Home / Browse projects / Raigarh, Maharashtra / CELESTE VILLAS

Registered No litigation declared Residential / Group Housing project

CELESTE VILLAS

By BUILD MARQUE REALTY LLP

RG-MH-37601 · RERA P52000050001 · Last updated on MahaRERA portal: 29 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 26 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 26 months from the original
43 of 176Construction stages doneacross 16 buildings; furthest along: Internal walls, 90%
14 of 16Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 75 documents Report an error

CELESTE VILLAS is a Residential / Group Housing project by BUILD MARQUE REALTY LLP in Raigarh, Maharashtra, registered with MahaRERA as P52000050001 on 6 Mar 2023. Possession is promised by 31 Dec 2027. The completion date has moved by 26 months from the original filing. 2 of the 16 units on this registration are recorded sold or booked, and 43 of 176 construction stages are filed complete.

At a glance

Project

  • NameCELESTE VILLAS
  • TypeResidential / Group Housing
  • Location
    • SURVEY NO 80
    • H NO 3
    • Kothimbe
    • Karjat
    • Raigarh
    • 410201
  • Pincode410201
  • RERA no.P52000050001
  • ReraGenie IDRG-MH-37601

Builder

  • NameBUILD MARQUE REALTY LLP
  • Entity typePartnership
  • PartnersSHAHAB SAAQIB ALTAF ANDRABI SYED, ZAIN ALTAF ANDRABI SAYED, ZAHEER ABBAS, WASIM AHMED SIDDIQUI, FAZAL AHMED SHAIKH, ISTYAK AHMED NABI SHAH

Key dates

this monthRegisteredMar 2023First promiseOct 2025Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on6 Mar 2023
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Oct 2025)
  • Buildings16 building records
  • Documents filed75 files

Current status

12%2 of 16 units booked
45.1%Work done, per cost certificate

Figures as on 29 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TYPE A-1NA21101
TYPE A-2NA21101
TYPE B-1NA21101
TYPE B-2NA21101
TYPE B-3NA21101
TYPE B-4NA21101
TYPE B-5NA21101
TYPE B-6NA21101
TYPE B-7NA21101
TYPE B-8NA21101
TYPE B-9NA21101
TYPE B-10NA21101
TYPE B-11NA21101
TYPE C-1NA21101
TYPE D-1NA21101
TYPE E-1NA21101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building16

As on 29 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

43 of 176 construction stages are filed complete across 16 buildings. The stage furthest along is Internal walls, at 90%.

TYPE A-1100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TYPE A-2100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TYPE B-179%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
TYPE B-227%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor50%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TYPE B-35%
ActivityProgress
Excavation50%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TYPE B-45%
ActivityProgress
Excavation50%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TYPE B-55%
ActivityProgress
Excavation50%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TYPE B-65%
ActivityProgress
Excavation50%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TYPE B-75%
ActivityProgress
Excavation50%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TYPE B-818%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TYPE B-918%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TYPE B-1082%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TYPE B-115%
ActivityProgress
Excavation50%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TYPE C-15%
ActivityProgress
Excavation50%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TYPE D-15%
ActivityProgress
Excavation50%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TYPE E-15%
ActivityProgress
Excavation50%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes35%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes30%
Storm Water DrainsYes30%
Landscaping & Tree PlantingYes30%
Street LightingYes40%
Community BuildingsYes50%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes30%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes20%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,400 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityRaigad - Alibaug
Permissible FSI1959.7
Proposed, not sanctioned1,960 sq m
Buildings approved16
Buildings sanctioned16

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMIRA ROAD - 401107
Estimated costRs 18.66 cr
Cost incurredRs 8.42 cr
Work done45.15%
BuildingWingEstimatedIncurred
-NARs 8.11 crRs 4.86 cr
TYPE C-1NARs 70.00 lakh-
TYPE D-1NARs 70.00 lakh-
TYPE E-1NARs 70.00 lakh-
TYPE A-1NARs 65.00 lakhRs 65.00 lakh
TYPE A-2NARs 65.00 lakhRs 65.00 lakh
TYPE B-1NARs 65.00 lakhRs 62.00 lakh
TYPE B-2NARs 65.00 lakhRs 20.00 lakh
TYPE B-3NARs 65.00 lakhRs 6.50 lakh
TYPE B-4NARs 65.00 lakhRs 6.50 lakh
TYPE B-5NARs 65.00 lakhRs 6.50 lakh
TYPE B-6NARs 65.00 lakhRs 6.50 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANUP SURESH SALVI
EngineerSHREESHAIL GAIKWAD
Chartered AccountantGANESH KRISHNA BHOIR
Chartered AccountantArsalaan Shaikh
PartnerRole in project
BUILD MARQUE REALTY LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA09102518074Oct 2025 → Dec 2027

Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has primarily occurred due to low sales, as the project is a bungalow project, which has impacted on the cash flow and slowed down the pace of execution. Despite this challenge, we are making continuous efforts to stabilize the project and complete the remaining work. Given the circumstances, we kindly request an extension until 31-12-2027 to complete the project and fulfil all regulatory requirements.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Feb 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Nov 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Nov 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed75

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 March 2026.pdf29 May 2026
Withdrawal Update Form 2File: Form 2 March 2026.pdf29 May 2026
Withdrawal Update Form 3File: Form 3 March 2026.pdf29 May 2026
Withdrawal Update Form 1File: Form 1 Jan 26 signed (1).pdf20 Feb 2026
Withdrawal Update Form 2File: Form 2 Jan 26 (1).pdf20 Feb 2026
Withdrawal Update Form 3File: Form 3 Jan 26 (1).pdf20 Feb 2026
Withdrawal Update Form 1File: Withdrawal Application Form1.pdf8 Oct 2025
Withdrawal Update Form 1File: Withdrawal Application Form1.pdf8 Oct 2025
Withdrawal Update Form 2File: Annexure B Form 2.pdf8 Oct 2025
Withdrawal Update Form 2File: Annexure B Form 2.pdf8 Oct 2025
Withdrawal Update Form 3File: BMR CA Certificate form 3 q3.pdf8 Oct 2025
Withdrawal Update Form 3File: BMR CA Certificate form 3 q3.pdf8 Oct 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Build Marque form 1 Quarter 1 2025.pdf22 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate.pdf22 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 BUILD MARQUE 4 QUARTER-compressed.pdf9 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: July To Sept 2024.pdf9 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Oct To Dec 2024.pdf9 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: NEW DOC 02-14-2025.pdf9 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Build Marque 3 Quarter 2024.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 QPR3 Sep24_compressed.pdf18 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A (Engineer's Certificate on Quality Assurance Submitted Annually).pdf2 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5.pdf2 May 2024
Disclosure of sold/ booked inventoryFile: bmr.pdf25 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate Q1.pdf23 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate Q1.pdf23 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Chartered Accountants Q1_11zon.pdf23 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 (ARTITECT'S CERTIFICATE Q2).pdf14 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 (ARTITECT'S CERTIFICATE Q3).pdf14 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 (ARTITECT'S CERTIFICATE Q4).pdf14 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 (ENGINEER CERTIFICATE Q2).pdf14 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 (ENGINEER CERTIFICATE Q3).pdf14 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 (ENGINEER CERTIFICATE Q4).pdf14 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q2.pdf14 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q3_11zon.pdf14 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q4.pdf14 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022-23.pdf14 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form - 1 Architect Certificate.pdf26 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 - Build Marque Reality.pdf26 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3.pdf26 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5.pdf26 Jan 2024
Copy of the legal title reportFile: Legal Title Report.pdf23 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 NEW COMPRESS.pdf23 Feb 2023
Proforma of Agreement for saleFile: New Draft Agreement For Sale.pdf23 Feb 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report in Agreement for sale.pdf16 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: FAZAL AHMED SHAIKH-1.pdf20 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: ISTYAK AHMED NABI SHAH-1.pdf20 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: SHAHAB SAAQIB ALTAF ANDRABI SYED.pdf20 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: SIDDIQUI WASIM AHMED-1.pdf20 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: ZAHEER ABBAS-1.pdf20 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: ZAIN ALTAF SYED-1.pdf20 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: ZEESHAN MANZOOR KHAN-1.pdf20 Jan 2023
Details of encumbrances concerned to FinanceFile: No encumbrance certificate.pdf5 Dec 2022
Details of encumbrances concerned to FinanceFile: No encumbrance certificate.pdf5 Dec 2022
Details of encumbrances concerned to LegalFile: No encumbrance certificate.pdf5 Dec 2022
Details of encumbrances concerned to LegalFile: No encumbrance certificate.pdf5 Dec 2022
CERSAI detailsFile: Undertaking regarding no security interest.pdf29 Nov 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Separate Bank Account.pdf29 Nov 2022
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf21 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate Kothimbe.pdf21 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 RERA Engineer Certificate.pdf21 Nov 2022
Proforma of Allotment letterFile: BMR Allotment Letter Form.pdf21 Nov 2022
Deviation Report with respect to Allotment letterFile: Deviation report with respect to allotment letter.pdf21 Nov 2022
Layout approvalFile: 05 Layout Approval.pdf17 Nov 2022
Building plan approvalFile: 06 NA ORDER.pdf17 Nov 2022
PAN CardFile: 01 Pan Card Build Marque Reality.pdf17 Nov 2022
Copy of Layout Approval (in case of layout)File: 05 Layout Approval.pdf17 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: 06 NA ORDER.pdf17 Nov 2022
Commencement Certificates / NA Order for plotted developmentFile: 06 NA ORDER.pdf17 Nov 2022
Declaration in FORM BFile: FORM B FAZAL AHMED SHAIKH.pdf17 Nov 2022
Declaration in FORM BFile: FORM B ISTYAK AHMED NABI SHAH.pdf17 Nov 2022
Declaration in FORM BFile: FORM B SHAHAB SAAQIB ALTAF ANDRABI SYED.pdf17 Nov 2022
Declaration in FORM BFile: FORM B SIDDIQUI WASIM AHMED.pdf17 Nov 2022
Declaration in FORM BFile: FORM B ZAHEER ABBAS.pdf17 Nov 2022
Declaration in FORM BFile: FORM B ZAIN ALTAF SYED.pdf17 Nov 2022
Declaration in FORM BFile: FORM B ZEESHAN MANZOOR KHAN.pdf17 Nov 2022

How this compares with Raigarh

12%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 26 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CELESTE VILLAS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near H NO 35,900+ in Raigarh

Builder: BUILD MARQUE REALTY LLP

BUILD MARQUE REALTY LLP has 1 registration on MahaRERA, including CELESTE VILLAS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if CELESTE VILLAS is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CELESTE VILLAS?

The registered promoter entity is BUILD MARQUE REALTY LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CELESTE VILLAS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for CELESTE VILLAS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CELESTE VILLAS?

The professionals named in the filing: Architect: ANUP SURESH SALVI; Engineer: SHREESHAIL GAIKWAD; Chartered Accountant: GANESH KRISHNA BHOIR; Chartered Accountant: Arsalaan Shaikh. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CELESTE VILLAS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CELESTE VILLAS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CELESTE VILLAS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.