Home / Browse projects / Bengaluru Rural, Karnataka / Brigade Oasis - Phase 3

Registration approved Litigation declared Plotted Development project

Brigade Oasis - Phase 3

By Brigade Enterprises Ltd

RG-KA-22193 · RERA PRM/KA/RERA/1250/303/PR/220124/006562 · Last updated on RERA Karnataka portal: 15 Jul 2026

Source: official RERA Karnataka filing

Red flags

  • Litigation declared
  • 2 complaints at RERA Karnataka
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Jun 2026Possession promisedmoved 12 months from the original
2Complaints at RERA Karnatakaon this registration
Jump to the 559 documents Report an error

Brigade Oasis - Phase 3 is a Plotted Development project by Brigade Enterprises Ltd in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/303/PR/220124/006562 on 22 Jan 2024. Possession is promised by 30 Jun 2026. The completion date has moved by 12 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameBrigade Oasis - Phase 3
  • TypePlotted Development
  • Location
    • Devanahalli
    • Bengaluru Rural
    • 562110
  • Pincode562110
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1250/303/PR/220124/006562
  • ReraGenie IDRG-KA-22193

Builder

  • NameBrigade Enterprises Ltd
  • Entity typeCompany
  • CINL85110KA1995PLC019126
  • GSTIN29AAACB7459F1ZI
  • Authorized SignatoryViswa Prathap Desu
  • Managing DirectorPavitra Shankar
  • DirectorsM. R. Jaishankar, Bijou Kurien, Aroon Raman, Lakshmi Venkatachalam, Pradeep Kumar Panja, Venkatesh Panchapagesan, Amar Mysore, Pavitra Shankar, Nirupa Shankar, Roshin Mathew, Velloor Venkatakrishnan Ranganathan, Pradyumna Krishnakumar
  • Project HeadBalasubramanian M N
  • Other registrations45 more →
  • No longer live1 withdrawn or revoked
  • Declared earlier projects67 →

Key dates

this monthRegisteredJan 2024First promiseJun 2025Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on22 Jan 2024
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2025)
  • BuildingsNot stated in filing
  • Documents filed559 files

Current status

0.0%Of the estimated cost spent so far

Figures as on 15 Jul 2026, this project's latest RERA Karnataka filing.

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Land and ownership62

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners62
LandownerVillageDistrict
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 48.23 cr
Spent of the estimate0.0%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 37.23 cr-
Payment of taxesRs 6.72 cr-
On-site expenditure-Site OverheadRs 2.08 cr-
Principal sum and interest payable to financial institutions-Scheduled BanksRs 2.07 cr-
On-site expenditure-Salaries of workersRs 9.01 lakh-
On-site expenditure-Consultants FeesRs 3.61 lakh-
Payment of PremiumsRs 15,646-
Payment of cessRs 13,786-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerVijay Kumar
Chartered AccountantR. Srinivasan

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1250/303/PR/250627/006562Jun 2025 → Jun 2026

Reason as filed by the promoterDelay in Approvals

Litigation declaredYes

The promoter declares litigation on this registration. The case records are in the filed documents.

Complaints filed with RERA Karnataka2

Case no.ComplainantRespondentFiled
00031/2026-Brigade Enterprises Ltd09/01/2026
00034/2026-Brigade Enterprises Ltd09/01/2026

Documents filed559

As listed on the registration, under the names the promoter filed them with; the newest 80 of 559 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/303/PR/220124/006562 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Brigade Oasis Phase-3 - Form 4 - Q1.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Brigade Oasis Phase 3 - Form 6 - Q1.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 Engineering Department (PWD) for completion of development works15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Horticulture department15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Brigade Oasis - Phase 3 - Form 4 - Q4.pdf8 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Brigade Oasis - Phase 3 - Form 6 - Q4.pdf8 Apr 2026
Q4 2025-26 Water supply and sewage board8 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)8 Apr 2026
Q4 2025-26 Engineering Department (PWD) for completion of development works8 Apr 2026
Q4 2025-26 KPTCL- BESCOM8 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Brigade Oasis Phase 3 - Form 4 - Q3.pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Brigade Oasis Phase 3 - Form 6 - Q3.pdf14 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Jan 2026
Current year RTC - Sy No 2/3File: RTC - SY NO 2-3.pdf18 Jan 2024
Hissa for Sy No 26File: Hissa Tippany Sy No 26.pdf18 Jan 2024
Akarband for Sy No 26File: Akarband - 26.pdf18 Jan 2024
Conversion Order for Sy No 26/8File: Conversion Order - Sy No 26-8.pdf18 Jan 2024
Conversion Order for Sy No 2/4File: Conversion Order - 2-4.pdf18 Jan 2024
Conversion Order for Sy No 6/11File: Conversion Order - Sy No 6-11.pdf18 Jan 2024
Old Relinquishment DeedFile: Brigade Oasis - Old Relinquishment Deed.pdf18 Jan 2024
Cancellation Deed of Old Relinquishment DeedFile: Cancellation Deed of Old Relinquishment Deed.pdf18 Jan 2024
Layout Work OrderFile: Layout Work Order.pdf18 Jan 2024
Village MapFile: LAXMIPURA Village Map.pdf18 Jan 2024
KSPCB NOCFile: Brigade Oasis - Consent for Establishment.pdf18 Jan 2024
ADLR SketchFile: ADLR Sketch.pdf18 Jan 2024
Common Area Details shown in the Sanction PlanFile: Common Area Details in Sanction Plan.pdf18 Jan 2024
Engineer CertificateFile: Brigade Oasis - Phase 3 - Form 3.pdf18 Jan 2024
Guideline Valuation DetailsFile: Brigade Oasis - Phase 3 - Guideline Value.pdf18 Jan 2024
Proforma Allotment LetterFile: Pro Forma Allotment - Oasis Ph 3.pdf18 Jan 2024
Agreement to SellFile: Agreement to Sell, Oasis_Phase 3 - for RERA.pdf18 Jan 2024
Demarcation SketchFile: Demarcation Sketch.pdf18 Jan 2024
Reply to the QueriesFile: Reply to Queries.pdf18 Jan 2024
RTC, survey 3/1-
Mutation, survey 3/1-
Encumbrance Certificate, survey 3/1-
Conversion/Alienation Order, survey 3/1-
Sale/Title/Gift Deed, survey 3/1-
JDA, survey 3/1-
Khatha, survey 3/1-
RTC, survey 4/2-
Mutation, survey 4/2-
Encumbrance Certificate, survey 4/2-
Conversion/Alienation Order, survey 4/2-
Sale/Title/Gift Deed, survey 4/2-
JDA, survey 4/2-
Khatha, survey 4/2-
RTC, survey 4/3-
Mutation, survey 4/3-
Encumbrance Certificate, survey 4/3-
Conversion/Alienation Order, survey 4/3-
Sale/Title/Gift Deed, survey 4/3-
JDA, survey 4/3-
Khatha, survey 4/3-
RTC, survey 4/4-
Mutation, survey 4/4-
Encumbrance Certificate, survey 4/4-
Conversion/Alienation Order, survey 4/4-
Sale/Title/Gift Deed, survey 4/4-
JDA, survey 4/4-
Khatha, survey 4/4-
RTC, survey 4/5-
Mutation, survey 4/5-
Encumbrance Certificate, survey 4/5-
Conversion/Alienation Order, survey 4/5-
Sale/Title/Gift Deed, survey 4/5-
JDA, survey 4/5-
Khatha, survey 4/5-
RTC, survey 4/6-
Mutation, survey 4/6-
Encumbrance Certificate, survey 4/6-
Conversion/Alienation Order, survey 4/6-
Sale/Title/Gift Deed, survey 4/6-
JDA, survey 4/6-
Khatha, survey 4/6-
RTC, survey 4/7-
Mutation, survey 4/7-
Encumbrance Certificate, survey 4/7-

How this compares with Bengaluru Rural

20%of Bengaluru Rural projects moved their completion datethis one moved by 12 months
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep Brigade Oasis - Phase 3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

2 kmBrigade Oasis - Phase 3Other 12Dot size: filed unitsN

Filed coordinates, straight-line distance. 12 registered projects within 2 km.

Builder: Brigade Enterprises Ltd

Brigade Enterprises Ltd has 46 registrations on RERA Karnataka, including Brigade Oasis - Phase 1 and Brigade Atmosphere- Phase 1. Its filings declare 67 earlier projects, 41 of them declared completed. Litigation is declared on 10 of its registrations. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if Brigade Oasis - Phase 3 is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Brigade Oasis - Phase 3?

The registered promoter entity is Brigade Enterprises Ltd, a company as per the filing. Its CIN L85110KA1995PLC019126 and GSTIN 29AAACB7459F1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Brigade Oasis - Phase 3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Brigade Oasis - Phase 3?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Brigade Oasis - Phase 3?

The professionals named in the filing: Engineer: Vijay Kumar; Chartered Accountant: R. Srinivasan. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Brigade Oasis - Phase 3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Brigade Oasis - Phase 3. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Brigade Oasis - Phase 3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.