BHUMI LAND
By BHUMI LANDS
RG-MH-00936 · RERA P50300006469 · Last updated on MahaRERA portal: 26 Oct 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 19 months past the filed date
- Completion date moved by 54 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Amravati registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
BHUMI LAND is a Residential / Group Housing project by BHUMI LANDS in Amravati, Maharashtra, registered with MahaRERA as P50300006469 on 14 Aug 2017. Possession was promised by 31 Mar 2025 and is now 19 months past that date. The completion date has moved by 54 months from the original filing.
At a glance
Project
- NameBHUMI LAND
- TypeResidential / Group Housing
- Location
- Achalpur (M Cl)
- Achalpur
- Amravati
- 444801
- Pincode444801
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50300006469
- ReraGenie IDRG-MH-00936
Builder
- NameBHUMI LANDS
- Entity typePartnership
- PartnerCHANDRABHAN KISANCHAND DEMBLA
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on14 Aug 2017
- Promised completion31 Mar 2025
- Revised completionRevised to 31 Mar 2025 (originally 30 Sep 2020)
- Buildings1 building record
- Documents filed136 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BHUMI LAND | NA | 67 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 26 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 92%.
BHUMI LAND: 75% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 88% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 92% |
| Sanitary Fittings within the flats / premises | 85% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 89% |
Progress on shared amenities15
As on 26 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed18
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SURAJ CHANDRABHAN DEMBLA | Amravati (M Corp.) | Amravati |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ARUN BIJWE |
| Engineer | ARUN SITARAM BIJWE |
| Partner | Role in project |
|---|---|
| BHUMI LANDS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter01.THE PLAN WAS REVISED AND GOT APPROVAL ON 27-12-2022 . 02.DUE TO CORONA THE WORK WAS EXTENDED AND ALSO LABOUR PROBLEM FACED IN PROJECT. 03.CONTRACTORS LEFT OUT IN CORONA PERIOD. 04. WE HAVE NOT SOLD ANY UNITS IN THE PROJECT. 05. PROMOTER HAVE COMPLETED THE PROJECT, DUE TO NON SALES PROMOTER IS IN FINANCIAL STRESS.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 10 Aug 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Aug 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 10 Aug 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 16 Jan 2024
Documents filed136
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 136 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Declaration in FORM BFile: bhumi_Form B.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A-Dec 17.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A-Dec 18.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A-Dec 19.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A-Dec 20.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 5 A-Dec 21.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 8 A-Jun 22.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 9 A-June 18.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 10 A-June 19.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 11 A-June 20.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 12 A-June 21.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 13 A-June 23.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 14 A-Mar 18.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 15 A-Mar 19.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 16 A-Mar 20.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 17 A-Mar 21.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 18 A-Mar 22.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 19 A-Mar 23.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20 A-Mar 24.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 21 A-Sep 18.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 22 A-Sep 19.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 23 A-Sep 20.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 24 A-Sep 21.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 25 A-Sep 22.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 26 A-Sep 23.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 27 A-Sept 17.pdf | 26 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Bhumi_Form 1.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_300917.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_311217.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_310318.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_300618.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_300918.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_311218.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_310319.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_300619.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_300919.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_311219.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_310320.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_300620.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_300920.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_311220.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_310321.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_300621.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_300921.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_311221.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_310322.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_300622.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_300922.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_311222.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_310323.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_300623.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_300923.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_311223.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi Land_Form 3_310324.pdf | 26 Oct 2024 |
| Certificates of CA (Form 3)File: Bhumi_Form 3.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 6 A-Dec 22.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 13 A-June 23.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_Dec 17.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_Dec 18.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_Dec 19.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_Dec 20.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_Dec 21.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_Dec 22.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_Dec 23.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_June 18.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_June 19.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_June 20.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_June 21.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_June 22.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_June 23.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_Mar 18.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_Mar 19.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_Mar 20.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_Mar 21.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_Mar 22.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_Mar 23.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_Mar 24.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_Sep 17.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_Sep 18.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: E_Sep 19.pdf | 26 Oct 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Amravati
Computed across the 450+ Amravati projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 136 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep BHUMI LAND on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Achalpur (M Cl)450+ in Amravati
SHRI GURU ANAND DHAM
Sudhir Rameshrao Wakode
Radha City
Krishnagiri Developers
Radha City
Rahul sharma And Yogesh Gawande
SHREE GURU ANAND DHAM PHASE 2
YOGIRAJ BUILDERS
Shri Guru Plaza
Shree Gajanan Infra
Orange City Centre
GAURINIDHI INFRAVENTURES LLP
See every Amravati project, with the district possession charts
Builder: BHUMI LANDS
BHUMI LANDS has 1 registration on MahaRERA, including BHUMI LAND. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Amravati district page.
Frequently asked questions
What does it mean that BHUMI LAND shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if BHUMI LAND is delayed beyond 31 Mar 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of BHUMI LAND?
The registered promoter entity is BHUMI LANDS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in BHUMI LAND?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for BHUMI LAND?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at BHUMI LAND?
The professionals named in the filing: Architect: ARUN BIJWE; Engineer: ARUN SITARAM BIJWE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in BHUMI LAND?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback