ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / BANDRA SIDDHARTH CO OP HSG SOC LTD

Completed No litigation declared Residential / Group Housing project

BANDRA SIDDHARTH CO OP HSG SOC LTD

By L NAGPAL BUILDERS

RG-MH-40588 · RERA P51800050072 · Last updated on MahaRERA portal: 15 Mar 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
May 2025Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 53 documents Report an error

BANDRA SIDDHARTH CO OP HSG SOC LTD is a Residential / Group Housing project by L NAGPAL BUILDERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800050072 on 13 Mar 2023. The registration is recorded completed; possession was promised by 31 May 2025.

At a glance

Project

  • NameBANDRA SIDDHARTH CO OP HSG SOC LTD
  • TypeResidential / Group Housing
  • Location
    • 15TH ROAD
    • BANDRA WEST
    • Bandra
    • Andheri
    • Mumbai Suburban
    • 400050
  • Pincode400050
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800050072
  • ReraGenie IDRG-MH-40588

Builder

  • NameL NAGPAL BUILDERS
  • Entity typePartnership
  • LLPINAAT-0196
  • GSTIN27AAJFL0230E1ZS
  • LLPIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • PartnersFATICHAND HOTCHAND NAGPAL, VINAYAK FATICHAND NAGPAL, KRISHNA FATICHAND NAGPAL
  • Other registrations1 more →
  • Completed2 of 2

Key dates

this monthRegisteredMar 2023PromisedMay 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on13 Mar 2023
  • Promised completion31 May 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed53 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BANDRA SIDDHARTHNA100000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

BANDRA SIDDHARTH: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 15 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed28

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots28
Closed/Covered24
Open Space4

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area554 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
BANDRA SIDDHARTHBandraMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI1646.39
Proposed, not sanctioned1,646 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTHE POINT, GROUND FLOOR, BANDRA WEST, MUMBAI 400050

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRIYANK BHATT ARCHITECT
Engineerframes
Chartered AccountantV C Gangawani & Co
PartnerRole in project
L NAGPAL BUILDERS LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Feb 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Feb 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Feb 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 15 Mar 2025

Documents filed53

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 1 Occupancy Certificate_ Completion Certificate_ Architect's certificate of completion for15 Mar 2025
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 Siddharth (1).pdf6 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2451135_OC_signed (1).pdf2 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - BANDRA SIDDHARTH CHSL as on Sep 2024.pdf16 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - BANDRA SIDDHARTH CHSL as on Sep 2024.pdf16 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - BANDRA SIDDHARTH CHSL as on Sep 2024.pdf16 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Bandra siddharth as on June 2024.pdf17 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Siddhart FORM 3 for RERA certificate (1).pdf16 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Bandra siddhart as on June 2024.pdf15 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Bandra Siddhart as on June 2024.pdf15 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1).pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: NN.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Bandra Siddharth CHSL as on June 2023.pdf2 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Bandra Siddharth CHSL as on March 2023.pdf30 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Bandra Siddharth CHSL as on June 2023.pdf30 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Bandra Siddharth CHSL as on Sep 2023.pdf30 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Bandra Siddharth CHSL as on Dec 2023.pdf30 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Bandra Siddharth CHSL as on March 2023.pdf29 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Bandra Siddharth CHSL as on June 2023.pdf29 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Bandra Siddharth CHSL as on Sep 2023.pdf29 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Bandra Siddharth CHSL as on Dec 2023.pdf29 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Bandra Siddharth CHSL as on Sep 2023.pdf12 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Bandra Siddharth CHSL as on Dec 2023.pdf12 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5- Bandra Siddharth.pdf6 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT RERA CFT -20112023 DS.pdf20 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SIDDHARTH ENGINEER Certificate(18-11-2023).pdf20 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 siddharth.pdf10 Nov 2023
Details of encumbrances concerned to FinanceFile: DECLARATION FOR FINANCIAL ENCUM.pdf3 Mar 2023
Details of encumbrances concerned to LegalFile: DECLARATION FOR FINANCIAL ENCUM.pdf3 Mar 2023
Deviation Report with respect to model copy of AgreementFile: Deviation report 27223.pdf25 Feb 2023
CERSAI detailsFile: DECLARATION FOR FINANCIAL ENCUM.pdf24 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE 1.pdf24 Feb 2023
Proforma of Agreement for saleFile: PROFORMA FOR AGREEMENT FOR SALE.pdf24 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CER.pdf13 Feb 2023
Copy of the legal title reportFile: Revised Title Report.pdf11 Feb 2023
Layout approvalFile: final_compressed.pdf10 Feb 2023
Building plan approvalFile: final_compressed.pdf10 Feb 2023
Copy of Layout Approval (in case of layout)File: final_compressed.pdf10 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: final_compressed.pdf10 Feb 2023
CERSAI detailsFile: CERSAI_Search_Report_200260103621_For_Asset_Based_Search_10_02_2023_17_11_47_663.pdf10 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: formet a.pdf2 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf14 Jan 2023
Copy of the legal title reportFile: search.pdf12 Jan 2023
Proforma of Allotment letterFile: AL FINAL.pdf12 Jan 2023
Declaration in FORM BFile: FORM B.pdf2 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer certificate.pdf30 Dec 2022
Deviation Report with respect to Allotment letterFile: deviation allotment ltr .pdf30 Dec 2022
PAN CardFile: LNB PAN CARD-1.pdf17 Dec 2022
Details of encumbrances concerned to FinanceFile: encumbrance legal.pdf17 Dec 2022
Details of encumbrances concerned to LegalFile: encumbrance legal.pdf17 Dec 2022
Commencement Certificates / NA Order for plotted developmentFile: 2351373_FirstCC_signed.pdf17 Dec 2022
Declaration about Commencement CertificateFile: declaration cc.pdf17 Dec 2022

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BANDRA SIDDHARTH CO OP HSG SOC LTD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BANDRA WEST6,700+ in Mumbai Suburban

2 kmBANDRA SIDDHARTH CO OP HCompleted 117Lapsed / revoked 55Other 145Dot size: filed unitsN

Filed coordinates, straight-line distance. 317 registered projects within 2 km.

Builder: L NAGPAL BUILDERS

L NAGPAL BUILDERS has 2 registrations on MahaRERA, including N N TOWER and BANDRA SIDDHARTH CO OP HSG SOC LTD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if BANDRA SIDDHARTH CO OP HSG SOC LTD is delayed beyond 31 May 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BANDRA SIDDHARTH CO OP HSG SOC LTD?

The registered promoter entity is L NAGPAL BUILDERS, a partnership as per the filing. Its LLPIN AAT-0196 and GSTIN 27AAJFL0230E1ZS can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BANDRA SIDDHARTH CO OP HSG SOC LTD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BANDRA SIDDHARTH CO OP HSG SOC LTD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BANDRA SIDDHARTH CO OP HSG SOC LTD?

The professionals named in the filing: Architect: PRIYANK BHATT ARCHITECT; Engineer: frames; Chartered Accountant: V C Gangawani & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BANDRA SIDDHARTH CO OP HSG SOC LTD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BANDRA SIDDHARTH CO OP HSG SOC LTD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BANDRA SIDDHARTH CO OP HSG SOC LTD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.