CA SIGNATURE

By U K FAROOQ

RG-KA-41476 · RERA PRM/KA/RERA/1257/334/PR/260325/007628 · Last updated on RERA Karnataka portal: 13 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2027Possession promisedno revision filed
5 of 16Construction stages donefurthest along: Masonry Construction, 95%
2 of 32Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 125 documents Report an error

CA SIGNATURE is a Mixed Development project by U K FAROOQ in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/260325/007628 on 26 Mar 2025. Possession is promised by 30 Dec 2027. 30 of the 32 units on this registration are recorded sold or booked, and 5 of 16 construction stages are filed complete.

At a glance

Project

  • NameCA SIGNATURE
  • TypeMixed Development
  • Location
    • Mangalore
    • Dakshina Kannada
    • 575020
  • Pincode575020
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/260325/007628
  • ReraGenie IDRG-KA-41476

Builder

  • NameU K FAROOQ
  • Entity typeProprietorship
  • GSTIN29AAEPF1018M2ZS
  • Authorized SignatoryU K FAROOQ

Key dates

this monthRegisteredMar 2025PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on26 Mar 2025
  • Promised completion30 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed125 files

Current status

94%30 of 32 units booked
15.3%Of the estimated cost spent so far

Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CA SIGNATURE-----32

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 16 construction stages are filed complete. The stage furthest along is Masonry Construction, at 95%.

Building: 59% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction95%
Plastering inside , outside & Ceiling80%
Joinery: Doors, Windows, Ventilators etc80%
Basic work of Water supply, Sanitary and Electrification20%
Dadoing, Skirting, Flooring, Tiles work (All types)20%
Railing and Grill fixing50%
Electrification, Water supply and Sanitary Finishing40%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work60%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes0%
Piped GasYes0%
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes80%
LiftsYes0%
Corridor/LobbiesYes80%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes80%
BasementNoNot applicable
TerraceYes60%
Outer WallYes60%
Open parking areasYes0%
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,619 sq m
Named landowners2
LandownerVillageDistrict
U T FAROOQ--
U K FAROOQ--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 13.33 cr
Cost incurredRs 2.04 cr
Spent of the estimate15.3%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 13.23 crRs 2.04 cr
other contingenciesRs 10.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectM VENKATESH PAI
EngineerM VENKATESH PAI
Chartered AccountantSIRAJUDDIN

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed125

As listed on the registration, under the names the promoter filed them with; the newest 80 of 125 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/260325/007628 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM 4.pdf13 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5.pdf13 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6.pdf13 Oct 2026
Q2 2026-27 Water supply and sewage board13 Oct 2026
Q2 2026-27 KPTCL- BESCOM13 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4-Chartered Accountant Certificate Q1_.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: form 5.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: form 6.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM 4.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Chartered Accountant Certificate Q3.pdf20 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: form 5.pdf20 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: form 6.pdf20 Feb 2026
Q3 2025-26 Water supply and sewage board20 Feb 2026
Q3 2025-26 KPTCL- BESCOM20 Feb 2026
SALE DEEDFile: Sale Deed 30cents.pdf21 Jan 2025
SALE DEEDFile: Sale Deed 10cents.pdf21 Jan 2025
GSTFile: gst.pdf21 Jan 2025
CLARIFICATIONFile: Clarification CA.pdf21 Jan 2025
sources of fundsFile: Source of fund.pdf14 Jan 2025
balance sheet, profit, loss account & ITR of 2021-22, 2022-2023, and 2023-24 with schedule and UDINFile: 2024 BS and PL with UDIN with schedules.pdf14 Jan 2025
2023File: BS and PL 2023 WITH UDIN with schedules.pdf14 Jan 2025
2022File: ITR and financials 2022.pdf14 Jan 2025
MRFile: MR.pdf14 Jan 2025
latest katha extractFile: Khata 10.pdf14 Jan 2025
latest katha extractFile: Khata 30.pdf14 Jan 2025
ADLR Certified survey sketchFile: ADLR.pdf14 Jan 2025
Original Single Plot layout plan. 3. Approved Original Single Plot layout planFile: single site plan and order original.pdf14 Jan 2025
Building License from Local Authority Original Copy.File: Building license original.pdf14 Jan 2025
Approved building plan - Original CopyFile: Approved plans and all drawings originals.pdf14 Jan 2025
Upload all original sanctioned drawings, floor plan, sectional drawings and elevations.File: Approved plans and all drawings originals.pdf14 Jan 2025
Approved Master plan Extract marked the proposed landFile: cdp with proposed site.pdf14 Jan 2025
Village map certified by the concern officer with demarcation of proposed landFile: village map with proposed site marking signed by the concerned authority.pdf14 Jan 2025
Amenities and Common Area detailsFile: Amenities and common area certified by Engineeer.pdf14 Jan 2025
Project Engineer details and upload the Engineer LicenseFile: Engineer License.pdf14 Jan 2025
Project Engineer details and upload the Engineer LicenseFile: ENGINEER LICENSE 24.pdf14 Jan 2025
Original Engineer certificate should be signed by the registered Engineer.File: Engineer Certificate.pdf14 Jan 2025
structural safetyFile: Stability certificate.pdf14 Jan 2025
land cost calculation sheet (self-attested copy) as per the guidance value in the original.File: Land valuation.pdf14 Jan 2025
GUIDANCE VALUEFile: guidance vaule street no11.pdf14 Jan 2025
Proforma of the Agreement for sale.File: AOS.pdf14 Jan 2025
Guidance ValueFile: Guidance value.pdf14 Jan 2025
Allotment letterFile: Allotment Letter with Annexure.pdf14 Jan 2025
WellFile: well pic.jpeg14 Jan 2025
WellFile: well.jpeg14 Jan 2025
ADDITIONAL FEES PAID RECEIPTFile: rera additional fees.pdf14 Jan 2025
RECEIPTFile: payt status.PNG14 Jan 2025
CLARIFICATIONFile: CLARIFICATION.pdf14 Jan 2025
RTC, survey 140/11-
Mutation, survey 140/11-
Encumbrance Certificate, survey 140/11-
Conversion/Alienation Order, survey 140/11-
Sale/Title/Gift Deed, survey 140/11-
Khatha, survey 140/11-
RTC, survey 140/2A6(P)-
Mutation, survey 140/2A6(P)-
Encumbrance Certificate, survey 140/2A6(P)-
Conversion/Alienation Order, survey 140/2A6(P)-
Sale/Title/Gift Deed, survey 140/2A6(P)-
Khatha, survey 140/2A6(P)-
Registration CertificateFile: trade licence new.pdf-
GST CertificateFile: gst.pdf-
Certificate issued by CA Form 1File: FORM 1.pdf-
Certificate issued by Architect Form 2File: Form 2.pdf-
Certificate issued by Engineer Form 3File: Form 3.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non-litigation.pdf-
Balance Sheet 2023 - 2024File: BS and PL with UDIN 2024.pdf-
Balance Sheet 2022 - 2023File: BS and PL 2023 WITH UDIN.pdf-
Balance Sheet 2021 - 2022File: UK Farooq 2022.pdf-
Audited Profit and Loss Statement 2023 - 2024File: BS and PL with UDIN 2024.pdf-
Audited Profit and Loss Statement 2022 - 2023File: BS and PL 2023 WITH UDIN.pdf-
Audited Profit and Loss Statement 2021 - 2022File: UK Farooq 2022.pdf-

How this compares with Dakshina Kannada

94%of this project is bookeddistrict median 38%
30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep CA SIGNATURE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmCA SIGNATUREOther 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: U K FAROOQ

U K FAROOQ has 1 registration on RERA Karnataka, including CA SIGNATURE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if CA SIGNATURE is delayed beyond 30 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of CA SIGNATURE?

The registered promoter entity is U K FAROOQ, a proprietorship as per the filing. Its GSTIN 29AAEPF1018M2ZS can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in CA SIGNATURE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at CA SIGNATURE?

The professionals named in the filing: Architect: M VENKATESH PAI; Engineer: M VENKATESH PAI; Chartered Accountant: SIRAJUDDIN. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CA SIGNATURE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CA SIGNATURE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CA SIGNATURE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.