Home / Browse projects / Pune, Maharashtra / BHIDE NIVARA

Registered No litigation declared Others project

BHIDE NIVARA

By SIDDHIVINAYAK VENTURES

RG-MH-05578 · RERA P52100055983 · Last updated on MahaRERA portal: 1 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
6 of 11Construction stages donefurthest along: Internal walls, 95%
23 of 38Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 66 documents Report an error

BHIDE NIVARA is a Others project by SIDDHIVINAYAK VENTURES in Pune, Maharashtra, registered with MahaRERA as P52100055983 on 2 May 2024. Possession is promised by 30 Dec 2027. 15 of the 38 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameBHIDE NIVARA
  • TypeOthers
  • Location
    • TALEGAON CHAKAN ROAD
    • TALEGAON
    • Talegaon Dabhade (M Cl)
    • Mawal
    • Pune
    • 410507
  • Pincode410507
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100055983
  • ReraGenie IDRG-MH-05578

Builder

  • NameSIDDHIVINAYAK VENTURES
  • Entity typePartnership
  • PartnerVINOD ASHOK NAIDU
  • Declared earlier projects1 →

Key dates

this monthRegisteredMay 2024PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on2 May 2024
  • Promised completion30 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed66 files

Current status

39%15 of 38 units booked
96.8%Work done, per cost certificate

Figures as on 1 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BHIDE NIWARANA86221638

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

BHIDE NIWARA: 81% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 1 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed8

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots8
Closed/Covered8

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area629 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on8 Nov 2025
LandownerVillageDistrict
BHIDE NIVARA CO OP HOUSING SOC .LTDTalegaon Dabhade (M Cl)Pune

Approvals and building plan

Sanctioning authorityTALEGAON DABHADE MUNCIPAL COUNCIL
Permissible FSI1972.0
Proposed, not sanctioned1,972 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 1,2 SHRINATHJI BUILDING,CHAKAN ROAD ,TALEGAON DABHADE ,PUNE ,410507
Estimated costRs 5.58 cr
Cost incurredRs 5.40 cr
Work done96.79%
BuildingWingEstimatedIncurred
BHIDE NIWARANARs 5.38 crRs 5.30 cr
-NARs 20.00 lakhRs 10.00 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDNYANESH BHEGADE
EngineerSHUBHAM BAGAL
Chartered AccountantKUNAL PILLAY
Chartered AccountantASHISH UDAVANT
PartnerRole in project
SIDDHIVINAYAK VENTURES-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Apr 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Mar 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2027

Documents filed66

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Q4 form 1 siddhivinayk.pdf1 May 2026
Withdrawal Update Form 2File: Q 4 FORM 2 SIDDHIVINAYAK.pdf1 May 2026
Withdrawal Update Form 3File: Q4 form 3 siddhivinayk.pdf1 May 2026
Withdrawal Update Form 1File: form 1 bhide nivara.pdf1 Apr 2026
Withdrawal Update Form 2File: form 2 bhide nivara.pdf1 Apr 2026
Withdrawal Update Form 3File: form 3 bhide nivara.pdf1 Apr 2026
Form 1File: ARCT 1.pdf20 Jan 2026
Form 2File: FORM 2 ENGG.pdf20 Jan 2026
Form 3File: FORM 3.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: SOLD BOOK.pdf20 Jan 2026
Form 1File: ARCT 1.pdf20 Jan 2026
Form 2File: ENGG FORM 2.pdf20 Jan 2026
Form 3File: Form-3 - Bhide Nivara.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: SOLD BOOK.pdf20 Jan 2026
Withdrawal Update Form 1File: form 1 bhide nivara.pdf20 Jan 2026
Withdrawal Update Form 2File: form 2 bhide nivara.pdf20 Jan 2026
Withdrawal Update Form 3File: form 3 bhide nivara.pdf20 Jan 2026
Form 1File: form 1 siddhivinayak.pdf14 Oct 2025
Form 2File: form 2siddhivinayk.pdf14 Oct 2025
Form 3File: FORM-3 Bhide Nivara Q3 2025 (2).pdf14 Oct 2025
Disclosure of Sold and Booked InventoryFile: SOLD BOOK Q 3 2025 (1).pdf14 Oct 2025
Form 1File: form 1 siddhivinayak.pdf21 Jul 2025
Form 2File: form 2 siddhivinayak.pdf21 Jul 2025
Form 3File: form 3 siddhivinayk.pdf21 Jul 2025
Disclosure of Sold and Booked InventoryFile: Q 1 APRIL TO JUNE SOLD UNSOLD.pdf21 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: BHIDE _page-0001.pdf25 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCT 1.pdf23 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 - Bhide Nivara - Q1 - 2025 _page-0001.pdf23 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG FORM 2.pdf23 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD BOOK Q 3 2025.pdf23 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCT 1 Q 3 2024.pdf14 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 OCT TO DEC_compressed (1).pdf14 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGG OCT TO DEC.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: SOLD BOOK Q 3 2025.pdf14 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCT FORM 1 Q JULY TO SEPT.pdf23 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Bhide Nivara (Q3 2024)_compressed.pdf23 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG FORM 2 Q 2 JULY TO SEPT 2024.pdf23 Oct 2024
Disclosure of sold/ booked inventoryFile: SOLD BOOK Q 2 JULY TO SEP 2024.pdf23 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCT FORM 1 Q 1 APRIL TO JUNE.pdf8 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA Q 1 BHIDE NIVARA.pdf8 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG FORM 2 Q 1 APRIL TO JUNE.pdf8 Oct 2024
Disclosure of sold/ booked inventoryFile: SOLD BOOK Q 1 2024.pdf8 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form- 3 Bhide Nivara_page-0001.pdf12 Apr 2024
Other - TechnicalFile: GetUserDocumentFileContent (2).pdf12 Apr 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 111.pdf11 Apr 2024
Copy of the legal title reportFile: Search Rera Bhide Niwara-signed (1)_compressed.pdf5 Apr 2024
Other - LegalFile: CC MAIL NAIDU.pdf5 Apr 2024
Other - TechnicalFile: CC MAIL NAIDU.pdf5 Apr 2024
Layout approvalFile: SANCTION PLAN BHIDENIVARA (2)_compressed (1).pdf27 Mar 2024
Building plan approvalFile: SANCTION PLAN BHIDENIVARA (2)_compressed (1).pdf27 Mar 2024
PAN CardFile: siddhivinay pan (1).pdf27 Mar 2024
Details of encumbrances concerned to FinanceFile: Details of encumbrances kakade swpnshilp.pdf27 Mar 2024
Details of encumbrances concerned to LegalFile: Details of encumbrances kakade swpnshilp.pdf27 Mar 2024
Copy of Layout Approval (in case of layout)File: SANCTION PLAN BHIDENIVARA (2)_compressed (1).pdf27 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: SANCTION PLAN BHIDENIVARA (2)_compressed (1).pdf27 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: COmmencement Bhidenivara (1).pdf27 Mar 2024
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf27 Mar 2024
Declaration in FORM BFile: form b promotar.pdf27 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 siddhivinayak.pdf27 Mar 2024
CERSAI detailsFile: CERSAIL REPORT.pdf27 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations - Copy.pdf27 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf27 Mar 2024
Proforma of Agreement for saleFile: Bhide Niwara AGG DRAFT.pdf27 Mar 2024
Proforma of Allotment letterFile: Allotment Letter - DRAFT.pdf27 Mar 2024
Deviation Report with respect to Allotment letterFile: DEVIATION SHEET.pdf27 Mar 2024
Deviation Report with respect to model copy of AgreementFile: DEVIATION SHEE1.pdf27 Mar 2024

How this compares with Pune

39%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BHIDE NIVARA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near TALEGAON13,700+ in Pune

2 kmBHIDE NIVARACompleted 57Lapsed / revoked 40Other 46Dot size: filed unitsN

Filed coordinates, straight-line distance. 143 registered projects within 2 km.

Builder: SIDDHIVINAYAK VENTURES

SIDDHIVINAYAK VENTURES has 1 registration on MahaRERA, including BHIDE NIVARA. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if BHIDE NIVARA is delayed beyond 30 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BHIDE NIVARA?

The registered promoter entity is SIDDHIVINAYAK VENTURES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BHIDE NIVARA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BHIDE NIVARA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BHIDE NIVARA?

The professionals named in the filing: Architect: DNYANESH BHEGADE; Engineer: SHUBHAM BAGAL; Chartered Accountant: KUNAL PILLAY; Chartered Accountant: ASHISH UDAVANT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BHIDE NIVARA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BHIDE NIVARA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BHIDE NIVARA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.