ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / BHOOMI ICON

Registration lapsed No litigation declared Others project

BHOOMI ICON

By FORNAX REALTY

RG-MH-28570 · RERA P51700026412 · Last updated on MahaRERA portal: 31 Jul 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
9 of 11Construction stages donefurthest along: Basement (if any), 0%
24 of 88Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 186 documents Report an error

BHOOMI ICON is a Others project by FORNAX REALTY in Thane, Maharashtra, registered with MahaRERA as P51700026412 on 17 Sep 2020. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 24 months from the original filing. 64 of the 88 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameBHOOMI ICON
  • TypeOthers
  • Location
    • PLOT NO 28A
    • SECTOR 9
    • KOPAR KHAIRANE
    • Navi Mumbai (M Corp.)
    • Thane
    • 400709
  • Pincode400709
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700026412
  • ReraGenie IDRG-MH-28570

Builder

  • NameFORNAX REALTY
  • Entity typePartnership
  • GSTIN27AAFFF7323N1Z3
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersJASAWANTKUMAR SOHANLAL JAIN, AMBALAL JIVAN CHAMARIYA, PUNJA NARAN MENAT
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

4 months past promisethis monthRegisteredSep 2020First promiseJun 2024Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on17 Sep 2020
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2024)
  • Buildings1 building record
  • Documents filed186 files

Current status

73%64 of 88 units booked
100.0%Work done, per cost certificate

Figures as on 31 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BHOOMI ICONNA2020682088

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 31 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

BHOOMI ICON: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 31 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,380 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on29 May 2026
LandownerVillageDistrict
PINJA NARAN MENATNavi Mumbai (M Corp.)Thane
JASWANTKUMAR SOHANLAL JAINNavi Mumbai (M Corp.)Thane
AMBALAL JIVAN CHAMARIYANavi Mumbai (M Corp.)Thane

Approvals and building plan

Sanctioning authorityNMMC CIDCO
Permissible FSI6638.07
Proposed, not sanctioned5,597 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSATRA PLAZA VASHI NAVI MUMBAI
Estimated costRs 35.65 cr
Cost incurredRs 35.65 cr
Work done100.0%
BuildingWingEstimatedIncurred
BHOOMI ICONNARs 31.88 crRs 31.88 cr
-NARs 3.77 crRs 3.77 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectATUL PATEL ARCHITECTS
ArchitectATUL PATEL
EngineerA G GOKHALE and ASSOCIATES
Chartered AccountantVISHAL SHETHIYA
Chartered AccountantPINKY JHA
PartnerRole in project
FORNAX REALTY-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700018786Jun 2024 → Jun 2025

Reason as filed by the promoterRespected Sir, We hereby apply for extension of project called “BHOOMI ICON” registered with the regulatory authority bide project registration certificate bearing No. P51700026412 which expires on 30.06.2024. We are writing to inform you that we have received the revised Commencement Certificates for the construction of our Residential cum Commercial building project. The first Commencement Certificate is dated 30.03.2022, indicating the construction of a 14-floor building with 52 Residential Units, 10 Commercial Shops, and 9 Offices. The revised Commencement Certificate, dated 27.04.2023, pe

EA16062501612Jun 2024 → Jun 2026

Reason as filed by the promoterBuilding is almost Complete. We need some more time for completion and obtaining occupancy certificate from competent authorities.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Sep 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Nov 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Sep 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed186

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 186 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 - Q4 31 03 2026.pdf31 Jul 2026
Withdrawal Update Form 2File: FORM 2 - Q4 31 03 2026.pdf31 Jul 2026
Withdrawal Update Form 3File: FORM 3 - Q4 31 03 2026_compressed.pdf31 Jul 2026
Withdrawal Update Form 1File: FORM 1 as on 31 12 2025.pdf29 May 2026
Withdrawal Update Form 2File: FORM 2 Q3 31 12 2025.pdf29 May 2026
Withdrawal Update Form 3File: FORM 3 29 05 2026_compressed.pdf29 May 2026
Withdrawal Update Form 1File: FORM 1 as on 31 12 2025.pdf23 Feb 2026
Withdrawal Update Form 2File: FORM 2 Q3 31 12 2025.pdf23 Feb 2026
Withdrawal Update Form 3File: FORM 3 as on 31 12 25 Q3.pdf23 Feb 2026
Withdrawal Update Form 1File: FORM 1 Q2 30 09 2025.pdf3 Jan 2026
Withdrawal Update Form 2File: FORM 2 Q2 30 09 2025.pdf3 Jan 2026
Withdrawal Update Form 3File: FORM 3 Q2 30 09 2025.pdf3 Jan 2026
Withdrawal Update Form 1File: FORM 1 Q2 30 09 2025.pdf27 Dec 2025
Withdrawal Update Form 2File: FORM 2 Q2 30 09 2025.pdf27 Dec 2025
Withdrawal Update Form 3File: FORM 3 Q2 30 09 2025.pdf27 Dec 2025
Withdrawal Update Form 1File: FORM 1 Q2 30 09 2025.pdf26 Dec 2025
Withdrawal Update Form 1File: FORM 1 Q2 30 09 2025.pdf26 Dec 2025
Withdrawal Update Form 2File: FORM 2 Q2 30 09 2025.pdf26 Dec 2025
Withdrawal Update Form 2File: FORM 2 Q2 30 09 2025.pdf26 Dec 2025
Withdrawal Update Form 3File: FORM 3 Q2 30 09 2025.pdf26 Dec 2025
Withdrawal Update Form 3File: FORM 3 Q2 30 09 2025.pdf26 Dec 2025
Withdrawal Update Form 1File: FORM 1 - Q1 30 06 2025.pdf3 Dec 2025
Withdrawal Update Form 2File: FORM 2 30 06 2025.pdf3 Dec 2025
Withdrawal Update Form 3File: Form 3 30 06 2025.pdf3 Dec 2025
Form 1File: Form 1 31 03 2023.pdf3 Jul 2025
Form 2File: Form 2 31 03 2023.pdf3 Jul 2025
Form 3File: Form 3 CA CERTIFICATE 31 03 2023.pdf3 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY 31 03 2023.pdf3 Jul 2025
Form 1File: Form 1 31 12 2022.pdf3 Jul 2025
Form 2File: Form 2 31 12 2022.pdf3 Jul 2025
Form 3File: Form 3 31 12 2022.pdf3 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY 31 12 2022.pdf3 Jul 2025
Form 1File: Form 1 30 09 2022.pdf3 Jul 2025
Form 2File: Form 2 30 09 2022.pdf3 Jul 2025
Form 3File: Form 3 30 09 2022.pdf3 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY 30 09 2022.pdf3 Jul 2025
Form 1File: Form 1 30 06 2022.pdf3 Jul 2025
Form 2File: Form 2 30 06 2022.pdf3 Jul 2025
Form 3File: Form 3 30 06 2022.pdf3 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY 30 06 2022.pdf3 Jul 2025
Form 2A (FY 2024-2025)File: FORM 2A Quality Assurance certificate NEW 31.03.2024.pdf3 Jul 2025
Form 5 (FY 2020-2021)File: Form 5 31 03 2021.pdf3 Jul 2025
Form 5 (FY 2021-2022)File: Form 5 31 03 2022.pdf3 Jul 2025
Form 5 (FY 2022-2023)File: Form 5 31 03 2023.pdf3 Jul 2025
Form 1File: FORM 1 as on 30 06 2024.pdf2 Jul 2025
Form 2File: FORM 2 as on 30 06 2024.pdf2 Jul 2025
Form 3File: Form 3 as on 30 06 2024_compressed.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD INVENTORY 30 06 2024.pdf2 Jul 2025
Self-declaration of Quarterly ProgressFile: Self Declaration 30 06 2024.pdf2 Jul 2025
Form 1File: FORM 1 as on 30 09 2024.pdf2 Jul 2025
Form 2File: FORM 2 ENGINEERS CERTIFICATE 30 09 2024.pdf2 Jul 2025
Form 3File: FORM 3 Q2 30 09 2024_11zon.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD INVENTORY 30 09 2024.pdf2 Jul 2025
Self-declaration of Quarterly ProgressFile: Self Declaration 30 09 2024.pdf2 Jul 2025
Form 1File: FORM 1 as on 31 12 2024.pdf2 Jul 2025
Form 2File: FORM 2-Engineer's Certificate 31 12 2024.pdf2 Jul 2025
Form 3File: FORM 3 - 31 12 2024_11zon.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD INVENTORY 31 12 2024.pdf2 Jul 2025
Self-declaration of Quarterly ProgressFile: Self Declaration 31 12 2024.pdf2 Jul 2025
Form 1File: FORM 1 30 06 2023.pdf2 Jul 2025
Form 2File: FORM 2 30 06 2023.pdf2 Jul 2025
Form 3File: Form 3 30 06 2023.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY 30 06 2023.pdf2 Jul 2025
Form 1File: Form 1 30 09 2023.pdf2 Jul 2025
Form 2File: Form 2 30 09 2023.pdf2 Jul 2025
Form 3File: Form 3 30 09 2023.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD INVENTORY 30 09 2023.pdf2 Jul 2025
Form 1File: Form 1 31 12 2023.pdf2 Jul 2025
Form 2File: Form 2 31 12 2023.pdf2 Jul 2025
Form 3File: FORM 3_as on 31 12 2023.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD INVENTORY 31 12 2023.pdf2 Jul 2025
Form 1File: Form 1 31 03 2024.pdf2 Jul 2025
Form 2File: FORM 2 31 03 2024.pdf2 Jul 2025
Form 3File: FORM 3 as on 31 03 2024.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD INVENTORY 31 03 2024.pdf2 Jul 2025
Form 2A (FY 2022-2023)File: FORM 2A Quality Assurance certificate NEW 31.03.2024.pdf2 Jul 2025
Form 2A (FY 2023-2024)2 Jul 2025
Form 5 (FY 2024-2025)File: Form 5 - as on 31 03 2025.pdf1 Jul 2025
Form 5 (FY 2023-2024)File: FORNAX REALTY FORM 5 AS ON 31 03 2024.pdf1 Jul 2025
Form 1File: FORM 1 as on 31 03 2025.pdf5 Jun 2025

How this compares with Thane

73%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 24 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BHOOMI ICON on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KOPAR KHAIRANE7,600+ in Thane

2 kmBHOOMI ICONCompleted 15Lapsed / revoked 6Other 33Dot size: filed unitsN

Filed coordinates, straight-line distance. 54 registered projects within 2 km.

Builder: FORNAX REALTY

FORNAX REALTY has 2 registrations on MahaRERA, including BHOOMI ICON and BHOOMI ICON WING B. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that BHOOMI ICON shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if BHOOMI ICON is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BHOOMI ICON?

The registered promoter entity is FORNAX REALTY, a partnership as per the filing. Its GSTIN 27AAFFF7323N1Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BHOOMI ICON?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BHOOMI ICON?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BHOOMI ICON?

The professionals named in the filing: Architect: ATUL PATEL ARCHITECTS; Architect: ATUL PATEL; Engineer: A G GOKHALE and ASSOCIATES; Chartered Accountant: VISHAL SHETHIYA; Chartered Accountant: PINKY JHA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BHOOMI ICON?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BHOOMI ICON. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BHOOMI ICON to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.