Home / Browse projects / Nagpur, Maharashtra / CENTRAL PARK TOWER
CENTRAL PARK TOWER
By PARS URBAN SERVICE PROVIDERS &INFRASTRUCTURE DEVELOPMENT PRIVATE LIMITED
RG-MH-19256 · RERA P50500078338 · Last updated on MahaRERA portal: 27 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
CENTRAL PARK TOWER is a Residential / Group Housing project by PARS URBAN SERVICE PROVIDERS &INFRASTRUCTURE DEVELOPMENT PRIVATE LIMITED in Nagpur, Maharashtra, registered with MahaRERA as P50500078338 on 4 Dec 2024. Possession is promised by 30 Apr 2028. 0 of the 33 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.
At a glance
Project
- NameCENTRAL PARK TOWER
- TypeResidential / Group Housing
- Location
- FARMLAND LAYOUT
- RAMDASPETH BEHIND LOKMAT BHAVAN
- Nagpur (M Corp.)
- Nagpur (Urban)
- Nagpur
- 440012
- Pincode440012
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50500078338
- ReraGenie IDRG-MH-19256
Builder
- NamePARS URBAN SERVICE PROVIDERS &INFRASTRUCTURE DEVELOPMENT PRIVATE LIMITED
- Entity typeCompany
- DirectorsRahul Rajendra Deshmukh
- DirectorPraful Narendra Deshmukh
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on4 Dec 2024
- Promised completion30 Apr 2028
- Revised completionNone
- Buildings1 building record
- Documents filed59 files
Current status
Figures as on 27 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| CENTRAL PARK TOWER | NA | 17 | 15 | 33 | 0 | 33 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 27 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 90%.
CENTRAL PARK TOWER: 20% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 90% |
| Podiums (if any) | 0% |
| Plinth | 30% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 27 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed220
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership6
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| SHYAM JAGDALE | Nagpur (M Corp.) | Nagpur |
| CHANDRAKANT JAGDALE | Nagpur (M Corp.) | Nagpur |
| JYOTI HIWALE | Nagpur (M Corp.) | Nagpur |
| VARSHA JADHAV | Nagpur (M Corp.) | Nagpur |
| BHAVANA JAGDALE | Nagpur (M Corp.) | Nagpur |
| CHAITANYA JAGDALE | Nagpur (M Corp.) | Nagpur |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PRIYANKA SURESH KHANORKAR |
| Engineer | NIKHIL THAKRE |
| Engineer | Pranil Jachak |
| Chartered Accountant | KARTIK KEJDIWAL |
| Chartered Accountant | Jodh Joshi and Co. |
| Partner | Role in project |
|---|---|
| PARS URBAN SERVICE PROVIDERS &INFRASTRUCTURE DEVELOPMENT PRIVATE LIMITED | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 21 Oct 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Oct 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Nov 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Apr 2028
Documents filed59
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 Q4.pdf | 27 May 2026 |
| Form 2File: Form 2 31032026.pdf | 27 May 2026 |
| Form 3File: Form 3.pdf | 27 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold unsold inventory.pdf | 27 May 2026 |
| Self-declaration of Quarterly ProgressFile: QPR.pdf | 27 May 2026 |
| Form 1File: Form 1 Central Park Tower Rera.pdf | 30 Apr 2026 |
| Form 2File: Form 2.pdf | 30 Apr 2026 |
| Form 3File: Form 3 Final.pdf | 30 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold unsold inventory.pdf | 30 Apr 2026 |
| Self-declaration of Quarterly ProgressFile: QPR.pdf | 30 Apr 2026 |
| Form 1File: Form 1 30092025.pdf | 15 Jan 2026 |
| Form 2File: Form 2.pdf | 15 Jan 2026 |
| Form 3File: Form 3 30092025.pdf | 15 Jan 2026 |
| Self-declaration of Quarterly ProgressFile: Quarterly progress report.pdf | 15 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSER OF SOLD AND BOOKED INVENTORY.pdf | 15 Jan 2026 |
| Form 5 (FY 2024-2025)File: Form 5 30092025.pdf | 28 Nov 2025 |
| Commencement certificateFile: Building Permission and Commencement Certificate CPT 2.pdf | 15 Jul 2025 |
| Declaration and undertaking (Annexure A)File: Declaration cum Undertaking on Letter Head_Annexure A.pdf | 15 Jul 2025 |
| Form 1File: Form 1 311224.pdf | 12 Jun 2025 |
| Form 2File: Form 2 311224.pdf | 12 Jun 2025 |
| Form 3File: FORM 3 Signed 31122024 Original.pdf | 12 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: 31122024 DISCOLSURE OF SOLD BOOKED INVENTORY_compressed.pdf | 12 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: 31122024 QUARTERLY PROGRESS REPORT (QPR2)_compressed.pdf | 12 Jun 2025 |
| Form 1File: Form 1 310325.pdf | 12 Jun 2025 |
| Form 2File: Form 2 310325.pdf | 12 Jun 2025 |
| Form 3File: form 3 31032025 SCANNED.pdf | 12 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: 31032025 DISCOLSURE OF SOLD BOOKED INVENTORY_compressed.pdf | 12 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: 31032025 QUARTERLY PROGRESS REPORT (QPR2)_compressed.pdf | 12 Jun 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 31032025.pdf | 30 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Signed 31122024.pdf | 29 Mar 2025 |
| Building plan approvalFile: CPT RERA SANCTION_compressed.pdf | 28 Nov 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: CPT RERA SANCTION_compressed.pdf | 28 Nov 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: PARS Format A 261124.pdf | 26 Nov 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Undertaking by Designated Promoter and Landowner.pdf | 26 Nov 2024 |
| Other - FinanceFile: Undertaking by Designated Promoter and Landowner.pdf | 26 Nov 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf | 26 Nov 2024 |
| Other - FinanceFile: Email from NMC.pdf | 21 Nov 2024 |
| CERSAI detailsFile: CERSAI Undertaking.pdf | 19 Nov 2024 |
| Proforma of Allotment letterFile: Proforma of Allotment Letter.pdf | 16 Nov 2024 |
| Proforma of Agreement for saleFile: Proforma of Agreement of Sale.pdf | 16 Nov 2024 |
| Deviation Report with respect to Allotment letterFile: Deviation Report in Allotment Letter merged.pdf | 13 Nov 2024 |
| Deviation Report with respect to model copy of AgreementFile: Deviation report in Agreement to Sale merged.pdf | 13 Nov 2024 |
| Details of encumbrances concerned to FinanceFile: Legal and Finance Encumbrance certificate.pdf | 6 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 6 Nov 2024 |
| Details of encumbrances concerned to LegalFile: Legal and Finance Encumbrance certificate.pdf | 6 Nov 2024 |
| Layout approvalFile: SANCTIONED DRAWING CPT1-compressed.pdf | 31 Oct 2024 |
| Copy of Layout Approval (in case of layout)File: SANCTIONED DRAWING CPT1-compressed.pdf | 31 Oct 2024 |
| Other - LegalFile: Deed of Declaration_compressed.pdf | 31 Oct 2024 |
| Declaration about Commencement CertificateFile: Declaration about Commencement certificate Format D.pdf | 31 Oct 2024 |
| Other - FinanceFile: Agreement of Development_.pdf | 31 Oct 2024 |
| Other - TechnicalFile: Declaration cum Undertaking on Letter Head.pdf | 31 Oct 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 11zon_merged-PDF.pdf | 31 Oct 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for Unsecured Loan.pdf | 31 Oct 2024 |
| PAN CardFile: PAN of PARS USPID Pvt Ltd.pdf | 21 Oct 2024 |
| Copy of the legal title reportFile: Legal Title Report_compressed.pdf | 21 Oct 2024 |
| Declaration in FORM BFile: Declaration in FORM B Notarised.pdf | 21 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 21 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 21 Oct 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Building Permission and Commencement Certificate CPT 2.pdf | 19 Oct 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 59 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep CENTRAL PARK TOWER on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near RAMDASPETH BEHIND LOKMAT BHAVAN2,800+ in Nagpur
Filed coordinates, straight-line distance. 140 registered projects within 2 km.
NEXUS
TIWARI GROUP
VEDANSH NAGRI
DEEPAK MADHAVRAO NILAWAR
Orange City Diamond
VISHAL PREMDAS BAWISTALE
DEV DATTA HEIGHTS
CONCRETE DEVELOPERS
JASMEETSINGH BHATIA/MANDEEPSINGH BHATIA
JASMEETSINGH AMARJEETSINGH BHATIA
Pooja Apartment
Pooja Constructions
See every Nagpur project, with the district possession charts
Builder: PARS URBAN SERVICE PROVIDERS &INFRASTRUCTURE DEVELOPMENT PRIVATE LIMITED
PARS URBAN SERVICE PROVIDERS &INFRASTRUCTURE DEVELOPMENT PRIVATE LIMITED has 1 registration on MahaRERA, including CENTRAL PARK TOWER. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What are my rights if CENTRAL PARK TOWER is delayed beyond 30 Apr 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of CENTRAL PARK TOWER?
The registered promoter entity is PARS URBAN SERVICE PROVIDERS &INFRASTRUCTURE DEVELOPMENT PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in CENTRAL PARK TOWER?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for CENTRAL PARK TOWER?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at CENTRAL PARK TOWER?
The professionals named in the filing: Architect: PRIYANKA SURESH KHANORKAR; Engineer: NIKHIL THAKRE; Engineer: Pranil Jachak; Chartered Accountant: KARTIK KEJDIWAL; Chartered Accountant: Jodh Joshi and Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in CENTRAL PARK TOWER?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback