Home / Browse projects / Thane, Maharashtra / CENTONIC
CENTONIC
RG-MH-46318 · RERA P51700046286 · Last updated on MahaRERA portal: 12 Jun 2026
Source: official MahaRERA filing
Red flags
- Litigation declared, 3 cases
- Rs 140.00 crore secured on the land, in favour of State Bank of India
- The declared charge does not appear in the CERSAI report on the filing
Clear
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 1 earlier projects delivered on promise
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
CENTONIC is a Commercial project by METRO LIFESCAPES INDIA LLP in Thane, Maharashtra, registered with MahaRERA as P51700046286 on 20 Jun 2022. The registration is recorded completed; possession was promised by 30 Jun 2027. 100 of the 228 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.
At a glance
Project
- NameCENTONIC
- TypeCommercial
- Location
- Sector 19 D
- Vashi
- Navi Mumbai (M Corp.)
- Thane
- 400703
- Pincode400703
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700046286
- ReraGenie IDRG-MH-46318
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on20 Jun 2022
- Promised completion30 Jun 2027
- Revised completionNone
- Buildings1 building record
- Documents filed198 files
Current status
Figures as on 12 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| CENTONIC | NA | 29 | 22 | 0 | 228 | 228 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 12 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
CENTONIC: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 12 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed694
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| City Center Vashi Mall Management LTD | Navi Mumbai (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| CENTONIC | NA | Rs 78.45 cr | Rs 78.45 cr |
| - | NA | Rs 12.70 cr | Rs 12.70 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DIMENSIONS ARCHITECTS PVT LTD |
| Engineer | Sandeep Rane |
| Engineer | Somnath Kale |
| Engineer | SOMNATH DHANAJI KALE |
| Chartered Accountant | BHASIN HOTA & CO |
| Chartered Accountant | P. N. SUBRAMANIAN & CO. |
| Partner | Role in project |
|---|---|
| METRO LIFESCAPES INDIA LLP | - |
Litigation declared3
| Case | Court | Status |
|---|---|---|
| 207/2019 | Civil Court Senior Division Thane | Disposed |
| 23/2021 | Civil Court Senior Division Thane | Disposed |
| 26/2017 | Mumbai DRT I | Disposed |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 13 Sep 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 23 May 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Jan 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed198
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 198 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2025-2026)File: Q4 FORM 5 31032026 CENTONIC.pdf | 12 Jun 2026 |
| Withdrawal Update Form 1File: Form 4 Architect Certificate.pdf | 8 May 2026 |
| Withdrawal Update Form 2File: Q4 FORM 2 31032026 CENTONIC.pdf | 8 May 2026 |
| Withdrawal Update Form 3File: Q4 FORM 3 31032026 CENTONIC.pdf | 8 May 2026 |
| Occupational CertificateFile: Centonic Part OC 11032024.pdf | 8 May 2026 |
| Occupational CertificateFile: Centonic Part OC 29092025.pdf | 8 May 2026 |
| Occupational CertificateFile: Part OC 11032024.pdf | 8 May 2026 |
| Occupational CertificateFile: Part OC 29092025.pdf | 8 May 2026 |
| Occupational CertificateFile: Full OC 27022026.pdf | 8 May 2026 |
| Occupational CertificateFile: Part OC Drawing 11032024.pdf | 8 May 2026 |
| Occupational CertificateFile: Part OC Drawing 29092025.pdf | 8 May 2026 |
| Occupational CertificateFile: Full OC Drawing 27022026.pdf | 8 May 2026 |
| Occupational CertificateFile: Mail from ADTP Part OC.pdf | 8 May 2026 |
| Occupational CertificateFile: Mail from ADTP Full OC.pdf | 8 May 2026 |
| Withdrawal Update Form 1File: Q2 FORM 1 30092025 CENTONIC.pdf | 16 Feb 2026 |
| Withdrawal Update Form 1File: Form 4 Architect Certificate.pdf | 16 Feb 2026 |
| Withdrawal Update Form 2File: Q3 FORM 2 31122025 CENTONIC.pdf | 16 Feb 2026 |
| Withdrawal Update Form 2File: Q3 FORM 2 31122025 CENTONIC.pdf | 16 Feb 2026 |
| Withdrawal Update Form 3File: Q3 FORM 3 31122025 CENTONIC.pdf | 16 Feb 2026 |
| Withdrawal Update Form 3File: Q3 FORM 3 31122025 CENTONIC.pdf | 16 Feb 2026 |
| Withdrawal Update Form 1File: Q2 FORM 1 30092025 CENTONIC.pdf | 20 Jan 2026 |
| Withdrawal Update Form 2File: Q2 FORM 2 30092025 CENTONIC.pdf | 20 Jan 2026 |
| Withdrawal Update Form 3File: Q2 FORM 3 30092025 CENTONIC.pdf | 20 Jan 2026 |
| Form 5 (FY 2022-2023)File: Q4 FORM 5 31032023 CENTONIC.pdf | 31 Oct 2025 |
| Form 5 (FY 2023-2024)File: Q4 FORM 5 31032024 CENTONIC.pdf | 31 Oct 2025 |
| Form 5 (FY 2024-2025)File: Form 5 Centonic FY 2024-25.pdf | 30 Oct 2025 |
| Withdrawal Update Form 1File: FORM 1 CENTONIC 300624.pdf | 10 Sep 2025 |
| Withdrawal Update Form 1File: FORM 1 CENTONIC 300624.pdf | 10 Sep 2025 |
| Withdrawal Update Form 2File: Q1 FORM 2 30062025 CENTONIC.pdf | 10 Sep 2025 |
| Withdrawal Update Form 2File: Q1 FORM 2 30062025 CENTONIC.pdf | 10 Sep 2025 |
| Withdrawal Update Form 3File: Q1 FORM 3 30062025 CENTONIC.pdf | 10 Sep 2025 |
| Withdrawal Update Form 3File: Q1 FORM 3 30062025 CENTONIC.pdf | 10 Sep 2025 |
| Form 1File: Q1 FORM 1 30062024 CENTONIC.pdf | 4 Jul 2025 |
| Form 2File: Q1 FORM 2 30062024 CENTONIC.pdf | 4 Jul 2025 |
| Form 3File: Q1 FORM 3 30062024 CENTONIC.pdf | 4 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Q1 DOS 30062024 CENTONIC.pdf | 4 Jul 2025 |
| Form 1File: Q2 FORM 1 30092024 CENTONIC.pdf | 4 Jul 2025 |
| Form 2File: Q2 FORM 2 30092024 CENTONIC.pdf | 4 Jul 2025 |
| Form 3File: Q2 FORM 3 30092024 CENTONIC.pdf | 4 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Q2 DOS 30092024 CENTONIC.pdf | 4 Jul 2025 |
| Form 1File: Q3 FORM 1 31122024 CENTONIC.pdf | 4 Jul 2025 |
| Form 2File: Q3 FORM 2 31122024 CENTONIC.pdf | 4 Jul 2025 |
| Form 3File: Q3 FORM 3 31122024 CENTONIC.pdf | 4 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Q3 DOS 31122024 CENTONIC.pdf | 4 Jul 2025 |
| Form 1File: Q4 FORM 1 31032025 CENTONIC.pdf | 4 Jul 2025 |
| Form 2File: Q4 FORM 2 31032025 CENTONIC.pdf | 4 Jul 2025 |
| Form 3File: Q4 FORM 3 31032025 CENTONIC.pdf | 4 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Q4 DOS 31032025 CENTONIC.pdf | 4 Jul 2025 |
| Form 1File: Q2 FORM 1 30092023 CENTONIC.pdf | 4 Jul 2025 |
| Form 2File: Q2 FORM 2 30092023 CENTONIC.pdf | 4 Jul 2025 |
| Form 3File: Q2 FORM 3 30092023 CENTONIC.pdf | 4 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Q2 DOS 30092023 CENTONIC.pdf | 4 Jul 2025 |
| Form 1File: Q3 FORM 1 31122023 CENTONIC.pdf | 4 Jul 2025 |
| Form 2File: Q3 FORM 2 31122023 CENTONIC.pdf | 4 Jul 2025 |
| Form 3File: Q3 FORM 3 31122023 CENTONIC.pdf | 4 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Q3 DOS 31122023 CENTONIC.pdf | 4 Jul 2025 |
| Form 1File: Q4 FORM 1 31032024 CENTONIC.pdf | 4 Jul 2025 |
| Form 2File: Q4 FORM 2 31032024 CENTONIC.pdf | 4 Jul 2025 |
| Form 3File: Q4 FORM 3 31032024 CENTONIC.pdf | 4 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Q4 DOS 31032024 CENTONIC.pdf | 4 Jul 2025 |
| Form 1File: Q1 FORM 1 30062023 CENTONIC.pdf | 4 Jul 2025 |
| Form 2File: Q1 FORM 2 30062023 CENTONIC.pdf | 4 Jul 2025 |
| Form 3File: Q1 FORM 3 30062023 CENTONIC.pdf | 4 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Q1 DOS 30062023 CENTONIC.pdf | 4 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q4 FORM 1 31032025 CENTONIC.pdf | 11 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Q4 SOLD BOOKED 31032025 CENTONIC.pdf | 11 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CENTONIC 31122024.pdf | 25 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 CENTONIC 31122024.pdf | 25 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 jul 22 sep 22.pdf | 22 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 JAN 23 MAR 23.pdf | 22 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 centonic 2022.pdf | 22 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 CENTONIC 30092022.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CENTONIC FORM 1 31122024.pdf | 18 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CENTONIC FORM 1 06102022.pdf | 18 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: MLILLP C WING Disclosure 31122024.pdf | 13 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: MLILLP C WING Disclosure 31122024 O.pdf | 13 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CENTONIC FORM 3 30092024 RUL.pdf | 7 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 CENTONIC 30092024.pdf | 4 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CENTONIC 30092024.pdf | 3 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Centonic 300924.pdf | 22 Oct 2024 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Swiss BoulevardP51700000636 | Chembur, Mumbai Suburban | Jul 2017 | Completed | Mar 2022 | Mar 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 198 filed documents as one ZIP, foldered, with a manifest
Keep CENTONIC on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Vashi7,600+ in Thane
Filed coordinates, straight-line distance. 61 registered projects within 2 km.
Plot No -1A,Sector -19, Vashi Truck Terminal
CITY AND INDUSTRIAL DEVELOPMENT CORPORATIO
KAMDHENU SHARAYU
Arpee Consultants LLP
Kamdhenu Synergy Square
Krsna Dynasty
10 Marina Bay
EV HOMES CONSTRUCTIONS PVT LTD
Goodwill Bizhub
M/s. Goodwill Dwellings LLP
ARIHANT ALEENTA
ARIHANT ESTATES
See every Thane project, with the district possession charts
Builder: METRO LIFESCAPES INDIA LLP
METRO LIFESCAPES INDIA LLP has 2 registrations on MahaRERA, including CENTONIC and AYKON. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if CENTONIC is delayed beyond 30 Jun 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of CENTONIC?
The registered promoter entity is METRO LIFESCAPES INDIA LLP, a partnership as per the filing. Its GSTIN 27ABOFM9037G1ZT can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in CENTONIC?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for CENTONIC?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at CENTONIC?
The professionals named in the filing: Architect: DIMENSIONS ARCHITECTS PVT LTD; Engineer: Sandeep Rane; Engineer: Somnath Kale; Engineer: SOMNATH DHANAJI KALE; Chartered Accountant: BHASIN HOTA & CO; Chartered Accountant: P. N. SUBRAMANIAN & CO.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in CENTONIC?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback