Home / Browse projects / Bengaluru Rural, Karnataka / Brigade Oasis - Phase 1

Registration approved Litigation declared Plotted Development project

Brigade Oasis - Phase 1

By Brigade Enterprises Ltd

RG-KA-49609 · RERA PRM/KA/RERA/1250/303/PR/041122/005401 · Last updated on RERA Karnataka portal: 15 Jul 2026

Source: official RERA Karnataka filing

Red flags

  • Litigation declared
  • 1 complaint at RERA Karnataka
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Jun 2026Possession promisedmoved 12 months from the original
1Complaints at RERA Karnatakaon this registration
Jump to the 255 documents Report an error

Brigade Oasis - Phase 1 is a Plotted Development project by Brigade Enterprises Ltd in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/303/PR/041122/005401 on 4 Nov 2022. Possession is promised by 30 Jun 2026. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameBrigade Oasis - Phase 1
  • TypePlotted Development
  • Location
    • Devanahalli
    • Bengaluru Rural
    • 562110
  • Pincode562110
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1250/303/PR/041122/005401
  • ReraGenie IDRG-KA-49609

Builder

  • NameBrigade Enterprises Ltd
  • Entity typeCompany
  • CINL85110KA1995PLC019126
  • GSTIN29AAACB7459F1ZI
  • Authorized SignatoryMr. Viswa Prathap Desu
  • Chief Sales OfficerMr. Viswa Prathap Desu
  • DirectorsMr. M. R. Jaishankar, Mr. Bijou Kurien, Mr. Aroon Raman, Ms. Lakshmi Venkatachalam, Mr. Pradeep Kumar Panja, Dr. Venkatesh Panchapagesan, Mr. Amar Mysore, Ms. Pavitra Shankar, Ms. Nirupa Shankar, Mr. Roshin Mathew
  • Project HeadBalasubramanian M N
  • Other registrations45 more →
  • No longer live1 withdrawn or revoked
  • Declared earlier projects67 →

Key dates

this monthRegisteredNov 2022First promiseJun 2025Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on4 Nov 2022
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2025)
  • BuildingsNot stated in filing
  • Documents filed255 files

Current status

0.0%Of the estimated cost spent so far

Figures as on 15 Jul 2026, this project's latest RERA Karnataka filing.

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Land and ownership20

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners20
LandownerVillageDistrict
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt LtdQ--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--
M/s Krishna Priya Estates Pvt Ltd--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 28.05 cr
Spent of the estimate0.0%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 19.73 cr-
Payment of taxesRs 3.57 cr-
On-site expenditure-Site OverheadRs 3.45 cr-
Principal sum and interest payable to financial institutions-Scheduled BanksRs 1.09 cr-
On-site expenditure-Salaries of workersRs 14.93 lakh-
On-site expenditure-Consultants FeesRs 5.99 lakh-
Payment of PremiumsRs 25,930-
Payment of cessRs 22,848-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerVijay Kumar
Chartered AccountantR. Srinivasan

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1250/303/PR/250627/005401Jun 2025 → Jun 2026

Reason as filed by the promoterDelay in Approvals

Litigation declaredYes

The promoter declares litigation on this registration. The case records are in the filed documents.

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
01181/2026-Brigade Enterprises Ltd03/10/2026

Documents filed255

As listed on the registration, under the names the promoter filed them with; the newest 80 of 255 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/303/PR/041122/005401 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Brigade Oasis Phase-1 - Form 4 - Q1.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Brigade Oasis Phase 1 - Form 6 - Q1.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 Engineering Department (PWD) for completion of development works15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Horticulture department15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Brigade Oasis - Phase 1 - Form 4 - Q4.pdf8 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Brigade Oasis - Phase 1 - Form 6 - Q4.pdf8 Apr 2026
Q4 2025-26 Water supply and sewage board8 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)8 Apr 2026
Q4 2025-26 Engineering Department (PWD) for completion of development works8 Apr 2026
Q4 2025-26 KPTCL- BESCOM8 Apr 2026
Q4 2025-26 Horticulture department8 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Brigade Oasis Phase 1 - Form 4 - Q3.pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Brigade Oasis Phase 1 - Form 6 - Q3.pdf14 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Jan 2026
KSPCB NOCFile: Brigade Oasis - CFE Application Ack Copy.pdf2 Nov 2022
MOEF NotificationFile: MOEF Notification.pdf2 Nov 2022
CDP Map showing the proposed Road WideningFile: Brigade Oasis - Extract of STRRPA Master Plan 2031.pdf2 Nov 2022
Response to QueriesFile: Brigade Oasis - List of Queries raised by RERA and BEL.pdf2 Nov 2022
Financial StatementFile: Financial Statement - 2021-22.pdf21 Oct 2022
RTC for all Sy NosFile: RTCs for all Sy Nos.pdf21 Oct 2022
Mutation RegistrarsFile: Mutation Registrar.pdf21 Oct 2022
Sale Deeds for all Sy Nos in the name of Mr. Binny P KuriyakasFile: Sale Deed in the name of Binny P Kuriyakas.pdf21 Oct 2022
Sale Deeds for all Sy Nos in the name of Mr. K. G KrishnaFile: Sale Deeds in the name of K G Krishna.pdf21 Oct 2022
Sale Deeds for all Sy Nos in the name of Mr. V. G. DesaiFile: Sale Deed - V G Desai - Sy No 7-5 (Old No 7).pdf21 Oct 2022
Sale Deeds for all Sy Nos in the name of Mr. Kondapudi IndrammaFile: Sale Ded - Kondla Pudi Indiramma - Sy No 6-6.pdf21 Oct 2022
GPA to K G KrishnaFile: GPA to K G Krishna.pdf21 Oct 2022
Sale Deed from V.G. Desai to Binny P. Kuriyakas and subsequently from Mr. Binny P. Kuriyakas to SSYFile: Sale Deed - V G Desai - Sy No 7-5 (Old No 7).pdf21 Oct 2022
CDP Map showing the proposed Road WideningFile: Brigade Oasis - Cadastral Survey Plan.pdf21 Oct 2022
Village MapFile: Village Map.jpg21 Oct 2022
Relinquishment Deed done for entire projectFile: Brigade Oasis - Relinquishment Deed dt 30-07-2022.pdf21 Oct 2022
Demarcation DrawingFile: Brigade Oasis - Phase 1 Demarcation Plan.pdf21 Oct 2022
Estimated cost of construction as certified by EngineerFile: Estimated Cost.jpeg21 Oct 2022
Project SpecificationFile: Brigade Oasis - Specification for Plotted development.pdf21 Oct 2022
Proforma Agreement for saleFile: Proforma Agreement for Sale - Brigade Oasis.pdf21 Oct 2022
STP PlanFile: Brigade Oasis - STP Plan.pdf21 Oct 2022
STP ReportFile: Brigade Oasis - STP Report.pdf21 Oct 2022
GPA to BinnyFile: GPA to Binny.pdf21 Oct 2022
GPA to Devagiri PropertiesFile: GPA to Devagiri.pdf21 Oct 2022
Guideline Value for Lakshmipura VillageFile: Brigade Oasis - Guideline Value.pdf21 Oct 2022
Reply to RERA QueriesFile: Reply to RERA Queries.pdf21 Oct 2022
RTC, survey Sy No 3/1-
Mutation, survey Sy No 3/1-
Encumbrance Certificate, survey Sy No 3/1-
Conversion/Alienation Order, survey Sy No 3/1-
Sale/Title/Gift Deed, survey Sy No 3/1-
JDA, survey Sy No 3/1-
Khatha, survey Sy No 3/1-
RTC, survey 4/2-
Mutation, survey 4/2-
Encumbrance Certificate, survey 4/2-
Conversion/Alienation Order, survey 4/2-
Sale/Title/Gift Deed, survey 4/2-
JDA, survey 4/2-
Khatha, survey 4/2-
RTC, survey 4/3-
Mutation, survey 4/3-
Encumbrance Certificate, survey 4/3-
Conversion/Alienation Order, survey 4/3-
Sale/Title/Gift Deed, survey 4/3-
JDA, survey 4/3-
Khatha, survey 4/3-
RTC, survey 4/4-
Mutation, survey 4/4-
Encumbrance Certificate, survey 4/4-
Conversion/Alienation Order, survey 4/4-
Sale/Title/Gift Deed, survey 4/4-
JDA, survey 4/4-
Khatha, survey 4/4-
RTC, survey 4/5-
Mutation, survey 4/5-
Encumbrance Certificate, survey 4/5-
Conversion/Alienation Order, survey 4/5-
Sale/Title/Gift Deed, survey 4/5-
JDA, survey 4/5-
Khatha, survey 4/5-
RTC, survey Sy No. 4/6-
Mutation, survey Sy No. 4/6-

How this compares with Bengaluru Rural

20%of Bengaluru Rural projects moved their completion datethis one moved by 12 months
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep Brigade Oasis - Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

2 kmBrigade Oasis - Phase 1Other 12Dot size: filed unitsN

Filed coordinates, straight-line distance. 12 registered projects within 2 km.

Builder: Brigade Enterprises Ltd

Brigade Enterprises Ltd has 46 registrations on RERA Karnataka, including Brigade Oasis - Phase 1 and Brigade Atmosphere- Phase 1. Its filings declare 67 earlier projects, 41 of them declared completed. Litigation is declared on 10 of its registrations. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if Brigade Oasis - Phase 1 is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Brigade Oasis - Phase 1?

The registered promoter entity is Brigade Enterprises Ltd, a company as per the filing. Its CIN L85110KA1995PLC019126 and GSTIN 29AAACB7459F1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Brigade Oasis - Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Brigade Oasis - Phase 1?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Brigade Oasis - Phase 1?

The professionals named in the filing: Engineer: Vijay Kumar; Chartered Accountant: R. Srinivasan. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Brigade Oasis - Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Brigade Oasis - Phase 1. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Brigade Oasis - Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.