Home / Browse projects / Bengaluru Rural, Karnataka / Century Bliss
Century Bliss
By Hebbal Properties Private Limited
RG-KA-63611 · RERA PRM/KA/RERA/1250/301/PR/210426/008595 · Last updated on RERA Karnataka portal: 14 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Century Bliss is a Residential/Group Housing project by Hebbal Properties Private Limited in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/301/PR/210426/008595 on 21 Apr 2026. Possession is promised by 7 Apr 2031. 87 of the 272 units on this registration are recorded sold or booked, and 0 of 18 construction stages are filed complete.
At a glance
Project
- NameCentury Bliss
- TypeResidential/Group Housing
- Location
- Doddaballapura
- Bengaluru Rural
- 562157
- Pincode562157
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1250/301/PR/210426/008595
- ReraGenie IDRG-KA-63611
Builder
- NameHebbal Properties Private Limited
- Entity typeCompany
- CINU70109KA2021PTC145179
- GSTIN29AAFCH6957D1ZA
- Authorized SignatoryMahesh Prabhu
- Non-executive DirectorP Ravindra Pai
- DirectorsP Ravindra Pai, P Ashwin Pai
- Project HeadNeelkanth Patil
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on21 Apr 2026
- Promised completion7 Apr 2031
- Revised completionNone
- Buildings3 building records
- Documents filed111 files
Current status
Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower 01 | - | - | - | 98 | 0 | 98 |
| Tower 02 | - | - | - | 96 | 0 | 96 |
| Tower 03 | - | - | - | 78 | 0 | 78 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 18 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 80%.
Building: 4% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 80% |
| Foundation footing work | 0% |
| Upto Plinth Level | 0% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 0% |
| Retaining wall (All types) | 0% |
| RCC or MS Framed structure | 0% |
| Masonry Construction | 0% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | 0% |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | Yes | 0% |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | Yes | 0% |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | Yes | 0% |
| Community Hall | Yes | 0% |
| Outdoor Sports facility | Yes | 0% |
| Indoor Sports facility | Yes | 0% |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 0% |
| Parks | Yes | 0% |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 0% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | Yes | 0% |
| Fire escapes | Yes | 0% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 0% |
| Basement | Yes | 0% |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 0% |
| Common storage spaces | No | Not applicable |
Land and ownership3
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| HEBBAL PROPERTIES PRIVATE LIMITED | - | - |
| HEBBAL PROPERTIES PRIVATE LIMITED | - | - |
| HEBBAL PROPERTIES PRIVATE LIMITED | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 112.38 cr | Rs 4.85 cr |
| On-site expenditure-Salaries of workers | Rs 64.83 cr | - |
| Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC) | Rs 54.00 cr | Rs 10.14 lakh |
| On-site expenditure-Site Overhead | Rs 32.42 cr | - |
| On-site expenditure-Cost Of Services(Water, Electricity, Sewage) | Rs 4.32 cr | - |
| On-site expenditure-Consultants Fees | Rs 2.16 cr | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Chandrashekar R |
| Engineer | Swaroop Devaiah KL |
| Chartered Accountant | Sugnana Kumar H |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed111
As listed on the registration, under the names the promoter filed them with; the newest 80 of 111 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/301/PR/210426/008595 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Bliss Form - 4 CA (Q2 2026-27).pdf | 14 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Bliss Form 5 - Architect (Q22027).pdf | 14 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Century Bliss Form 6 - Engineer (Q22027).pdf | 14 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 14 Oct 2026 |
| Q2 2026-27 KSPCB- MOEF (Above 50 Acres) | 14 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 14 Oct 2026 |
| Q2 2026-27 Fire and Safety | 14 Oct 2026 |
| Q2 2026-27 Airport Authority of India | 14 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Century Bliss Form - 4 CA (Q12027).pdf | 6 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Bliss Form 5 - Architect (Q12027).pdf | 6 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Century Bliss Form 6 - Engineer (Q12027).pdf | 6 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 6 Jul 2026 |
| Q1 2026-27 KSPCB- MOEF (Above 50 Acres) | 6 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 6 Jul 2026 |
| Q1 2026-27 Fire and Safety | 6 Jul 2026 |
| Q1 2026-27 Airport Authority of India | 6 Jul 2026 |
| RERA RepliesFile: RERA Reply.pdf | 10 Apr 2026 |
| Authorisation letterFile: Annexure R1 Authorisation.pdf | 10 Apr 2026 |
| Clarification on JDAFile: Annexure R3 Clarification on JDA.pdf | 10 Apr 2026 |
| Clarification on sources of fundsFile: Annexure R5 Clarification on Sources of Funds.pdf | 10 Apr 2026 |
| Bank StatementsFile: Annexure R6 Bank statements.pdf | 10 Apr 2026 |
| Building licenseFile: Annexure R7 Building license.pdf | 10 Apr 2026 |
| Building PlanFile: Annexure R8 Building plan.pdf | 10 Apr 2026 |
| Affidavit for KSPCB NOC and receiptFile: Annexure R9 Affidavit and receipt.pdf | 10 Apr 2026 |
| CDP demarcating the projectFile: Annexure R10 CDP.pdf | 10 Apr 2026 |
| Facilities detailsFile: Annexure R12 Facilities details.pdf | 10 Apr 2026 |
| NOCsFile: Annexure R13 NOCs.pdf | 10 Apr 2026 |
| Structural stability certificate and license of the engineerFile: Annexure R14 Structural stability certificate and license.pdf | 10 Apr 2026 |
| Allotment letterFile: Annexure R15 Allotment Letter.pdf | 10 Apr 2026 |
| Updated ATSFile: Annexure R16 ATS.pdf | 10 Apr 2026 |
| RTC, survey 37/1A | - |
| Mutation, survey 37/1A | - |
| Encumbrance Certificate, survey 37/1A | - |
| Conversion/Alienation Order, survey 37/1A | - |
| Sale/Title/Gift Deed, survey 37/1A | - |
| Khatha, survey 37/1A | - |
| RTC, survey 37/1B | - |
| Mutation, survey 37/1B | - |
| Encumbrance Certificate, survey 37/1B | - |
| Conversion/Alienation Order, survey 37/1B | - |
| Sale/Title/Gift Deed, survey 37/1B | - |
| Khatha, survey 37/1B | - |
| RTC, survey 37/2 | - |
| Mutation, survey 37/2 | - |
| Encumbrance Certificate, survey 37/2 | - |
| Conversion/Alienation Order, survey 37/2 | - |
| Sale/Title/Gift Deed, survey 37/2 | - |
| Khatha, survey 37/2 | - |
| Registration CertificateFile: Annexure 1 HPPL COI.PDF | - |
| Memorandum of AssociationFile: Annexure 15 HPPL MOA.pdf | - |
| Article of AssociationFile: Annexure 16 HPPL AOA.pdf | - |
| GST CertificateFile: Annexure 3 HPPL GSTIN Certificate.pdf | - |
| Organization StructureFile: Annexure 14 Orgination Structure.pdf | - |
| Certificate issued by CA Form 1File: Annexure 59 Form 1 CA.pdf | - |
| Certificate issued by Architect Form 2File: Annexure 61 Form - 2 Architect .pdf | - |
| Certificate issued by Engineer Form 3File: Annexure 60 Form - 3 Engineer (PR).pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Annexure 49 No Litigation Affidavit.pdf | - |
| Balance Sheet 2024 - 2025File: HPPL Balance sheet 24-25.pdf | - |
| Balance Sheet 2023 - 2024File: Annexure 70 Balance sheet.pdf | - |
| Balance Sheet 2022 - 2023File: Annexure 70 Balance sheet.pdf | - |
| Audited Profit and Loss Statement 2024 - 2025File: HPPL P&L 24-25.pdf | - |
| Audited Profit and Loss Statement 2023 - 2024File: Annexure 71 P&L.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: Annexure 71 P&L.pdf | - |
| Income Tax Return Acknowledgement 2024 - 2025File: Annexure 72 ITR FY 24-25 HPPL.pdf | - |
| Income Tax Return Acknowledgement 2023 - 2024File: Annexure 72 ITR FY 23-24 HPPL.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: Annexure 72 ITR FY 2022-23 HPPL.pdf | - |
| Director's Report 2024 - 2025File: Annexure 73.pdf | - |
| Director's Report 2023 - 2024File: Annexure 73 HPPL Directors Report 23-24.pdf | - |
| Director's Report 2022 - 2023File: Annexure 73 HPPL Directors Report 22-23.pdf | - |
| Cash Flow Statement 2024 - 2025File: HPPL Cash Flow statement 24-25.pdf | - |
| Cash Flow Statement 2023 - 2024File: Annexure 74 Cash flow.pdf | - |
| Auditor's Report 2024 - 2025File: HPPL Signed FS.pdf | - |
| Auditor's Report 2023 - 2024File: Annexure 75 Auditor Report.pdf | - |
| Auditor's Report 2022 - 2023File: Annexure 75 Auditor Report.pdf | - |
| Annexure 80 Approval letter | - |
| Annexure 81 Building plan | - |
| Annexure 82 Bulding drawings | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Rural
Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.
Keep Century Bliss on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Rural650+ in Bengaluru Rural
Filed coordinates, straight-line distance. 12 registered projects within 2 km.
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
EMBASSY VERDE
EMBASSY DEVELOPMENTS LIMITED
Aeropolis, a project of Sattva Group
TRINAYANI REALTOR PRIVATE LIMITED
DS MAX SKY SHLOKAM
DS Max Properties Private Limited
EMBASSY SOUTH RESERVE
SUMMIT DEVELOPMENTS LIMITED
Bhartiya Garden Estate Phase-1
Bhartiya Urban Pvt Ltd
See every Bengaluru Rural project, with the district possession charts
Builder: Hebbal Properties Private Limited
Hebbal Properties Private Limited has 2 registrations on RERA Karnataka, including Century Bliss and Century Kindle Phase 1. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Rural district page.
Frequently asked questions
What are my rights if Century Bliss is delayed beyond 7 Apr 2031?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Century Bliss?
The registered promoter entity is Hebbal Properties Private Limited, a company as per the filing. Its CIN U70109KA2021PTC145179 and GSTIN 29AAFCH6957D1ZA can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Century Bliss?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Century Bliss?
The professionals named in the filing: Architect: Chandrashekar R; Engineer: Swaroop Devaiah KL; Chartered Accountant: Sugnana Kumar H. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Century Bliss?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback