Home / Browse projects / Raigarh, Maharashtra / CASA UNICO PHASE - 1

Registered No litigation declared Residential / Group Housing project

CASA UNICO PHASE - 1

By Landmark Real Estate Developers Limited

RG-MH-74669 · RERA P52000007113 · Last updated on MahaRERA portal: 26 May 2026

Source: official MahaRERA filing

Red flags

  • 12 complaints at MahaRERA
  • Completion date moved by 60 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 60 months from the original
51 of 110Construction stages doneacross 10 buildings; furthest along: External plumbing and external plaster, 97%
13 of 216Units unsoldnot recorded sold or booked
12Complaints at MahaRERAon this registration
Jump to the 186 documents Report an error

CASA UNICO PHASE - 1 is a Residential / Group Housing project by Landmark Real Estate Developers Limited in Raigarh, Maharashtra, registered with MahaRERA as P52000007113 on 17 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 60 months from the original filing. 203 of the 216 units on this registration are recorded sold or booked, and 51 of 110 construction stages are filed complete. 12 complaints are on record with the regulator.

At a glance

Project

  • NameCASA UNICO PHASE - 1
  • TypeResidential / Group Housing
  • Location
    • Karjat Neral Road
    • Karjat
    • Ashane
    • Raigarh
    • 410201
  • Pincode410201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000007113
  • ReraGenie IDRG-MH-74669

Builder

  • NameLandmark Real Estate Developers Limited
  • Entity typeCompany
  • DirectorsAugustine Socorro Fernandes, Arun Narahari Sawant
  • Managing DirectorShehzad Valimohamed Merchant

Key dates

this monthRegisteredAug 2017First promiseDec 2021Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2021)
  • Buildings10 building records
  • Documents filed186 files

Current status

94%203 of 216 units booked
83.6%Work done, per cost certificate

Figures as on 26 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ADONIA-1NA6032032
ADONIA-2NA6632032
ADONIA-3NA6632032
ADONIA-4NA6632032
GRANDE-1NA54606
GRANDE-2NA54606
GRANDE-3NA54606
GRANDE-4NA54606
STELLA-1NA5440040
STELLA-3NA5424024

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building10

As on 26 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

51 of 110 construction stages are filed complete across 10 buildings. The stage furthest along is External plumbing and external plaster, at 97%.

ADONIA-182%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
ADONIA-281%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.97%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
ADONIA-365%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor75%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ADONIA-467%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
GRANDE-148%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor60%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks35%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
GRANDE-247%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor70%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
GRANDE-347%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor75%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
GRANDE-488%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%
STELLA-189%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor95%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
STELLA-310%
ActivityProgress
Excavation100%
Basement (if any)10%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 26 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes45%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes70%
Landscaping & Tree PlantingYes55%
Street LightingYes30%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes10%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed187

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots187
Closed/Covered120
Open Space67
BuildingClosed/CoveredOpen SpaceTotal
ADONIA-1242044
ADONIA-224933
ADONIA-3241842
ADONIA-4242044
GRANDE-1606
GRANDE-2606
GRANDE-3606
GRANDE-4606

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area33,529 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on24 Jul 2025

Approvals and building plan

Sanctioning authorityTown Planning Department Alibaug
Permissible FSI11870.0
Proposed, not sanctioned11,870 sq m
Buildings approved10
Buildings sanctioned10

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchFree Press House Nariman Point Mumbai 400021
Estimated costRs 46.84 cr
Cost incurredRs 39.17 cr
Work done83.62%
BuildingWingEstimatedIncurred
-NARs 15.50 crRs 13.18 cr
STELLA-1NARs 4.50 crRs 4.50 cr
ADONIA-1NARs 4.36 crRs 4.36 cr
ADONIA-2NARs 4.36 crRs 4.19 cr
ADONIA-3NARs 4.36 crRs 3.71 cr
ADONIA-4NARs 4.36 crRs 3.92 cr
STELLA-3NARs 3.15 crRs 15.75 lakh
GRANDE-1NARs 1.56 crRs 1.25 cr
GRANDE-2NARs 1.56 crRs 1.17 cr
GRANDE-3NARs 1.56 crRs 1.17 cr
GRANDE-4NARs 1.56 crRs 1.56 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGA DESIGN
ArchitectSHREE VASTU SANKALPA CONSULTANCY
EngineerINTEGRATED BUILDING SERVICES
Chartered AccountantKeyur Bhayani
Chartered AccountantCA SHRADDHA PARANJAPE
PartnerRole in project
Landmark Real Estate Developers Limited-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000013428Dec 2021 → Dec 2023

Reason as filed by the promotervi. Various reasons for the project to be stalled and delay in completion of the development works: a. Stop work notice issued by the (Revenue and Forest Department), District Collector and District Magistrate, Raigad - Alibuag, dated 02.08.2018, due to which the actual work could not be carried on as per the sanctioned plan resulting in delay for a period of (5) Five months. Also, post the said stop work notice was lifted on 12/12/2018, the migratory labourers were not available at the site of the Builder / Promoter/ Developer for a quick kick start resulting in further delay of another (4) F

EXT52000011217Dec 2021 → Dec 2022

Reason as filed by the promoter1.) Stop work notice issued by the (Revenue and Forest Department), District Collector and District Magistrate, Raigad - Alibuag, dated 02.08.2018, due to which the actual work could not be carried on as per the sanctioned plan resulting in delay for a period of (5) Five months. 2. )Also, post the said stop work notice was lifted on 12/12/2018, the migratory labourers were not available at the site of the Builder / Promoter/ Developer for a quick kick start resulting in further delay of another (4) Four months; 3.) Due to the pre-pandemic situation Covid Phase - I and strict Lockdown situation

EXT52000018590Dec 2021 → Dec 2025

Reason as filed by the promoterVarious reasons for the project to be stalled and delay in completion of the development works: a. Stop work notice issued by the (Revenue and Forest Department), District Collector and District Magistrate, Raigad - Alibuag, dated 02.08.2018, due to which the actual work could not be carried on as per the sanctioned plan resulting in delay for a period of (5) Five months. Also, post the said stop work notice was lifted on 12/12/2018, the migratory labourers were not available at the site of the Builder / Promoter/ Developer for a quick kick start resulting in further delay of another (4) Four

EA22122518917Dec 2021 → Dec 2026

Reason as filed by the promoterThe COVID-19 pandemic has had a profound and far-reaching impact on the construction industry, both locally and globally. As a direct consequence of the pandemic, there has been a significant and sustained increase in the prices of essential construction materials, including but not limited to cement, steel, copper, electrical components, plumbing materials, and paints. This escalation in material costs has resulted in severe financial strain, disrupting the supply chain and leading to delays in procurement and delivery of these materials to the project site. In particular, the delivery timeli

Litigation declared3

CaseCourtStatus
89/2009CIVIL JUDGE SENIOR DIVISION AT PANVEL CIVIL COURTPROMOTER NOT PARTY IN THE SUIT ONLY PART OF ENTIRE PROPERTY IS SUBJECT MATTER INJUNCTION REFUSED
91/2009CIVIL JUDGE SENIOR DIVISION AT PANVEL CIVIL COURTPROMOTER NOT PARTY IN THE SUIT ONLY PART OF ENTIRE PROPERTY IS SUBJECT MATTER INJUNCTION REFUSED
115/2012CIVIL JUDGE JUNIOR DIVISION AT KARJATWRIT PETITION PENDING IN BOMBAY HIGH COURT AGAINST THE SUIT PENDING IN CIVIL COURT JUNIOR DIVISION A

Complaints filed with MahaRERA12

Case no.ComplainantRespondentFiled
CC006000000001039ABBAS SYED ZULFIQUARValimohamed merchant and shehzad valimohamed merchant through landmark real estate10/11/2017
CC006000000001040SYED ZISHAN HAIDERVALIMOHAMED MERCHANT AND SHEHZAD VALI MOHAMED MERCHANT THROUGH LANDMARK DEVELOPERS10/11/2017
CC006000000012094SANJAYcas unico karjat24/11/2017
CC006000000023761M/s Landmark Real Estate Developers LtdMr Arvind Kumar29/03/2018
CC006000000057171SURESH KUMAR SURENDRANLANDMARK REAL ESTATE DEVELOPERS LTD03/01/2019
CC006000000057557MANDEEP SINGHLANDMARK REAL ESTATE DEVELOPERS LTD08/01/2019
CC006000000057610Landmark developersSURESH KUMAR SURENDRAN09/01/2019
CC006000000057685M/s Landmark Real Estate DevelopersLtdMr Mandeep Singh16/01/2019
CC006000000089709Hemal Semlani & Arvindraj SemlaniLandmark Real Estate Developers Ltd.14/06/2019
CC006000000192771Nadeem PatankarLandmark Real Estate Developers Ltd27/02/2020
CC006000000194312Jyotsna Chaudhary Shantaram ChaudharyM/s Landmark Real Estate Developers Ltd05/10/2020
CC006000000196148CASA UNICO MEMBERS WELFARE ASSOCIATIONLANDMARK REAL ESTATE DEVELOPERS LTD26/02/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Jun 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed186

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 186 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A Quality Assurance Certificate March 2026.pdf26 May 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate for March 2026.pdf26 Apr 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate for March 2026.pdf26 Apr 2026
Withdrawal Update Form 3File: Form 3 CA Certificate for March 2026.pdf26 Apr 2026
Withdrawal Update Form 1File: FORM 1_ DEC 25_ CASA UNICO.pdf5 Feb 2026
Withdrawal Update Form 2File: FORM 2_ DEC 25_ CASA UNICO.pdf5 Feb 2026
Withdrawal Update Form 3File: FORM 3_ DEC 25_ CASA UNICO compress.pdf5 Feb 2026
Form 2A (FY 2024-2025)File: FORM 2A_ MARCH 25_ CASA UNICO.pdf5 Feb 2026
Withdrawal Update Form 1File: FORM 1_ SEP 25_ CASA UNICO.pdf22 Dec 2025
Withdrawal Update Form 2File: FORM 2_ SEP 25_ CASA UNIC0.pdf22 Dec 2025
Withdrawal Update Form 3File: FORM 3_ SEP 25_ CASA UNICO.pdf22 Dec 2025
Form 5 (FY 2024-2025)File: FORM 5_ MARCH 25_ CASA UNICO.pdf22 Dec 2025
Withdrawal Update Form 1File: Form 1, RERA Architect Certificate, June 2025_compressed.pdf11 Nov 2025
Withdrawal Update Form 2File: Form 2, RERA Engineer Certificate, June 2025.pdf11 Nov 2025
Withdrawal Update Form 3File: Form 3, CA Certificate, June 2025_compressed.pdf11 Nov 2025
Form 1File: Form 1, Architect Certificate, March 2025_compressed.pdf25 Jul 2025
Form 2File: Form 2 Engineer Certificate, March 2025.pdf25 Jul 2025
Form 3File: Form 3 CA Certificate, March 2025_compressed.pdf25 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold inventory, 31-3-2025_compressed.pdf25 Jul 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Form 2 Engineer Certificate, December 2024_compressed.pdf24 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form 1 Architect Certificate, December 2024_compressed.pdf12 Mar 2025
Certificates of CA (Form 3)File: RERA Form 3 CA Certificate, December 2024_compressed (1).pdf21 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Certificate_Dec 2021.pdf23 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate_Sep 2022.pdf23 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate_Dec 2022.pdf23 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate_Jun 2022.pdf23 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Certificate_Jun 2022.pdf23 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Certificate_Jun 2023.pdf23 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Certificate_Sep 2023.pdf23 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Certificate_Dec 2023 (1).pdf23 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assurance Certificate_March 2024.pdf23 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assurance Certificate_June 2024.pdf23 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assurance Certificate_Sep 2024.pdf23 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assurance Certificate_Dec 2024.pdf23 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form 1 Architect Certificate, September 2024_compressed.pdf22 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Form 2 Engineer Certificate, June 2024.pdf4 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Form 2 Engineer Certificate, September 2024.pdf4 Jan 2025
Certificates of CA (Form 3)File: RERA Form 3 CA Certificate, September 2024_compressed.pdf21 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA FORM 5 CA Certificate, March 2024.pdf21 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form 1 Architect's Certificate, June 2024_compressed.pdf25 Nov 2024
Certificates of CA (Form 3)File: RERA Form 3 CA Certificate, June 2024_compressed.pdf18 Nov 2024
Certificates of CA (Form 3)File: RERA Form 3 CA Certificate, March 2024_compressed (1).pdf4 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Engineer Certificate March 2024.pdf17 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Architect Certificate March 2024.pdf30 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form 1, Architect Certificate, December 2023_compressed (1).pdf4 Apr 2024
Certificates of CA (Form 3)File: FORM 3, RERA CA CERTIFICATE, DECEMBER 2023_compressed.pdf26 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Engineer Certificate, December 2023_compressed.pdf21 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A, Engineer Certificate, March 2022.pdf18 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A, Engineer Certificate, March 2023.pdf18 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate_Mar 2022.pdf16 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Certificate_Mar 2023.pdf16 Jan 2024
Declaration in FORM BFile: Form B, Affidavit cum Declaration, LREDL.pdf5 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 8 Certificates of CA (Form 5).pdf5 Jan 2024
Certificates of CA (Form 3)File: Signed Form 3 RERA CA Certificate for March 2023_compressed.pdf3 Jan 2024
Certificates of CA (Form 3)File: Signed Form 3 CA Certificate for June 2023_compressed.pdf3 Jan 2024
Certificates of CA (Form 3)File: Signed Form 3 RERA CA Certificate for September 2023_compressed.pdf3 Jan 2024
Certificates of CA (Form 5)File: Signed Form 5, RERA CA Certificate, March 2023.pdf3 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold inventory, 30-12-2023_compressed (1).pdf30 Dec 2023
Certificates of CA (Form 3)File: JUNE.pdf30 Dec 2023
Certificates of CA (Form 3)File: SEPT.pdf30 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Rera Certificate September 2023_compressed.pdf26 Dec 2023
Certificates of CA (Form 5)File: Form 5, CA Certificate, March 2023.pdf26 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_Engineer Certificate RERA Sept 2023 , 12-10-2023.pdf23 Dec 2023
Certificates of CA (Form 3)File: RERA Form 3 CA Certificate, March 2023.pdf1 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Engineer Certificate RERA June 2023- compressed.pdf30 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certficate, March 2023_compressed.pdf29 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certficate, June 2023_compressed.pdf29 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 230410 Landmark MahaRERA certificate_Mar 2023 R_compressed.pdf4 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5, ANNUAL REPORST STATEMENTnew format, March 2022.pdf24 Mar 2023
Certificates of CA (Form 3)File: RERA Form 3 CA Certificate, December 2022.pdf30 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Architect Certificate December 2022.pdf28 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Engineer Certificate December 2022.pdf28 Jan 2023
Certificates of CA (Form 5)File: Form 5, new format, March 2022.pdf28 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5, ANNUAL REPORST STATEMENTnew format, March 2022.pdf28 Jan 2023
Certificates of CA (Form 3)File: FORM_3_RERA CA_CERTIFICATE, September 2022.pdf6 Jan 2023
Certificates of CA (Form 5)File: FORM-5 ANNUAL_REPORT_STATEMENT, MARCH 2022.pdf5 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Architect Certificate, September 2022.pdf2 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Engineer Certificate, September 2022.pdf31 Dec 2022
Certificates of CA (Form 3)File: Final RERA CA Certificate, March 2022.pdf19 Dec 2022
Certificates of CA (Form 3)File: RERA CA Certificate, June 2022.pdf19 Dec 2022

How this compares with Raigarh

94%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 60 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CASA UNICO PHASE - 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Karjat5,900+ in Raigarh

2 kmCASA UNICO PHASE - 1Completed 2Lapsed / revoked 5Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 13 registered projects within 2 km.

Builder: Landmark Real Estate Developers Limited

Landmark Real Estate Developers Limited has 1 registration on MahaRERA, including CASA UNICO PHASE - 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if CASA UNICO PHASE - 1 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CASA UNICO PHASE - 1?

The registered promoter entity is Landmark Real Estate Developers Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CASA UNICO PHASE - 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against CASA UNICO PHASE - 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for CASA UNICO PHASE - 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CASA UNICO PHASE - 1?

The professionals named in the filing: Architect: GA DESIGN; Architect: SHREE VASTU SANKALPA CONSULTANCY; Engineer: INTEGRATED BUILDING SERVICES; Chartered Accountant: Keyur Bhayani; Chartered Accountant: CA SHRADDHA PARANJAPE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CASA UNICO PHASE - 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CASA UNICO PHASE - 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CASA UNICO PHASE - 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.