Home / Browse projects / Thane, Maharashtra / BHAIRAAV MILESTONE PHASE II

Registered No litigation declared Commercial project

BHAIRAAV MILESTONE PHASE II

By Sharpmind Consultancy Services Private Limited

RG-MH-03336 · RERA P51700020951 · Last updated on MahaRERA portal: 17 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 48 months
  • 3 extensions taken
  • Rs 27.00 crore secured on the land, in favour of Aditya Birla Finance Limited
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 48 months from the original
4 of 11Construction stages donefurthest along: Internal walls, 98%
22 of 97Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 164 documents Report an error

BHAIRAAV MILESTONE PHASE II is a Commercial project by Sharpmind Consultancy Services Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700020951 on 23 May 2019. Possession is promised by 30 Dec 2026. The completion date has moved by 48 months from the original filing. 75 of the 97 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameBHAIRAAV MILESTONE PHASE II
  • TypeCommercial
  • Location
    • PLOT NO C-15 ROAD NO.16
    • WAGALE ESTATE
    • Thane (M Corp.)
    • Thane
    • 400604
  • Pincode400604
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700020951
  • ReraGenie IDRG-MH-03336

Builder

  • NameSharpmind Consultancy Services Private Limited
  • Entity typeCompany
  • CINU70100MH1995PTC087297
  • GSTIN27AABCS3989A1ZB
  • DirectorsMadanlal Pukhraj Jain, Viivek Madanlal Jain
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects1 →

Key dates

this monthRegisteredMay 2019First promiseDec 2022Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 May 2019
  • Promised completion30 Dec 2026
  • Revised completionRevised to 30 Dec 2026 (originally 30 Dec 2022)
  • Buildings1 building record
  • Documents filed164 files

Current status

77%75 of 97 units booked
93.9%Work done, per cost certificate

Figures as on 17 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BHAIRAAV MILESTONENA11009797

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 98%.

BHAIRAAV MILESTONE: 79% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.88%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 17 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes97%
Street LightingYes97%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes98%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationYes93%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed98

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots98
Closed/Covered98

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area5,201 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofAditya Birla Finance Limited
Secured amountRs 27.00 crore
Declared on23 Jan 2026

Approvals and building plan

Sanctioning authorityMaharashtra Industrial Development Corporation
Permissible FSI14632.02
Proposed, not sanctioned14,632 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCST-VT BRANCH ELPHINSTONE HOUSE, 17, MURZBAN ROAD, NEAR CST-VT MUMBAI-400001
Estimated costRs 62.00 cr
Cost incurredRs 58.23 cr
Work done93.92%
BuildingWingEstimatedIncurred
BHAIRAAV MILESTONENARs 48.30 crRs 45.47 cr
-NARs 13.70 crRs 12.76 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSUDHIR THORAT
EngineerAli Abbas Jaffrey
EngineerAkshay Patil
Chartered AccountantNitesh Jain
Chartered AccountantK.Kaveria & Co.
PartnerRole in project
Sharpmind Consultancy Services Private Limited-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700018454Dec 2022 → Dec 2024

Reason as filed by the promoterWe have already obtained part OC upto 5th Floor of the Project but due to some technical & administrative factors, NOC is pending as per certain norms and requirements, hence the OC for the 6th floor(Part) could not be obtained. However, the building upto 6th Floor is complete as per the plans submitted in RERA. We will be applying for OC for the 6th Floor units shortly. As per UDPCR 2034, additional FSI has been sanctioned for construction of further floors in the building. Presently, seeking extension for one year so that necessary updating of details can be done to carry out the further dev

EXT51700024608Dec 2022 → Dec 2026

Reason as filed by the promoterConstruction upto Part 6 floor has been completed and Occupancy certificate has been duly obtained. Revised commencement certificate has been received from MIDC

EXT51700013170Dec 2022 → Dec 2023

Reason as filed by the promoterThe Project ‘Bhairaav Milestone’ is being developed in Phases. Phase I is already completed and OC received. For Phase II, Building is already completed as per approved plans and as per MIDC DCR- 2009. Also, Part OC has been received upto 5th Floor. However, due to some technical & administrative reasons, NOC from the concerned authority is pending as per certain norms and requirements and thereby the OC for the 6th floor(Part) could not be obtained till date, although the building upto 6th Floor is complete in all respects as per the approved plans. Presently, seeking extension so that the pe

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Jun 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 May 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 25 May 2024

Documents filed164

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 164 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: BMT - FORM 1 - Q4.pdf17 Jun 2026
Withdrawal Update Form 2File: BMT - FORM 2 - Q4.pdf17 Jun 2026
Withdrawal Update Form 3File: SCSPL FORM 3_Q4_MAR 26.pdf17 Jun 2026
Form 2A (FY 2025-2026)File: BMT - Form 2A - Qtr 4.pdf8 Jun 2026
Withdrawal Update Form 1File: BMT - FORM 1 - Q4.pdf1 Jun 2026
Withdrawal Update Form 2File: BMT - FORM 2 - Q4.pdf1 Jun 2026
Withdrawal Update Form 3File: SCSPL FORM 3_Q4_MAR 26.pdf1 Jun 2026
Withdrawal Update Form 1File: Form 1 Q3 2025 26.pdf28 May 2026
Withdrawal Update Form 2File: Form 2-QR-3-2025-26.pdf28 May 2026
Withdrawal Update Form 3File: Form 3 Q3 25-26.pdf28 May 2026
Form 5 (FY 2025-2026)File: SCSPL FORM 5.pdf28 May 2026
Withdrawal Update Form 1File: 2025-07-03 _ARCHITECTS CERTIFICATE.pdf8 May 2026
Withdrawal Update Form 1File: Form 1 Q2 2025 26.pdf8 May 2026
Withdrawal Update Form 2File: Form 2- QR-1-2025-2026.pdf8 May 2026
Withdrawal Update Form 2File: Form 2- QR-1-2025-2026.pdf8 May 2026
Withdrawal Update Form 3File: Form 3 Q1 25-26.pdf8 May 2026
Withdrawal Update Form 3File: Form 3 Q1 25-26.pdf8 May 2026
Withdrawal Update Form 1File: 2025-07-03 _ARCHITECTS CERTIFICATE.pdf7 May 2026
Withdrawal Update Form 2File: Form 2- QR-1-2025-2026.pdf7 May 2026
Withdrawal Update Form 3File: Form 3 Q1 25-26.pdf7 May 2026
Form 1File: Form 1 Q2 2025 26.pdf11 Mar 2026
Form 2File: Form 2-QR-2-2025-26.pdf11 Mar 2026
Form 3File: Form 3 Q2 25-26.pdf11 Mar 2026
Disclosure of Sold and Booked InventoryFile: BMT Q2 Sold unsold inventory.pdf11 Mar 2026
Form 5 (FY 2024-2025)File: Form 5 2024 25 updated.pdf11 Mar 2026
Withdrawal Update Form 1File: Form 1 Q2 2025 26.pdf10 Jan 2026
Withdrawal Update Form 1File: Form 1 Q2 2025 26.pdf10 Jan 2026
Withdrawal Update Form 2File: Form 2-QR-2-2025-26.pdf10 Jan 2026
Withdrawal Update Form 2File: Form 2-QR-2-2025-26.pdf10 Jan 2026
Withdrawal Update Form 3File: Form 3 Q1 25-26.pdf10 Jan 2026
Withdrawal Update Form 3File: Form 3 Q1 25-26.pdf10 Jan 2026
Withdrawal Update Form 1File: Form 1 Q2 2025 26.pdf7 Jan 2026
Withdrawal Update Form 2File: Form 2-QR-2-2025-26.pdf7 Jan 2026
Withdrawal Update Form 3File: Form 3 Q1 25-26.pdf7 Jan 2026
Other - FinanceFile: Financial Encumbrance.pdf28 Dec 2024
Details of encumbrancesFile: Encumbrance detail.pdf23 Oct 2024
Declaration in FORM BFile: Encumbrance detail.pdf23 Oct 2024
OtherFile: BMT Consent format C.pdf29 May 2024
Building plan approvalFile: BMT APPROVED AMENDED CC PLAN 191223.pdf28 May 2024
Building Plan Approval (IOD)File: BMT APPROVED AMENDED CC PLAN 191223.pdf28 May 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC 2019.pdf25 May 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PART OC 2024.pdf25 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: BMT Phase II Form 1 Q4 23-24.pdf24 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: BMT Phase II Form 2 Q4 23-24.pdf24 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: BMT- II RERA FORM 2A FOR JUNE 2023.pdf24 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: BMT-II RERA FORM 2A FOR SEP 2023.pdf24 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: BMT-Phase II_FORM 2A_FY 23-24_DECEMBER-2023.pdf24 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: BMT Phase II Form 2A Q4 23-24.pdf24 May 2024
Disclosure of sold/ booked inventoryFile: BMT Phase II Sold Unsold inventory Q4 23-24.pdf24 May 2024
Certificates of CA (Form 3)File: SCSPL Form 3 Q4.pdf24 May 2024
OtherFile: FORMAT C REVISED.pdf20 Apr 2024
OtherFile: Declaration IT Paark.pdf18 Apr 2024
Declaration about Commencement CertificateFile: DocScanner Apr 16, 2024 16-53.pdf16 Apr 2024
OtherFile: SCSPL Form 3 - Amended.pdf16 Apr 2024
Building plan approvalFile: BMT APPROVED AMENDED CC PLAN 19122023.pdf11 Apr 2024
Building Plan Approval (IOD)File: BMT APPROVED AMENDED CC PLAN 19122023.pdf11 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: BMT - Form 1 - Dec 2023.pdf28 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: BMT-Phase II_FORM 2_FY 23-24_DECEMBER-2023.pdf27 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: BMT-Phase II_FORM 2A_FY 23-24_DECEMBER-2023.pdf27 Feb 2024
Certificates of CA (Form 3)File: SCSPL Form 3 Q 3.pdf27 Feb 2024
Certificates of CA (Form 3)File: SCSPL Form 3 - Amended.pdf27 Feb 2024
OtherFile: fORM C new.pdf22 Feb 2024
OtherFile: Annexure A Unit Nos 201 to 302 Actual Possession letter copies.pdf22 Feb 2024
OtherFile: Annexure B Unit Nos 303 to 312 Actual possession letter copies.pdf22 Feb 2024
OtherFile: AnnexureC Unit Nos 401 to 512 Actual possession letter copies.pdf22 Feb 2024
OtherFile: Annexure D Email consent 610.pdf22 Feb 2024
Building plan approvalFile: 4 BMT APPROVED CC REVISED PLAN.pdf19 Jan 2024
Building plan approvalFile: BMT MIDC approval Letter internal Modification of unit no 508 509 510.pdf19 Jan 2024
Building Plan Approval (IOD)File: 4 BMT APPROVED CC REVISED PLAN.pdf19 Jan 2024
Building Plan Approval (IOD)File: BMT MIDC approval Letter internal Modification of unit no 508 509 510.pdf19 Jan 2024
CERSAI detailsFile: SCSPL CERSAI REPORT.pdf16 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure- Annexure A- ViIvek Jain.pdf16 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure- Annexure A- Madanlal P Jain.pdf16 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure- Annexure A- Akkshay Jain.pdf16 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: RERA Bank Details BMT.pdf16 Jan 2024
Declaration in FORM BFile: Form B Affidavit cum Declaration.pdf5 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2 Engineers Certificate on Quality Assurance.pdf5 Jan 2024
Disclosure of sold/ booked inventoryFile: LIST OF SOLD UNSOLD INVENTORY DECEMBER QUARTER 2023.pdf4 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 SCSPL FY 22-23.pdf4 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: BMT-Phase II_FORM 2_FY 23-24_SEPTEMBER-2023.pdf20 Dec 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Goldcrest Residency - Phase 2P51700010579GHANSOLI, Thane316Aug 2017OngoingDec 2024Registered original: Jun 2021Not delivered

How this compares with Thane

77%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 48 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BHAIRAAV MILESTONE PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WAGALE ESTATE7,600+ in Thane

2 kmBHAIRAAV MILESTONE PHASECompleted 90Lapsed / revoked 60Other 118Dot size: filed unitsN

Filed coordinates, straight-line distance. 268 registered projects within 2 km.

Builder: Sharpmind Consultancy Services Private Limited

Sharpmind Consultancy Services Private Limited has 2 registrations on MahaRERA, including BHAIRAAV MILESTONE and BHAIRAAV MILESTONE PHASE II. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if BHAIRAAV MILESTONE PHASE II is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BHAIRAAV MILESTONE PHASE II?

The registered promoter entity is Sharpmind Consultancy Services Private Limited, a company as per the filing. Its CIN U70100MH1995PTC087297 and GSTIN 27AABCS3989A1ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BHAIRAAV MILESTONE PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BHAIRAAV MILESTONE PHASE II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BHAIRAAV MILESTONE PHASE II?

The professionals named in the filing: Architect: SUDHIR THORAT; Engineer: Ali Abbas Jaffrey; Engineer: Akshay Patil; Chartered Accountant: Nitesh Jain; Chartered Accountant: K.Kaveria & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BHAIRAAV MILESTONE PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BHAIRAAV MILESTONE PHASE II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BHAIRAAV MILESTONE PHASE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.