ReraGenieLog inGet a buyer report

Home / Browse projects / Mysore, Karnataka / Bhavani Enclave

Registration approved No litigation declared Plotted Development project

Bhavani Enclave

By K Mahadevamma

RG-KA-42284 · RERA PRM/KA/RERA/1268/378/PR/041123/006374 · Last updated on RERA Karnataka portal: 26 Oct 2023

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Oct 2024Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 67 documents Report an error

Bhavani Enclave is a Plotted Development project by K Mahadevamma in Mysore, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1268/378/PR/041123/006374 on 4 Nov 2023. Possession is promised by 30 Oct 2024.

At a glance

Project

  • NameBhavani Enclave
  • TypePlotted Development
  • Location
    • MYSORE
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1268/378/PR/041123/006374
  • ReraGenie IDRG-KA-42284

Builder

  • NameK Mahadevamma
  • Entity typeProprietorship
  • Authorized SignatoryK MAHADEVAMMA

Key dates

this monthRegisteredNov 2023PromisedOct 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on4 Nov 2023
  • Promised completion30 Oct 2024
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed67 files

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners1
LandownerVillageDistrict
K Mahadevamma--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 75.00 lakh
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 50.79 lakh-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 13.52 lakh-
Outgoing Payment made to (Like, WaterSupply, power etc.)Rs 8.12 lakh-
Payment of taxesRs 1.28 lakh-
Payment of feesRs 40,000-
On-site expenditure-Consultants FeesRs 39,000-
Payment of chargesRs 30,000-
On-site expenditure-Salaries of workersRs 14,000-
On-site expenditure-Site OverheadRs 6,000-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerNataraju V
Chartered AccountantChetan Bhati

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed67

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1268/378/PR/041123/006374 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Documents relating to Acquisition notificationFile: Land acquisition details.pdf26 Oct 2023
Total estimated cost of the project is not matched with CA certificate - attached Form 1File: Form 1.pdf17 Oct 2023
Sources of funds proofFile: Sources of funds proof.pdf17 Oct 2023
Layout planFile: Plan approval v1.pdf17 Oct 2023
Work OrderFile: Work order.pdf17 Oct 2023
CDP mapFile: 101 CDP.pdf17 Oct 2023
self-attested copy of the Engineer license certificateFile: Engineer Registration certificate self attested.pdf17 Oct 2023
Engineer certificate in the prescribed format in form 6File: Form 6.pdf17 Oct 2023
Self Attested Electricity board NOCFile: Self attested Electricity board NOC.pdf17 Oct 2023
Self Attested Water Board NOCFile: Water board NOC Self attested.pdf17 Oct 2023
Updated Agreement for SaleFile: Updated Agreement for sale.pdf17 Oct 2023
Updated Proforma of Allotment letterFile: Updated Allotment letter.pdf17 Oct 2023
STP/Septic Tank, Soak pit, and sewer line drawing certified by the Engineer along with the demarcatiFile: STP Septic Tank, Soak pit, and sewer line.pdf17 Oct 2023
Land cost calculation sheet as per the guidance valueFile: Land cost calculation sheet.pdf17 Oct 2023
Guideline value by subregistrarFile: Guidance value.pdf17 Oct 2023
Source of Water supply - BorewellFile: bore.pdf17 Oct 2023
Replies to Rera QueryFile: Replies to RERA Query.pdf17 Oct 2023
RTC, survey 101/2-
Mutation, survey 101/2-
Encumbrance Certificate, survey 101/2-
Conversion/Alienation Order, survey 101/2-
Sale/Title/Gift Deed, survey 101/2-
Khatha, survey 101/2-
Registration CertificateFile: Udyam Registration certificatev1.pdf-
Certificate issued by CA Form 1File: Form 1.pdf-
Certificate issued by Engineer Form 3File: Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
AffidavitFile: Non litigation of land affidavit.pdf-
Certificate from Chartered AccountFile: Non withdrawal of funds certificate.pdf-
Certificate issued by ArchitectFile: Architect Certificate.pdf-
Balance Sheet 2022 - 2023File: Balance sheet.pdf-
Balance Sheet 2021 - 2022File: Balance sheet.pdf-
Balance Sheet 2020 - 2021File: Balance sheet.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Profit and loss account.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Profit and Loss account.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITR V and COmputaiton.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR V and Computation.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR V.pdf-
Work order-
Electricity board NOC-
Water board NOC-
Plan approval v1-
Plan approval v1-
Plan approval v1-
Plan approval v1-
Project specification-
Plan approval v1-
Plan approval v1-
Legal Scrutiny report-
Alienation order-
Alienation order-
Sale deed in favour of Mahadevamma-
Profarma of Agreement for sale-
Profarma of allotment letter-
Form b-
Section 3 Affidavit-
Electricity board NOC-
Water board NOC-
Relinquishment deed-
Village map-
UGD Demarcation-
Bhavani Enclave-
Guidance value-
Detailed estimation and Project specification-
Technical Order-
Plot Excel SheetFile: Bhavani Enclave.xlsx-

How this compares with Mysore

28%of Mysore projects moved their completion datethis one has not
0%of Mysore registrations are shown as withdrawn or revokedthis one is not

Computed across the 700+ Mysore projects on ReraGenie, from their own filings.

Keep Bhavani Enclave on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Mysore700+ in Mysore

Builder: K Mahadevamma

K Mahadevamma has 1 registration on RERA Karnataka, including Bhavani Enclave. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Mysore district page.

Frequently asked questions

What are my rights if Bhavani Enclave is delayed beyond 30 Oct 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Bhavani Enclave?

The registered promoter entity is K Mahadevamma, a proprietorship as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Bhavani Enclave?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Bhavani Enclave?

The professionals named in the filing: Engineer: Nataraju V; Chartered Accountant: Chetan Bhati. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Bhavani Enclave?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Bhavani Enclave. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Bhavani Enclave to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.