Registration lapsed No litigation declared Plotted project

CHANDAN NAGAR

By NARENDRA SONULE & 3 OTHERS RAMESH SONULE

RG-MH-00039 · RERA P50400026300 · Last updated on MahaRERA portal: 19 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 39 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Wardha registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
14 of 27Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 67 documents Report an error

CHANDAN NAGAR is a Plotted project by NARENDRA SONULE & 3 OTHERS RAMESH SONULE in Wardha, Maharashtra, registered with MahaRERA as P50400026300 on 7 Sep 2020. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 39 months from the original filing. 13 of the 27 units on this registration are recorded sold or booked.

At a glance

Project

  • NameCHANDAN NAGAR
  • TypePlotted
  • Location
    • SURVEY NO 6 DHOTRA KASAR WARDHA 442304
    • DHOTRA KASAR
    • Dhotra (534164)
    • Wardha
    • 442304
  • Pincode442304
  • RERA no.P50400026300
  • ReraGenie IDRG-MH-00039

Builder

  • NameNARENDRA SONULE & 3 OTHERS RAMESH SONULE
  • Entity typeIndividual

Key dates

10 months past promisethis monthRegisteredSep 2020First promiseSep 2022Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on7 Sep 2020
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Sep 2022)
  • BuildingsNot stated in filing
  • Documents filed67 files

Current status

48%13 of 27 units booked

Figures as on 19 Feb 2025, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities18

As on 19 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
ENTRACE GATEYes100%
CORNER POOLYes100%
COMPOUND WALLYes100%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,447 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4446.73

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMOHTA MARKET MAIN ROAD WARDHA 442001

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBHUPENDRA BELKAIYA
ArchitectROHIT RATHI
EngineerBHUPENDRA BELKAIYA
EngineerAJAY RATHI
Chartered AccountantDARSHAN WAKHARIYA
PartnerRole in project
NARENDRA SONULE & 3 OTHERS RAMESH SONULE-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50400018275Sep 2022 → Dec 2025

Reason as filed by the promoterExisting Promoter (Ramesh Sonule) died on 20/04/2021, and he was a farmer , thereafter projects rights and liabilities change by succession in our name , hence to understand the project situation and to complete the project we request you to grant project extention up to 31/12/2025. We assure you all the pending works will be completed by us within extended period of time.

EXT50400013532Sep 2022 → Sep 2023

Reason as filed by the promoterDEATH OF PROMOTER

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Sep 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Sep 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Sep 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Sep 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 19 Feb 2025

Documents filed67

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 FORM 1 310324.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 FORM 1 300624.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 FORM 1 300924.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5 FORM 1 311224.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 FORM 1 311223.pdf19 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 FORM 3 311223.pdf19 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 FORM 3 310324.pdf19 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 FORM 3 300624.pdf19 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4 FORM 3 300924.pdf19 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 FORM 3 311224.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 FORM 2 310324.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 FORM 2 311224.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 FORM 2 300924.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 FORM 2 300624.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 FORM 2 311223.pdf19 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: from 4.pdf19 Feb 2025
Disclosure of sold/ booked inventoryFile: 1 sold inventory date 31 12 2023.pdf19 Feb 2025
Disclosure of sold/ booked inventoryFile: 3 sold inventory date 30 6 2024.pdf19 Feb 2025
Disclosure of sold/ booked inventoryFile: 4 sold inventory date 30 9 2024.pdf19 Feb 2025
Disclosure of sold/ booked inventoryFile: 5 sold inventory date 31 12 2024.pdf19 Feb 2025
CERSAI detailsFile: 2 sold inventory date 31 3 2024.pdf19 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 310324.pdf19 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 2324.pdf19 Feb 2025
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Date 15_12_2024.pdf27 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: completion certificate_ Sonule.pdf27 Dec 2024
Declaration in FORM BFile: Form B_ Chandan Nagar.pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_08_12_2023.pdf18 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_08_12_2023.pdf18 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A_08_12_2023.pdf18 Dec 2023
Disclosure of sold/ booked inventoryFile: Book sold inventory _30_06_2023.pdf18 Dec 2023
Disclosure of sold/ booked inventoryFile: Book Sold Inventory_31_03_2023.pdf18 Dec 2023
Disclosure of sold/ booked inventoryFile: Books sold inventory_30_09_2023.pdf18 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_01_12_2023.pdf18 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_04_12_2023.pdf18 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_12_12_2023.pdf18 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 2223.pdf18 Dec 2023
PAN CardFile: PAN AND AADHAR ALL.pdf15 Feb 2023
Declaration in FORM BFile: FORM B_PROPOSED PROMOTER.pdf15 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Chandan Nagar_ form 1.pdf15 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Chandan Nagar_ form 2.pdf15 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Chandan Nagar_ form 2A.pdf15 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 _ part 1.pdf15 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 _ part 2.pdf15 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5_20-21.pdf15 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5_21-22.pdf15 Feb 2023
Other - LegalFile: 7 12 EXTRACT_PART 1.pdf15 Feb 2023
Other - LegalFile: 7 12 EXTRACT_PART 2.pdf15 Feb 2023
Other - LegalFile: 7 12 EXTRACT_PART 3.pdf15 Feb 2023
Other - LegalFile: APPLICATION_ANNEXURE A,B,C.pdf15 Feb 2023
Other - LegalFile: PAN AND AADHAR ALL.pdf15 Feb 2023
Other - LegalFile: Ramesh Sonule Death certificate.pdf15 Feb 2023
Other - FinanceFile: Ramesh Sonule_ Bank statement.pdf15 Feb 2023
Other - FinanceFile: Satyabhama _ Bank statement.pdf15 Feb 2023
Building plan approval or NA orderFile: NA ORDER.pdf3 Sep 2020
Building Plan Approval / NA Order for plotted developmentFile: NA ORDER.pdf3 Sep 2020
Layout approvalFile: NA ORDER.pdf1 Sep 2020
Building plan approval or NA orderFile: SANCTIONED MAP.pdf1 Sep 2020
PAN CardFile: PAN.pdf1 Sep 2020
Copy of the legal title reportFile: SEARCH REPORT.pdf1 Sep 2020
Details of encumbrancesFile: DECLARATION FOR ENCUMBRANCE.pdf1 Sep 2020
Copy of Layout Approval (in case of layout)File: NA ORDER.pdf1 Sep 2020
Building Plan Approval / NA Order for plotted developmentFile: SANCTIONED MAP.pdf1 Sep 2020
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf1 Sep 2020
Declaration in FORM BFile: FORM B.pdf1 Sep 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf1 Sep 2020
Proforma of Allotment letterFile: DECLARATION FOR PLOT ALLOTMENT.pdf1 Sep 2020
Proforma of Allotment letterFile: PROFARMA AGREEMENT TO SALE.pdf1 Sep 2020

How this compares with Wardha

48%of this project is bookeddistrict median 0%
5%of Wardha projects moved their completion datethis one moved by 39 months
18%of Wardha registrations have lapsed or been cancelledthis one is among them

Computed across the 290+ Wardha projects on ReraGenie, from their own filings.

Keep CHANDAN NAGAR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DHOTRA KASAR290+ in Wardha

Builder: NARENDRA SONULE & 3 OTHERS RAMESH SONULE

NARENDRA SONULE & 3 OTHERS RAMESH SONULE has 1 registration on MahaRERA, including CHANDAN NAGAR. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Wardha district page.

Frequently asked questions

What does it mean that CHANDAN NAGAR shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if CHANDAN NAGAR is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CHANDAN NAGAR?

The registered promoter entity is NARENDRA SONULE & 3 OTHERS RAMESH SONULE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CHANDAN NAGAR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for CHANDAN NAGAR?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CHANDAN NAGAR?

The professionals named in the filing: Architect: BHUPENDRA BELKAIYA; Architect: ROHIT RATHI; Engineer: BHUPENDRA BELKAIYA; Engineer: AJAY RATHI; Chartered Accountant: DARSHAN WAKHARIYA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CHANDAN NAGAR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CHANDAN NAGAR. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CHANDAN NAGAR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.