CASA PALAZZO

By M/S. PARADIGM REAL ESTATES LLP

RG-MH-24635 · RERA P51800008441 · Last updated on MahaRERA portal: 6 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 56 months past the filed date
  • 7 complaints at MahaRERA
  • Completion date moved by 35 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Feb 2022Possession promised56 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
7Complaints at MahaRERAon this registration
Jump to the 87 documents Report an error

CASA PALAZZO is a Others project by M/S. PARADIGM REAL ESTATES LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800008441 on 18 Aug 2017. Possession was promised by 28 Feb 2022 and is now 56 months past that date. The completion date has moved by 35 months from the original filing. 7 complaints are on record with the regulator.

At a glance

Project

  • NameCASA PALAZZO
  • TypeOthers
  • Location
    • Carter Road No. 3
    • Borivali (East)
    • Borivali
    • Mumbai Suburban
    • 400066
  • Pincode400066
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800008441
  • ReraGenie IDRG-MH-24635

Builder

  • NameM/S. PARADIGM REAL ESTATES LLP
  • Entity typeOthers
  • Named personsDOTOM URBAN SPACE LLP, PARTH KAUSHIK MEHTA
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

56 months past promisethis monthRegisteredAug 2017First promiseMar 2019Revised toFeb 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 Aug 2017
  • Promised completion28 Feb 2022
  • Revised completionRevised to 28 Feb 2022 (originally 31 Mar 2019)
  • Buildings1 building record
  • Documents filed87 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CASA PALAZZONA220000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

CASA PALAZZO: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities21

As on 6 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
Swimming PoolNoNot applicable
SOCIETY OFFICEYes100%
24X7 CCTVSURVEILLANCEYes100%
ElevatorYes100%
ENTRANCE LOBBYYes100%
FITNESS CENTREYes100%

Parking filed25

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots25
Closed/Covered25

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area840 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
M/S. SHREE SAI TAJ DEVELOPERSBorivaliMumbai Suburban

Approvals and building plan

Permissible FSI3649.53
Proposed, not sanctioned1,535 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSAANA A BUILDING, LINKING ROAD, SANTACRUZ WEST, MUMBAI - 400054

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDOT ARCHITECTS
EngineerGIREESH RAJADHYAKSHA
PartnerRole in project
M/S. PARADIGM REAL ESTATES LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800005843Mar 2019 → Feb 2021

Reason as filed by the promoterThe completion of the Project has been delayed over a period of time essentially on the reasons which are beyond the control of the Developer because: (i) The present Project is being developed under the provisions of slum scheme. The Developer are obliged to construct 2 rehab wings, Wing A and Wing ‘B’ and 1 sale wing being Wing ‘C’ (Casa Palazzo). The Developer commenced construction of said rehab wings and sale wing. Various compliances were to be complied with by the Developer not only with respect to the sale Wing C but also with respect to the said rehab wings. Simultaneously Developer a

EXT51800001485Mar 2019 → Feb 2021

Reason as filed by the promoterProject was registered on 18.08.2017 with RERA and time for completion of the project as mentioned under RERA is 31.03.2019. The said project under reference is implemented under the Slum Rehabilitation Scheme. The Annexure -II had 79 slum dwellers out of which 56 slum dwellers were declared eligible and the balance 23 were ineligible slum dwellers. The ineligible slum dwellers had made an application for reconsideration of their eligibility before the Competent Authority SRA and the same is under process. Pending the said application and in the event such eligibility is considered by the Comp

Complaints filed with MahaRERA7

Case no.ComplainantRespondentFiled
CC006000000171947Paras DoshiParadigm real Estate LLP23/12/2019
CC006000000197683Kalpak DesaleParadigm Real Estate LLP23/07/2021
CC006000000210266Rachana SmithParadigm Realty10/03/2022
CC006000000221017Deepali JadiaParadigm Real Estates LLP30/04/2022
CC006000000292683VIRAL ASHOKKUMAR SHAHPARADIGM REAL ESTATES LLP23/03/2023
CC006000000303071Harsh Shahparadigm realty20/10/2022
CC006000000303667Paras M DoshiParadigm Real Estate LLP14/12/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Jun 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 18 Jan 2023

Documents filed87

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 87 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: Casa Palazzo sold unsold till dec 2024.pdf6 Feb 2025
Disclosure of sold/ booked inventoryFile: Casa Palazzo sold unsold till sept 2024.pdf30 Oct 2024
Disclosure of sold/ booked inventoryFile: Casa Palazzo sold unsold till june 2024.pdf5 Aug 2024
Disclosure of sold/ booked inventoryFile: Casa Palazzo sold unsold inventory till Mar 2024.pdf5 Jun 2024
Disclosure of sold/ booked inventoryFile: Casa Palazzo sold unsold inventory till sept 2023.pdf29 Feb 2024
Disclosure of sold/ booked inventoryFile: Casa Palazzo sold unsold - Dec 2023.pdf29 Feb 2024
Disclosure of sold/ booked inventoryFile: Casa Palazzo Sold Unsold 30th June 2023.pdf18 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE-CASA PALAZZO -31-04-2023.pdf1 May 2023
Disclosure of sold/ booked inventoryFile: Casa Palazzo Sold Unsold till mar 2023.pdf1 May 2023
Certificates of CA (Form 3)File: Form 3 Dec 22_Signed_compressed.pdf5 Apr 2023
Disclosure of sold/ booked inventoryFile: Casa Palazzo Sold Unsold Dec, 2022.pdf30 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE-CASA PALAZZO -31-12-2022.pdf27 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 19 - 20.pdf27 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 20 - 21.pdf27 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 21-22.pdf27 Mar 2023
Certificates of CA (Form 5)File: Paradigm Real Estates LLP FORM 5.pdf10 Feb 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Casa OC.pdf18 Jan 2023
Certificates of CA (Form 3)File: Form-3 Casa Pallazo Sept 22 compressed.pdf17 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE-CASA PALAZZO Sept 22.pdf13 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: casa form 2.pdf13 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 casa march 2022.pdf8 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 casa june 22.pdf8 Jul 2022
Building plan approvalFile: Casa amended IOA.pdf20 Jun 2022
Building Plan Approval (IOD)File: Casa amended IOA.pdf20 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: Casa Plazo CC Full.pdf20 Jun 2022
Declaration about Commencement CertificateFile: Scanned copy of declaration of CC casa palazzo.pdf20 Jun 2022
Disclosure of sold/ booked inventoryFile: Casa Pallazo Inventory.pdf11 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CASA ARCHITECT CERTIFICATE 30-12-2021.pdf9 Mar 2022
Disclosure of sold/ booked inventoryFile: Casa Palazo.pdf18 Feb 2022
Disclosure of sold/ booked inventoryFile: sold unsold casa.pdf22 Oct 2021
Disclosure of sold/ booked inventoryFile: CASA SOLD UNSOLD.pdf26 Jul 2021
Declaration about Commencement CertificateFile: Declaration CC Casa.pdf23 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AC 31st Mar,2018.pdf23 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AC 31st DEc 2018.pdf23 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AC 31st Dec2017.pdf23 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AC 30 Sep,18.pdf23 Jul 2021
Form 2AFile: quality assurance - casa pallazo -30-06-2020.pdf23 Jul 2021
Form 2AFile: quality assurance - casa pallazo -30-09-2020.pdf23 Jul 2021
Form 2AFile: quality assurance - casa pallazo -31-03-2020.pdf23 Jul 2021
Form 2AFile: quality assurance - casa pallazo -31-12-2020.pdf23 Jul 2021
Form 2AFile: quality assurance - casa pallazo -30-06-2021.pdf23 Jul 2021
Form 2AFile: quality assurance - casa pallazo -31-03-2021.pdf23 Jul 2021
Form 2AFile: FORM2A CASAPALLAZO.pdf23 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: quality assurance - casa pallazo -30-06-2021.pdf23 Jul 2021
Certificates of CA (Form 5)File: _1067366767 (1)_compressed.pdf23 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CASA (2).pdf19 Jul 2021
Certificates of CA (Form 5)File: -2063110093.pdf17 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: CC CASA.pdf12 Jul 2021
Certificates of CA (Form 5)File: CASA form 5_compressed.pdf12 Jul 2021
Disclosure of sold/ booked inventoryFile: CASA palazo.pdf9 Jul 2021
Certificates of CA (Form 3)File: CA certificate CASA.pdf6 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SKM_C224e21060318060_rotated.pdf4 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SKM_C224e21060318051_rotated.pdf4 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 3 PRELLP 30032020.pdf11 Nov 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 3 PRELLP 30062020.pdf11 Nov 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 3 PRELLP 30092020.pdf11 Nov 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate - casa pallazo.pdf5 Mar 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: PARADIGM REAL ESTATES LLP Casa Palazzo FORM 5.pdf28 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE_CASA PALAZZO_30 09 2019_compressed.pdf27 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE - 29-06-2019.pdf9 Aug 2019
Form 2AFile: 09 07 2019_SAITAJ QUALITY ASSURANCE_TILL JUNE2019.pdf23 Jul 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CASA PALAZZO ARCHITECT CERTIFICATE- 30-03-2019.pdf21 May 2019
Form 2AFile: 14 05 2019_SAITAJ QUALITY ASSURANCE_TILL MARCH2019.pdf16 May 2019
Form 2AFile: CASA QUALITY ASSURANCE_07 02 2019 FORM 2A.pdf25 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Casa Palzzo_31_12_2018.pdf13 Feb 2019
Certificates of CA (Form 5)File: Annual report on statement of Account (1).pdf15 Oct 2018
Certificates of CA (Form 5)File: Paradigm Real Estate llp.pdf3 Oct 2018
Building plan approvalFile: scan.pdf10 Jul 2018
Building Plan Approval (IOD)File: scan.pdf10 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: 0064_001.pdf10 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: Casa Palazzo CC upto 9th Floor.pdf25 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE-CASA PALAZZO.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg letter SAI TAJ Sale 310717.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Letter Sai Taj Rehab 310717.pdf31 Jul 2017
Certificates of CA (Form 3)File: Form 3 CA Certificate.pdf31 Jul 2017
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf31 Jul 2017
Proforma of Allotment letterFile: AGREEMENT FOR SALE.pdf31 Jul 2017
Layout approvalFile: Declaration on no layout.PDF29 Jul 2017
Building plan approvalFile: Amended IOA.pdf29 Jul 2017
PAN CardFile: PAN PRE LLP.pdf29 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 35 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CASA PALAZZO on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Borivali (East)6,700+ in Mumbai Suburban

2 kmCASA PALAZZOCompleted 138Lapsed / revoked 77Other 196Dot size: filed unitsN

Filed coordinates, straight-line distance. 411 registered projects within 2 km.

Builder: M/S. PARADIGM REAL ESTATES LLP

M/S. PARADIGM REAL ESTATES LLP has 2 registrations on MahaRERA, including NIVAN and CASA PALAZZO. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that CASA PALAZZO shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if CASA PALAZZO is delayed beyond 28 Feb 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CASA PALAZZO?

The registered promoter entity is M/S. PARADIGM REAL ESTATES LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CASA PALAZZO?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against CASA PALAZZO?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for CASA PALAZZO?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CASA PALAZZO?

The professionals named in the filing: Architect: DOT ARCHITECTS; Engineer: GIREESH RAJADHYAKSHA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CASA PALAZZO?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CASA PALAZZO. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CASA PALAZZO to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.