ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / BEAUFORT PARK

Valid until 30 Nov 2030 Mixed Development project

BEAUFORT PARK

By HARSIDDH BUILDCON

RG-GJ-06244 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA12373/041023 · Last updated on GujRERA portal: 18 Nov 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Nov 2030Possession promisedno revision filed
4 of 18Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 92%
249 of 302Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

BEAUFORT PARK is a Mixed Development project by HARSIDDH BUILDCON in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA12373/041023 on 4 Oct 2023. Possession is promised by 30 Nov 2030. 53 of the 302 units on this registration are recorded sold or booked, and 4 of 18 construction stages are filed complete.

At a glance

Project

  • NameBEAUFORT PARK
  • TypeMixed Development
  • Location
    • BESIDE ANAYA PARMESHWAR
    • OPP. VANDEMATARAN VISHWAM
    • ADALAJ
    • JUNDAL ROAD
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA12373/041023
  • ReraGenie IDRG-GJ-06244

Builder

  • NameHARSIDDH BUILDCON
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredOct 2023PromisedNov 2030

Key facts

Registration and timeline

  • StatusValid until 30 Nov 2030
  • Registered on4 Oct 2023
  • Promised completion30 Nov 2030
  • Revised completionNone
  • Buildings2 building records
  • Documents filed40 files

Current status

18%53 of 302 units booked
55.7%Of the estimated cost spent so far

Figures as on 18 Nov 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK A---781492
BLOCK B+C+D---2100210

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 18 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 92%.

BLOCK A47%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure92%
Internal walls, internal plaster, floorings, doors and windows within flats42%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing15%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
BLOCK B+C+D39%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure71%
Internal walls, internal plaster, floorings, doors and windows within flats32%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks52%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 18 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,609 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 125.00 cr
Cost incurredRs 69.61 cr
Spent of the estimate55.69%
BuildingWingEstimatedIncurred
BLOCK B+C+DNARs 85.00 crRs 47.33 cr
BLOCK ANARs 40.00 crRs 22.28 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSAURABH VERMA
EngineerSAUMYA SHAH

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA12373/041023 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)18 Nov 2025
Engineer's certificate annexure18 Nov 2025
Accountant's certificate (Form 3)18 Nov 2025
Architect's certificate (Form 1)13 Nov 2025
Site photograph, BLOCK A12 Nov 2025
Site photograph, BLOCK B+C+D12 Nov 2025
RERA registration certificate4 Oct 2023
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

18%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep BEAUFORT PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Gandhinagar1,600+ in Gandhinagar

2 kmBEAUFORT PARKOther 47Dot size: filed unitsN

Filed coordinates, straight-line distance. 47 registered projects within 2 km.

Builder: HARSIDDH BUILDCON

HARSIDDH BUILDCON has 2 registrations on GujRERA, including BEAUFORT PARK and HARSIDDH HEARTLAND. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if BEAUFORT PARK is delayed beyond 30 Nov 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of BEAUFORT PARK?

The registered promoter entity is HARSIDDH BUILDCON, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in BEAUFORT PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at BEAUFORT PARK?

The professionals named in the filing: Architect: SAURABH VERMA; Engineer: SAUMYA SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BEAUFORT PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BEAUFORT PARK. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BEAUFORT PARK to a free account