Home / Browse projects / Bengaluru Urban, Karnataka / Bhartiya Leela Residences

Registration approved Commercial project

Bhartiya Leela Residences

By Bhartiya Urban Private Limited

RG-KA-65321 · RERA PRM/KA/RERA/1251/309/PR/171015/000184 · Last updated on RERA Karnataka portal: 2 Oct 2021

Source: official RERA Karnataka filing

Red flags

  • 3 complaints at RERA Karnataka
  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • Separate project account declared
Jun 2022Possession promisedmoved 21 months from the original
3Complaints at RERA Karnatakaon this registration
Jump to the 158 documents Report an error

Bhartiya Leela Residences is a Commercial project by Bhartiya Urban Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/171015/000184 on 15 Oct 2017. Possession is promised by 30 Jun 2022. The completion date has moved by 21 months from the original filing. 3 complaints are on record with the regulator.

At a glance

Project

  • NameBhartiya Leela Residences
  • TypeCommercial
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/309/PR/171015/000184
  • ReraGenie IDRG-KA-65321

Builder

  • NameBhartiya Urban Private Limited
  • Entity typeCompany
  • CINU45200TN2008PTC103956
  • Authorized SignatoryArjun Aggarwal
  • DirectorsSnehdeep Aggarwal, Arjun Aggarwal
  • Other registrations7 more →
  • Declared earlier projects7 →

Key dates

this monthRegisteredOct 2017First promiseSep 2020Revised toJun 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on15 Oct 2017
  • Promised completion30 Jun 2022
  • Revised completionRevised to 30 Jun 2022 (originally 30 Sep 2020)
  • Buildings3 building records
  • Documents filed158 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---1120112
B---32032
C---32032

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 2 Oct 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 2 Oct 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionYes-
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,919 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 242.95 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRSP Design Consultants (India) Pvt Ltd
EngineerInnotech Engineering Consult Pvt Ltd

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionSep 2020 → Jun 2021

No reason recorded in the filing

EX/PRM/KA/RERA/1251/309/PR/220413/000184Jun 2021 → Jun 2022

Reason as filed by the promoterShortage of Labour

Complaints filed with RERA Karnataka3

Case no.ComplainantRespondentFiled
CMP/191118/0004752-Bhartiya City Developers Private Limited18/11/2019
CMP/220106/0008769-Bhartiya Urban Private Limited06/01/2022
01723/2023-Bhartiya Urban Private Limited17/11/2023

Documents filed158

As listed on the registration, under the names the promoter filed them with; the newest 80 of 158 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/171015/000184 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
1. 1) Demarcation of site plan specifying the total area of Land as mentioned in the project detailFile: Demarcation site plan.pdf2 Oct 2021
1. 2) Architect Certificate for Work CompletionFile: Architect Certificate Form -Ex1.pdf2 Oct 2021
2. 1) Architect Certificate for Pending Work Completion ScheduleFile: Architect Certificate Form-Ex2.pdf2 Oct 2021
2. 2) Demarcation plan specifying the area of the Land mentioned in the project detailFile: Demarcation site plan.pdf2 Oct 2021
2. 3) Certificate from Registered Engineer indicating the structural safety of the buildingFile: Engineer Certificate Leela BR.pdf2 Oct 2021
Bank statementFile: Bank statement.pdf2 Oct 2021
Bank statementFile: Fund transfer confirmation - Leela - LVB.pdf2 Oct 2021
Architect certificateFile: Architect Certificate Form-Ex2.pdf27 Sep 2021
Demarcation planFile: Demarcation Plan.pdf27 Sep 2021
Engineer certificate for structural safetyFile: Engineer Certificate Leela BR.pdf27 Sep 2021
1. CA certificate bank account number and Designated bank account numberFile: Cert_RERA_FormEx3057.pdf27 Aug 2021
1. CA certificate bank account number and Designated bank account numberFile: Cert_RERA_FormEx4058.pdf27 Aug 2021
1. CA certificate bank account number and Designated bank account numberFile: Change in bank account.pdf27 Aug 2021
2. 1) Architect’s CertificateFile: Architect Certificate Form - Ex1.pdf27 Aug 2021
2. 2)Affidavit for seeking extension of registered projectFile: Affidavit for project extension.pdf27 Aug 2021
2. 3) Affidavit abiding to pay compensationFile: Affidavit for delay compensation.pdf27 Aug 2021
2. 4) Uploaded NOC issued by BWSSBFile: BWSSB_13751-Common.pdf27 Aug 2021
2. 4) Uploaded NOC issued by Fire forceFile: Fire NOC - Block-2 (6th May 2016)-Leela Hotel.pdf27 Aug 2021
2. 4) Uploaded NOC issued by SEIAAFile: MOEF-SEIAA-EC-Common.pdf27 Aug 2021
2. 4) Uploaded NOC issued by BSNLFile: BSNL.pdf27 Aug 2021
2. 4) Validity of NOC'sFile: NOC writeup.pdf27 Aug 2021
2. 5) Relinquishment Deed not uploadedFile: Relinquishment deed.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 1File: 1st TO 60th SHEETS-FULL SET_Part1.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 2File: 1st TO 60th SHEETS-FULL SET_Part2.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 3File: 1st TO 60th SHEETS-FULL SET_Part3.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 4File: 1st TO 60th SHEETS-FULL SET_Part4.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 5File: 1st TO 60th SHEETS-FULL SET_Part5.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 6File: 1st TO 60th SHEETS-FULL SET_Part6.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 7File: 1st TO 60th SHEETS-FULL SET_Part7.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 8File: 1st TO 60th SHEETS-FULL SET_Part8.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 9File: 1st TO 60th SHEETS-FULL SET_Part9.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 10File: 1st TO 60th SHEETS-FULL SET_Part10.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 11File: 1st TO 60th SHEETS-FULL SET_Part11.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 12File: 1st TO 60th SHEETS-FULL SET_Part12.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 13File: 1st TO 60th SHEETS-FULL SET_Part13.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 14File: 1st TO 60th SHEETS-FULL SET_Part14.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 15File: 1st TO 60th SHEETS-FULL SET_Part15.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 16File: 1st TO 60th SHEETS-FULL SET_Part16.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 17File: 1st TO 60th SHEETS-FULL SET_Part17.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 18File: 1st TO 60th SHEETS-FULL SET_Part18.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 19File: 1st TO 60th SHEETS-FULL SET_Part19.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 20File: 1st TO 60th SHEETS-FULL SET_Part20.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 21File: 1st TO 60th SHEETS-FULL SET_Part21.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 22File: 1st TO 60th SHEETS-FULL SET_Part22.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 23File: 1st TO 60th SHEETS-FULL SET_Part23.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 24File: 1st TO 60th SHEETS-FULL SET_Part24.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 25File: 1st TO 60th SHEETS-FULL SET_Part25.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 26File: 1st TO 60th SHEETS-FULL SET_Part26.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 27File: 1st TO 60th SHEETS-FULL SET_Part27.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 28File: 1st TO 60th SHEETS-FULL SET_Part28.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 29File: 1st TO 60th SHEETS-FULL SET_Part29.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 30File: 1st TO 60th SHEETS-FULL SET_Part30.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 31File: 1st TO 60th SHEETS-FULL SET_Part31.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 32File: 1st TO 60th SHEETS-FULL SET_Part32.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 33File: 1st TO 60th SHEETS-FULL SET_Part33.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 34File: 1st TO 60th SHEETS-FULL SET_Part34.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 35File: 1st TO 60th SHEETS-FULL SET_Part35.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 36File: 1st TO 60th SHEETS-FULL SET_Part36.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 37File: 1st TO 60th SHEETS-FULL SET_Part37.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 38File: 1st TO 60th SHEETS-FULL SET_Part38.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 39File: 1st TO 60th SHEETS-FULL SET_Part39.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans - 40File: 1st TO 60th SHEETS-FULL SET_Part40.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans -41File: 1st TO 60th SHEETS-FULL SET_Part41.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans -42File: 1st TO 60th SHEETS-FULL SET_Part42.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans -43File: 1st TO 60th SHEETS-FULL SET_Part43.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans -44File: 1st TO 60th SHEETS-FULL SET_Part44.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans -45File: 1st TO 60th SHEETS-FULL SET_Part45.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans -46File: 1st TO 60th SHEETS-FULL SET_Part46.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans -47File: 1st TO 60th SHEETS-FULL SET_Part47.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans -48File: 1st TO 60th SHEETS-FULL SET_Part48.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans -49File: 1st TO 60th SHEETS-FULL SET_Part49.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans -50File: 1st TO 60th SHEETS-FULL SET_Part50.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans -51File: 1st TO 60th SHEETS-FULL SET_Part51.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans -52File: 1st TO 60th SHEETS-FULL SET_Part52.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans -53File: 1st TO 60th SHEETS-FULL SET_Part53.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans -54File: 1st TO 60th SHEETS-FULL SET_Part54.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans -55File: 1st TO 60th SHEETS-FULL SET_Part55.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans -56File: 1st TO 60th SHEETS-FULL SET_Part56.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans -57File: 1st TO 60th SHEETS-FULL SET_Part57.pdf27 Aug 2021
2. 6) Demarcation plan, Site plan, Section, Elevation, All floor plans -58File: 1st TO 60th SHEETS-FULL SET_Part58.pdf27 Aug 2021

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
Nikoo Homes II West-OngoingJul 2017Not delivered
Nikoo Homes II East-OngoingJul 2017Not delivered
Nikoo Homes I-OngoingJul 2017Not delivered

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 21 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Bhartiya Leela Residences on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Bhartiya Urban Private Limited

Bhartiya Urban Private Limited has 8 registrations on RERA Karnataka, including Nikoo Homes VI - Phase-2 and Nikoo Homes II West. Its filings declare 7 earlier projects, 4 of them declared completed. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Bhartiya Leela Residences is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Bhartiya Leela Residences?

The registered promoter entity is Bhartiya Urban Private Limited, a company as per the filing. Its CIN U45200TN2008PTC103956 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Bhartiya Leela Residences?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Bhartiya Leela Residences?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Bhartiya Leela Residences?

The professionals named in the filing: Architect: RSP Design Consultants (India) Pvt Ltd; Engineer: Innotech Engineering Consult Pvt Ltd. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Bhartiya Leela Residences?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Bhartiya Leela Residences. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Bhartiya Leela Residences to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.