep-25.pdf19 Feb 2026
Withdrawal Update Form 1File: Form 1 Sep-25.pdf19 Feb 2026
Withdrawal Update Form 1File: Form 1 Sep-25.pdf19 Feb 2026
Withdrawal Update Form 1File: Form 1 Dec-25.pdf19 Feb 2026
Withdrawal Update Form 1File: Form 1 Dec-25.pdf19 Feb 2026
Withdrawal Update Form 2File: Form 2 Sep-25.pdf19 Feb 2026
Withdrawal Update Form 2File: Form 2 Sep-25.pdf19 Feb 2026
Withdrawal Update Form 2File: Form 2 Sep-25.pdf19 Feb 2026
Withdrawal Update Form 2File: Form 2 Sep-25.pdf19 Feb 2026
Withdrawal Update Form 2File: Form 2 Sep-25.pdf19 Feb 2026
Withdrawal Update Form 2File: Form 2 Sep-25.pdf19 Feb 2026
Withdrawal Update Form 2File: Form 2 Sep-25.pdf19 Feb 2026
Withdrawal Update Form 2File: Form 2 Dec-25.pdf19 Feb 2026
Withdrawal Update Form 2File: Form 2 Dec-25.pdf19 Feb 2026
Withdrawal Update Form 3File: Form 3 Sep-25.pdf19 Feb 2026
Withdrawal Update Form 3File: Form 3 Sep-25.pdf19 Feb 2026
Withdrawal Update Form 3File: Form 3 Sep-25.pdf19 Feb 2026
Withdrawal Update Form 3File: Form 3 Sep-25.pdf19 Feb 2026
Withdrawal Update Form 3File: Form 3 Sep-25.pdf19 Feb 2026
Withdrawal Update Form 3File: Form 3 Sep-25.pdf19 Feb 2026
Withdrawal Update Form 3File: Form 3 Sep-25.pdf19 Feb 2026
Withdrawal Update Form 3File: Form 3 Dec-25.pdf19 Feb 2026
Withdrawal Update Form 3File: Form 3 Dec-25.pdf19 Feb 2026
Form 1File: Form 1 Dec-23.pdf3 Feb 2026
Form 2File: Form 2 Dec-23.pdf3 Feb 2026
Form 3File: Form 3 Dec-23.pdf3 Feb 2026
Disclosure of Sold and Booked InventoryFile: Dec-23.pdf3 Feb 2026
Form 1File: Form 1 Mar-24.pdf3 Feb 2026
Form 2File: Form 2 Mar-24.pdf3 Feb 2026
Form 3File: Form 3 Mar-24.pdf3 Feb 2026
Disclosure of Sold and Booked InventoryFile: Mar-24.pdf3 Feb 2026
Form 1File: Form 1 Jun-24.pdf3 Feb 2026
Form 2File: Form 2 Jun-24.pdf3 Feb 2026
Form 3File: Form 3 Jun-24.pdf3 Feb 2026
Disclosure of Sold and Booked InventoryFile: Jun-24.pdf3 Feb 2026
Form 1File: Form 1 Sep-24.pdf3 Feb 2026
Form 2File: Form 2 Sep-24.pdf3 Feb 2026
Form 3File: Form 3 Sep-24.pdf3 Feb 2026
Disclosure of Sold and Booked InventoryFile: Sep-24.pdf3 Feb 2026
Form 1File: Form 1 Dec-24.pdf3 Feb 2026
Form 2File: Form 2 Dec-24.pdf3 Feb 2026
Form 3File: Form 3 Dec-24.pdf3 Feb 2026
Disclosure of Sold and Booked InventoryFile: Dec-24.pdf3 Feb 2026
Form 1File: Form 1 Mar-25.pdf3 Feb 2026
Form 2File: Form 2 Mar-25.pdf3 Feb 2026
Form 3File: Form 3 Mar-25.pdf3 Feb 2026
Disclosure of Sold and Booked InventoryFile: Mar-25.pdf3 Feb 2026
Withdrawal Update Form 1File: Form 1 Jun-25.pdf3 Feb 2026
Withdrawal Update Form 1File: Form 1 Jun-25.pdf3 Feb 2026
Withdrawal Update Form 2File: Form 2 Jun-25.pdf3 Feb 2026
Withdrawal Update Form 2File: Form 2 Jun-25.pdf3 Feb 2026
Withdrawal Update Form 3File: Form 3 June-25.pdf3 Feb 2026
Withdrawal Update Form 3File: Form 3 June-25.pdf3 Feb 2026
Form 2A (FY 2023-2024)File: Form 2A Mar-24.pdf3 Feb 2026
Form 2A (FY 2024-2025)File: Form 2A Mar-25.pdf3 Feb 2026
Form 5 (FY 2023-2024)File: Form 5 23-24.pdf3 Feb 2026
Form 5 (FY 2024-2025)File: Form 5 24-25.pdf3 Feb 2026
Disclosure of sold/ booked inventoryFile: Chaitanya Nagari Sold unsold inventory .pdf23 Jan 2024
Declaration in FORM BFile: Formbmotghare.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec-21.pdf12 Jan 2024

How this compares with Nagpur

73%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one moved by 36 months
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CHAYTANYA NAGARI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VILLAGE PARDI, KALMESHWAR ROAD2,800+ in Nagpur

Builder: RAJESH MOTGHARE

RAJESH MOTGHARE has 1 registration on MahaRERA, including CHAYTANYA NAGARI. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if CHAYTANYA NAGARI is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CHAYTANYA NAGARI?

The registered promoter entity is RAJESH MOTGHARE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CHAYTANYA NAGARI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for CHAYTANYA NAGARI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CHAYTANYA NAGARI?

The professionals named in the filing: Architect: EKVEERA ARCHITECHS; Architect: RAVEENA MOTGHARE; Engineer: KIRAN SHIVANKAR; Engineer: Aspect Designs; Chartered Accountant: AMOL SHEGAONKAR; Chartered Accountant: NAHUSH PRAVIN SAHASTRABUDDHE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CHAYTANYA NAGARI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CHAYTANYA NAGARI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CHAYTANYA NAGARI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.