Centropolis

By Skywards Ashtika Lifestyle

RG-MH-66808 · RERA P52100018529 · Last updated on MahaRERA portal: 28 Jan 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • 2 complaints at MahaRERA
  • Completion date moved by 73 months
  • 4 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Oct 2026Possession promisedmoved 73 months from the original
1 of 11Construction stages donefurthest along: Slabs of Super Structure, 85%
24 of 28Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 75 documents Report an error

Centropolis is a Commercial project by Skywards Ashtika Lifestyle in Pune, Maharashtra, registered with MahaRERA as P52100018529 on 12 Nov 2018. Possession is promised by 30 Oct 2026. The completion date has moved by 73 months from the original filing. 4 of the 28 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameCentropolis
  • TypeCommercial
  • Location
    • near Shivajinagar bus Stand
    • Shivaji nagar
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411005
  • Pincode411005
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100018529
  • ReraGenie IDRG-MH-66808

Builder

  • NameSkywards Ashtika Lifestyle
  • Entity typePartnership
  • PartnersAshwin Arun Adsul, Ashish Arun Adsul, Ratnamala Ratikant Galinde

Key dates

this monthRegisteredNov 2018First promiseSep 2020Revised toOct 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on12 Nov 2018
  • Promised completion30 Oct 2026
  • Revised completionRevised to 30 Oct 2026 (originally 30 Sep 2020)
  • Buildings1 building record
  • Documents filed75 files

Current status

14%4 of 28 units booked
50.0%Work done, per cost certificate

Figures as on 28 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CentropolisNA7502828

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 28 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 85%.

Centropolis: 62% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)0%
Plinth60%
Stilt Floor75%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 28 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed14

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots14
Closed/Covered13
Open Space1

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area805 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on28 Jan 2026
LandownerVillageDistrict
Mr Rajendra Shivajirao ShirolePune (M Corp.)Pune
Kalyani Kailas ShirolePune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPune Municipal corporation
Permissible FSI2397.63
Proposed, not sanctioned777 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMillenium star dhole patil road Pune 411001
Estimated costRs 12.00 cr
Cost incurredRs 6.00 cr
Work done50.0%
BuildingWingEstimatedIncurred
CentropolisNARs 12.00 crRs 6.00 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Jagadish Salunkhe
EngineerSUHAS SURVE
Chartered Accountantrushabh jain
Chartered AccountantRushabh R Jain
Chartered AccountantPramod B Shah
PartnerRole in project
Skywards Ashtika Lifestyle-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100012684Sep 2020 → Sep 2023

Reason as filed by the promoterconstruction work of the project is completed upto 70% , due to revised development rules of Sanctioning authority.we intend to purchase and upload TDR on said project. Therefore we processed for revised sanction from competent authority therefore we need extension of project .

EXT52100011045Sep 2020 → Sep 2022

Reason as filed by the promoterDue to Covid, the construction of the project has been severely affected. The Promoter has obtained 75% consent from allottees as required under Sec. 7 (3) of the RERA Act and undertakes to complete the construction within the said stipulated period. Hence it is, therefore, prayed extension may kindly be granted as proposed by the Promoter.

EXT52100008717Sep 2020 → Apr 2021

Reason as filed by the promoterdue to covide we coludent complet project within specified time

EXT52100017734Sep 2020 → Oct 2026

Reason as filed by the promoterDue to revised sanctioned plan received from Pune municipal corporation additional 1 Floor yet to be construct therefore required extension till 30th October 2026

Litigation declared2

CaseCourtStatus
1220/2010civil judge senior divisionhearing
1220/2010puneOngoing

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC005000000023333Mr. Milind Prabhakar BadeM/s. Skywards Ashtika Lifestyle Through its Partner Mr. Ashwin Arun Adsul,Mr. Ashish Arun Adsul16/08/2019
CC12600106Shantaram DawaneSkywards Ashtika Lifestyle07/01/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Oct 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Oct 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Sep 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Oct 2026

Documents filed75

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1_June 25.pdf28 Jan 2026
Withdrawal Update Form 1File: Form 1_June 25.pdf28 Jan 2026
Withdrawal Update Form 1File: Form 1_Sep 25.pdf28 Jan 2026
Withdrawal Update Form 1File: Form 1_Dec 25.pdf28 Jan 2026
Withdrawal Update Form 2File: Form 2_June 25.pdf28 Jan 2026
Withdrawal Update Form 2File: Form 2_June 25.pdf28 Jan 2026
Withdrawal Update Form 2File: Form 2_Sep 25.pdf28 Jan 2026
Withdrawal Update Form 2File: Form 2_Dec 25.pdf28 Jan 2026
Withdrawal Update Form 3File: Form 3_June 25.pdf28 Jan 2026
Withdrawal Update Form 3File: Form 3_June 25.pdf28 Jan 2026
Withdrawal Update Form 3File: Form 3_Sep 25.pdf28 Jan 2026
Withdrawal Update Form 3File: Form 3_Dec 25.pdf28 Jan 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 architect.pdf10 Jul 2025
CERSAI detailsFile: CERSAI_Search_Report_200362979343_For_Asset_Based_Search_10_07_2025_15_25_38_596.pdf10 Jul 2025
Other - FinanceFile: form b bank.pdf10 Jul 2025
Other - FinanceFile: format A skyward.pdf10 Jul 2025
Other - TechnicalFile: pert chart.pdf10 Jul 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure.pdf10 Jul 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2 (1).pdf10 Jul 2025
Certificates of CA (Form 3)File: march 2024.pdf11 Jun 2025
Certificates of CA (Form 3)File: jun 2024.pdf11 Jun 2025
Certificates of CA (Form 3)File: upto december.pdf11 Jun 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: march 2024.pdf11 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2centopolis.pdf28 Nov 2024
Declaration in FORM BFile: Ashwin Affidavit.pdf11 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer certificate.pdf11 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2a 2022.pdf11 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2a 2023.pdf11 Jul 2024
Deviation Report with respect to Allotment letterFile: devi allotment.pdf11 Jul 2024
Deviation Report with respect to model copy of AgreementFile: devi agreemtn.pdf11 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: engineer certificate.pdf10 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: annexuter form.pdf10 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 MARCH-21.pdf10 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: SKYWARD ASHTIKA LIFESTYLE FORM 5 (2) (4).pdf10 Jun 2024
CERSAI detailsFile: CERSAI centopolise.pdf20 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf12 Mar 2024
Disclosure of sold/ booked inventoryFile: book unsold 2024.pdf12 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5.pdf12 Mar 2024
Other - LegalFile: b form builder.pdf12 Mar 2024
Other - LegalFile: owner b form shirole.pdf12 Mar 2024
Declaration about Commencement CertificateFile: DECLARATION ABOUT.pdf11 Oct 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: sEPRATE aCCOUNT.pdf11 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: archirecht.pdf10 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2 a.pdf10 Oct 2023
Building plan approvalFile: plan 1 final.pdf28 Sep 2023
Building plan approvalFile: plan 1 final.pdf28 Sep 2023
Building plan approvalFile: plan 2.pdf28 Sep 2023
Building Plan Approval (IOD)File: plan 1 final.pdf28 Sep 2023
Building Plan Approval (IOD)File: plan 1 final.pdf28 Sep 2023
Building Plan Approval (IOD)File: plan 2.pdf28 Sep 2023
Commencement Certificates / NA Order for plotted developmentFile: cc.pdf28 Sep 2023
Declaration about Commencement CertificateFile: scan copy.PDF11 Nov 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form-2 Eng Certificate_compressed.pdf31 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: engineer certificate 19-20.pdf1 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: engineer certificate 20-21.pdf1 Sep 2021
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Booked Inventory.pdf1 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 CA 20-21.pdf1 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CA Form 5- 2019.pdf1 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 CA 20-21.pdf1 Sep 2021
Building plan approvalFile: Plan-2020_compressed.pdf6 Jan 2021
Building Plan Approval (IOD)File: Plan-2020_compressed.pdf6 Jan 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 Revised .pdf6 Jan 2021
Details of Restarting of Construction work post lockdownFile: covide work start.pdf6 Jan 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CERTIFICATE 03.pdf11 Oct 2019
Annual Audit Report of Statutory CA (Form 5)File: ca form 5.pdf11 Oct 2019
Building plan approvalFile: Plan 2018 (1).pdf31 Oct 2018
Layout approvalFile: Lay out plan.pdf31 Oct 2018
Copy of the legal title reportFile: titel.pdf31 Oct 2018
Details of encumbrancesFile: encum.pdf31 Oct 2018
Copy of Layout Approval (in case of layout)File: Lay out plan.pdf31 Oct 2018
Building Plan Approval (IOD)File: Plan 2018 (1).pdf31 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: cc (1).pdf31 Oct 2018
Declaration in FORM BFile: skyward.pdf31 Oct 2018
Certificates of CA (Form 3)File: ca.pdf31 Oct 2018
Proforma of Allotment letterFile: RERA DRAFT AGREEMENT Centropolis _1_.pdf31 Oct 2018

How this compares with Pune

14%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 73 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Centropolis on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Shivaji nagar13,700+ in Pune

Builder: Skywards Ashtika Lifestyle

Skywards Ashtika Lifestyle has 1 registration on MahaRERA, including Centropolis. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Centropolis is delayed beyond 30 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Centropolis?

The registered promoter entity is Skywards Ashtika Lifestyle, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Centropolis?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Centropolis?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Centropolis?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Centropolis?

The professionals named in the filing: Architect: Mr Jagadish Salunkhe; Engineer: SUHAS SURVE; Chartered Accountant: rushabh jain; Chartered Accountant: Rushabh R Jain; Chartered Accountant: Pramod B Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Centropolis?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Centropolis. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Centropolis to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.