Red flags

  • 3 complaints at RERA Karnataka

Clear

  • Completion date never moved
  • Separate project account declared
Feb 2020Possession promisedno revision filed
3Complaints at RERA Karnatakaon this registration
Jump to the 42 documents Report an error

Brigade Atmosphere- Phase 1 is a Residential/Group Housing project by Brigade Enterprises Ltd in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/303/PR/170916/000497 on 16 Sep 2017. Possession is promised by 28 Feb 2020. 3 complaints are on record with the regulator.

At a glance

Project

  • NameBrigade Atmosphere- Phase 1
  • TypeResidential/Group Housing
  • Location
    • Devanahalli
    • Bengaluru Rural
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1250/303/PR/170916/000497
  • ReraGenie IDRG-KA-88681

Builder

  • NameBrigade Enterprises Ltd
  • Entity typeCompany
  • CINL85110KA1995PLC019126
  • Authorized SignatoryViswa Prathap Desu
  • OthersBalasubramaniam M.N, Adil Singh Chhachhi, Kakoli Dey, Gopinath Reddy
  • Other registrations45 more →
  • No longer live1 withdrawn or revoked
  • Declared earlier projects67 →

Key dates

this monthRegisteredSep 2017PromisedFeb 2020

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on16 Sep 2017
  • Promised completion28 Feb 2020
  • Revised completionNone
  • Buildings8 building records
  • Documents filed42 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---404
B---808
C---404
D---808
E---808
F---606
G---808
H---404

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionYes-
StaircasesNoNot applicable
LiftsNoNot applicable
Staircases and Lift lobbies, corridor,lobbies, corridorNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceNoNot applicable
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area24,279 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 55.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr.Abhay Itty Zachariah
EngineerMr. Vinod

Complaints filed with RERA Karnataka3

Case no.ComplainantRespondentFiled
00666/2023-Brigade Enterprises Ltd04/05/2023
00986/2023-Brigade Enterprises Ltd27/06/2023
00036/2024-Brigade Enterprises Ltd10/01/2024

Documents filed42

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/303/PR/170916/000497 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Certificate of Incorporation - BEL.PDF-
CC cum Plan Sanction_CTC_Atmosphere1-
Site and Section Plan_CTC_Atmosphere-
DP_CTC_Atmosphere-
Sale deed draft from RERA-
Agreements from RERA-
Title Opinion_CTC_Atmosphere1-
Site and Section Plan_CTC_Atmosphere-
DP_CTC_Atmosphere-
Allotment Atmosphere-
Atmosphere-
All NOC_CTC_Atmosphere1-
Atmosphere - Specifications-
EC_Atmosphere_CTC-
Brigade Atmosphere - AAI-
Brigade Atmosphere - Water NOC-
Brigade Atmosphere - KSPCB-
Balance Sheet 2015 - 2016File: Balance Sheet - 31-03-2016.pdf-
Balance Sheet 2014 - 2015File: Balance Sheet - 31-03-2015.pdf-
Balance Sheet 2013 - 2014File: Balance Sheet - 31-03-2014.pdf-
Audited Profit and Loss Statement 2015 - 2016File: P&L Account - 31-03-2016.pdf-
Audited Profit and Loss Statement 2014 - 2015File: P&L Account - 31-03-2015.pdf-
Audited Profit and Loss Statement 2013 - 2014File: P&L Account - 31-03-2014.pdf-
Director's Report 2015 - 2016File: Director's Report 2015-16.pdf-
Director's Report 2014 - 2015File: Director's Report 2014-15.pdf-
Director's Report 2013 - 2014File: Director's Report 2013-14.pdf-
Cash Flow Statement 2015 - 2016File: Cash Flow Statement - 31-03-2016.pdf-
Cash Flow Statement 2014 - 2015File: Cash Flow Statement - 31-03-2015.pdf-
Auditor's Report 2015 - 2016File: Auditor's Report - 31-03-2016.pdf-
Auditor's Report 2014 - 2015File: Auditor's Report - 31-03-2015.pdf-
Auditor's Report 2013 - 2014File: Auditor's Report - 31-03-2014.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: BEL_ ITR V - FY 15-16.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: BEL_ITR V_FY14-15.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: ITR - V aknowledgment-AY 2013-14.pdf-
Form B-
Prospectus/BrochureFile: Atmosphere Brochure 10x10 Ref.pdf-
Advertisement Copy 1File: Marketing - No Ad.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1250_303_PR_170916_000497.xlsx-
Occupancy CertificateFile: Brigade Atmosphere - Partial Occupancy Certificate.pdf-
Completion certificateFile: Brigade Atmosphere - Partial Occupancy Certificate.pdf-
Registered Agreement of SaleFile: Sale Agreement- Atmosphere.pdf-
Registered conveyance deed for an individual unitFile: Sale Deed.pdf-

Promoter's earlier projects37

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

15 not delivered by the promised date22 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
World Trade Centre Kochi- Phase 2-OngoingJul 2017Not delivered
Signature Towers-OngoingJul 2017Not delivered
Plumeria Phase 1 at Brigade Meadows-OngoingJul 2017Not delivered
Pearl at Palmgrove-Apartment-OngoingJul 2017Not delivered
Brigade Xanadu- Phase 1-OngoingJul 2017Not delivered
Brigade Symphony-A-OngoingJul 2017Not delivered
Brigade Panaroma-OngoingJul 2017Not delivered
Brigade Opus-OngoingJul 2017Not delivered
Brigade Mountain View-OngoingJul 2017Not delivered
Brigade Lakefront - Crimson-OngoingJul 2017Not delivered
Brigade Lakefront - Blue-OngoingJul 2017Not delivered
Brigade Exotica - Burgandy-OngoingJul 2017Not delivered
Brigade Buena Vista- Phase 1-OngoingJul 2017Not delivered
Brigade At No 7-OngoingJul 2017Not delivered
Brigade 7 Gardens-OngoingJul 2017Not delivered
World Trade Centre Kochi- Phase 1-Completed-No date filed
Wisteria at Brigade Meadows-Completed-No date filed
Villas @ Palmgrove-Completed-No date filed
Nalapad Brigade Centre-Completed-No date filed
Nalapad Brigade Broadway-Completed-No date filed
Brigade Vantage-Completed-No date filed
Brigade Symphony-B and C-Completed-No date filed
Brigade Serenity-Completed-No date filed
Brigade Pinnacle-Completed-No date filed
Brigade Omega-Completed-No date filed
Brigade Northridge - Phase I-Completed-No date filed
Brigade Meadows Phase 1-Completed-No date filed
Brigade Magnum-Completed-No date filed
Brigade Lakefront - Amber-Completed-No date filed
Brigade IRV Centre-Completed-No date filed
Brigade Golden Triangle-Completed-No date filed
Brigade Gardenia Annex-Completed-No date filed
Brigade Exotica - Azure-Completed-No date filed
Brigade Caladium-Completed-No date filed
Brigade Bhuwalka Icon-Completed-No date filed
Brigade Altamont-Completed-No date filed
Arcade at B. Meadows-Completed-No date filed

How this compares with Bengaluru Rural

20%of Bengaluru Rural projects moved their completion datethis one has not
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep Brigade Atmosphere- Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

Builder: Brigade Enterprises Ltd

Brigade Enterprises Ltd has 46 registrations on RERA Karnataka, including Brigade Oasis - Phase 1 and Brigade Atmosphere- Phase 1. Its filings declare 67 earlier projects, 41 of them declared completed. Litigation is declared on 10 of its registrations. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if Brigade Atmosphere- Phase 1 is delayed beyond 28 Feb 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Brigade Atmosphere- Phase 1?

The registered promoter entity is Brigade Enterprises Ltd, a company as per the filing. Its CIN L85110KA1995PLC019126 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Brigade Atmosphere- Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Brigade Atmosphere- Phase 1?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Brigade Atmosphere- Phase 1?

The professionals named in the filing: Architect: Ar.Abhay Itty Zachariah; Engineer: Mr. Vinod. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Brigade Atmosphere- Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Brigade Atmosphere- Phase 1. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Brigade Atmosphere- Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.