Registered No litigation declared Residential / Group Housing project

BAY VUE

By H AND Y REALITIES PRIVAE LIMITED

RG-MH-26628 · RERA P51800009514 · Last updated on MahaRERA portal: 29 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 48 months
  • 2 extensions taken
  • Rs 63.00 crore secured on the land, in favour of KAUTILYA REAL ESTATE FUND
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 48 months from the original
5 of 11Construction stages donefurthest along: Internal walls, 95%
87 of 140Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 79 documents Report an error

BAY VUE is a Residential / Group Housing project by H AND Y REALITIES PRIVAE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800009514 on 22 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 48 months from the original filing. 53 of the 140 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameBAY VUE
  • TypeResidential / Group Housing
  • Location
    • KHARODI
    • MALVANI
    • Borivali
    • Mumbai Suburban
    • 400095
  • Pincode400095
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800009514
  • ReraGenie IDRG-MH-26628

Builder

  • NameH AND Y REALITIES PRIVAE LIMITED
  • Entity typeCompany
  • Managing DirectorKIRTI SHAMJI PATEL

Key dates

this monthRegisteredAug 2017First promiseDec 2022Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2022)
  • Buildings1 building record
  • Documents filed79 files

Current status

38%53 of 140 units booked
89.3%Work done, per cost certificate

Figures as on 29 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BAY VUENA39371337140

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

BAY VUE: 84% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 29 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed151

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots151
Closed/Covered151

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area5,327 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofKAUTILYA REAL ESTATE FUND
Secured amountRs 63.00 crore
CERSAI search filedYes
Declared on29 Jul 2026
LandownerVillageDistrict
SAI CONSTRUCTION COMPANYBorivaliMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI8052.14
Proposed, not sanctioned6,425 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch BORIVALI EAST MUMBAI 400067
Estimated costRs 224.51 cr
Cost incurredRs 200.50 cr
Work done89.3%
BuildingWingEstimatedIncurred
-NARs 150.16 crRs 132.04 cr
BAY VUENARs 74.36 crRs 68.46 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHANTANOO RANE AND ASSOCIATES
EngineerREGAL CONSULTANTS
EngineerNexus Project Solutions Private Limited
Chartered AccountantN P SHETTY AND COMPANY
Chartered AccountantH S P AND ASSOCIATES
PartnerRole in project
H AND Y REALITIES PRIVATE LIMITED-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800012670Dec 2022 → Dec 2025

Reason as filed by the promoterDUE TO COVID AND LOCKDOWN AND SHORTHAGE OF BOOKING AND FINANCE.

EA08122518571Dec 2022 → Dec 2026

Reason as filed by the promoteras per letter attached in application form

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Oct 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed79

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: aRCHITECH CERTIFICATEMARCH 26.pdf29 Jul 2026
Withdrawal Update Form 1File: Rera Arch Cert june 26.pdf29 Jul 2026
Withdrawal Update Form 2File: ENG MARCH 26.pdf29 Jul 2026
Withdrawal Update Form 2File: engin june 26.pdf29 Jul 2026
Withdrawal Update Form 3File: form 3 march 2026.pdf29 Jul 2026
Withdrawal Update Form 3File: form 3 JUNE 26.pdf29 Jul 2026
Withdrawal Update Form 1File: Rera Arch Cert form 1.pdf27 Jul 2026
Withdrawal Update Form 1File: Rera Arch Cert form 1.pdf27 Jul 2026
Withdrawal Update Form 2File: Rera Engineer Cert..pdf27 Jul 2026
Withdrawal Update Form 2File: Rera Engineer Cert..pdf27 Jul 2026
Withdrawal Update Form 3File: form 3.pdf27 Jul 2026
Withdrawal Update Form 3File: form 3.pdf27 Jul 2026
Withdrawal Update Form 1File: Rera Arch Cert form 1.pdf7 Feb 2026
Withdrawal Update Form 2File: Rera Engineer Cert..pdf7 Feb 2026
Withdrawal Update Form 3File: form 3.pdf7 Feb 2026
Withdrawal Update Form 1File: FORM 1 ARCTITECH CERTIFICATE.pdf4 Dec 2025
Withdrawal Update Form 2File: fORM 3 Rera C A cert.pdf4 Dec 2025
Withdrawal Update Form 3File: FROM3.pdf4 Dec 2025
Form 5 (FY 2024-2025)File: SIGN FORM 5.pdf4 Dec 2025
Form 1File: Rera Arch. Cert..pdf17 Nov 2025
Form 2File: Rera Engineer Cert..pdf17 Nov 2025
Form 3File: Adobe Scan 15 Nov 2025 (2).pdf17 Nov 2025
Disclosure of Sold and Booked InventoryFile: Rera Bay Vue Inventory 31032025.pdf17 Nov 2025
Form 1File: Rera Arch Cert 30092025.pdf17 Nov 2025
Form 2File: Rera Engg Cert 30092025.pdf17 Nov 2025
Form 3File: Adobe Scan 15 Nov 2025 (1) (1).pdf17 Nov 2025
Disclosure of Sold and Booked InventoryFile: bay Vue Rev Inventory 30092025.pdf17 Nov 2025
Disclosure of sold/ booked inventoryFile: Rera Inventory 30092024.pdf26 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCTITECH CERTIFICATE.pdf25 Dec 2024
Certificates of CA (Form 3)File: fORM 3 Rera C A cert.pdf25 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: fORM 2 ENGINEER CERTIFICATE.pdf25 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera Arch Cert.pdf26 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera Engg Cert.pdf26 Apr 2024
Certificates of CA (Form 3)File: Rera Form 3 (30092023).pdf26 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 signed.pdf9 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: Bay Vue FULL CC.pdf23 Dec 2023
Building plan approvalFile: Bay Vue Amended IOA 27122021.pdf18 Oct 2023
Building Plan Approval (IOD)File: Bay Vue Amended IOA 27122021.pdf18 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: Bay Vue CC (32) 09062023.pdf18 Oct 2023
Certificates of CA (Form 3)File: FORM 3-HNY BAY VUE TOWER.pdf18 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5.pdf3 Feb 2023
Disclosure of sold/ booked inventoryFile: declartion of unsold.pdf22 Oct 2022
Certificates of CA (Form 3)File: form3.pdf19 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: H Y ANNUAL REPORT 17-18_0001.pdf9 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: H Y ANNUAL REPORT 18-19_0001.pdf9 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: H Y ANNUAL REPORT 19-20_0001.pdf9 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: H Y ANNUAL REPORT 20-21_0001.pdf9 Sep 2022
Proforma of Allotment letterFile: Bay Vue HY RERA Agree.pdf18 May 2022
Commencement Certificates / NA Order for plotted developmentFile: BayVue CC (21)_compressed.pdf26 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Arch Cert 020921_compressed.pdf26 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera FORM2 (Engineers Certificate)23102021.pdf26 Feb 2022
Details of encumbrancesFile: DETAILS OF ENCUBUSMENT.pdf16 Feb 2022
Building plan approvalFile: LOI.pdf27 Oct 2021
Building Plan Approval (IOD)File: LOI.pdf27 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: BayVue CC.pdf27 Oct 2021
Declaration about Commencement CertificateFile: Rera cc Decl.pdf27 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A CERTIFICATE.pdf27 Oct 2021
Disclosure of sold/ booked inventoryFile: BayVue Flat list Declaration Reracompressed.pdf27 Oct 2021
Certificates of CA (Form 3)File: FORM 3-H N Y REALTIES-BAYUE TOWER.pdf27 Oct 2021
Details of encumbrancesFile: Bay Vue Rera Encumb.pdf4 Nov 2020
Details of encumbrancesFile: BOI Loan Closure letter.pdf4 Nov 2020
Certificates of CA (Form 3)File: FORM 3.pdf4 Nov 2020
Certificates of CA (Form 3)File: Rera Certificate-Form 3 H AND Y-.pdf14 Jan 2019
Building plan approvalFile: ioa.pdf30 Jul 2017
Layout approvalFile: Layout Plan.pdf30 Jul 2017
PAN CardFile: PAN CARDS.pdf30 Jul 2017
Copy of the legal title reportFile: TITLE CERTIFICATE.pdf30 Jul 2017
Details of encumbrancesFile: BANK LETTER OF LOAN.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf30 Jul 2017
Building Plan Approval (IOD)File: ioa.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf30 Jul 2017
Declaration in FORM BFile: AFFIFAVIT.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARTCHITECT CERTI.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CERTIFICATE.pdf30 Jul 2017
Certificates of CA (Form 3)File: FORM 3.pdf30 Jul 2017
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf30 Jul 2017
Proforma of Allotment letterFile: Draft Agreement RERA.pdf30 Jul 2017
OtherFile: develpment agreement-ilovepdf-compressed.pdf30 Jul 2017
OtherFile: LOI.pdf30 Jul 2017

How this compares with Mumbai Suburban

38%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 48 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BAY VUE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MALVANI6,700+ in Mumbai Suburban

2 kmBAY VUECompleted 16Lapsed / revoked 17Other 48Dot size: filed unitsN

Filed coordinates, straight-line distance. 81 registered projects within 2 km.

Builder: H AND Y REALITIES PRIVAE LIMITED

H AND Y REALITIES PRIVAE LIMITED has 1 registration on MahaRERA, including BAY VUE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if BAY VUE is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BAY VUE?

The registered promoter entity is H AND Y REALITIES PRIVAE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BAY VUE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BAY VUE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BAY VUE?

The professionals named in the filing: Architect: SHANTANOO RANE AND ASSOCIATES; Engineer: REGAL CONSULTANTS; Engineer: Nexus Project Solutions Private Limited; Chartered Accountant: N P SHETTY AND COMPANY; Chartered Accountant: H S P AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BAY VUE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BAY VUE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BAY VUE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.