BANDAL VED BHUMI-PHASE 2
RG-MH-26105 · RERA P52000003424 · Last updated on MahaRERA portal: 30 Apr 2026
Source: official MahaRERA filing
Red flags
- Completion date moved by 32 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
BANDAL VED BHUMI-PHASE 2 is a Plotted project by Nilesh Kisanrao Bandal in Raigarh, Maharashtra, registered with MahaRERA as P52000003424 on 5 Aug 2017. The registration is recorded completed; possession was promised by 28 Apr 2025. The completion date has moved by 32 months from the original filing. 14 of the 57 units on this registration are recorded sold or booked.
At a glance
Project
- NameBANDAL VED BHUMI-PHASE 2
- TypePlotted
- Location
- Shrivardhan-Mhasala Road
- Bhoste
- Shrivardhan
- Raigarh
- 402110
- Pincode402110
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000003424
- ReraGenie IDRG-MH-26105
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on5 Aug 2017
- Promised completion28 Apr 2025
- Revised completionRevised to 28 Apr 2025 (originally 28 Aug 2022)
- BuildingsNot stated in filing
- Documents filed132 files
Current status
Figures as on 30 Apr 2026, this project's latest MahaRERA filing.
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 30 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
NA Plot Without Structure:
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 30 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ar. Nitin Mahadeorao Waghmare |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAs our project is exempted from RERA we require the RERA extension for Agreement registration only.
Reason as filed by the promoterThe project work is 100% completed. We have received full Occupancy Certificate dated 28/04/25. We require extension till the date of Occupancy Certificate.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 11 Sep 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 Jan 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Jan 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 30 Apr 2026
Documents filed132
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 132 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Completion CertificateFile: Vedbhumi_Architects_Completion Certificate__Ack.pdf | 30 Apr 2026 |
| Completion CertificateFile: CC VERIFICATION - BANDAL.pdf | 17 Nov 2025 |
| Completion CertificateFile: LAYOUT 1.pdf | 17 Nov 2025 |
| Completion CertificateFile: PLAN 2.pdf | 17 Nov 2025 |
| Completion CertificateFile: CLUB HOUSE PLAN.pdf | 17 Nov 2025 |
| Completion CertificateFile: Occupency Certificate.pdf | 8 Aug 2025 |
| Declaration in FORM BFile: Form _B_Bandal Vedbhumi Phase 2.pdf | 29 May 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Gat No 58_Bhoste_bhogavata pramanpatra OC.pdf | 22 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Bandal Vedbhumi_Phase 2.pdf | 11 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3_Bandal Vedbhumi_Phase II.pdf | 11 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form _2_Bandal Vedbhumi Phase II.pdf | 11 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Discloure of sold booked inventory Bandal Vedbhumi Phase II.pdf | 9 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 13 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3 (2)_11zon.pdf | 13 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form - 2.pdf | 13 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Discolsure of Sold_Booked Inventory.pdf | 13 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 10 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 10 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 (2).pdf | 9 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 (1)_11zon.pdf | 9 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Discolsure of Sold_booked Inventory_Vedbhumi _Phase II.pdf | 9 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 (2).pdf | 9 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 (1)_11zon.pdf | 9 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Discolsure of Sold_booked Inventory_Vedbhumi _Phase II.pdf | 9 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 (3).pdf | 2 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 (2).pdf | 2 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Discolsure of sold booked inventory.pdf | 2 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 (1)_compressed.pdf | 2 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form5 (2023-2024).pdf | 2 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3_31_3_2018_11zon.pdf | 11 Jun 2024 |
| Certificates of CA (Form 3)File: Form 3_31-3-19_11zon.pdf | 11 Jun 2024 |
| Certificates of CA (Form 3)File: Form 3_31_3_2020_11zon.pdf | 11 Jun 2024 |
| Certificates of CA (Form 3)File: Form 3_dated 31-3-21_11zon.pdf | 11 Jun 2024 |
| Certificates of CA (Form 3)File: Form 3_dated 31-3-22_11zon.pdf | 11 Jun 2024 |
| Certificates of CA (Form 3)File: Form 3_31-12-2022_11zon.pdf | 11 Jun 2024 |
| Certificates of CA (Form 3)File: Form 3_dated 31-3-23_11zon.pdf | 11 Jun 2024 |
| Certificates of CA (Form 3)File: Form 3_30_6_23_11zon.pdf | 11 Jun 2024 |
| Certificates of CA (Form 3)File: Form 3_30-9-2023_11zon.pdf | 11 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_22_23.pdf | 11 Jun 2024 |
| Declaration in FORM BFile: Form B bandal ved bhumi.pdf | 10 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form5 (2023-2024).pdf | 10 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Clarification_Declartion for not submitting Form 2A_vedbhumi.pdf | 7 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booking inventory_Vedbhumi_Phase_II(Mar2023).pdf | 7 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 4 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 4 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventorY.pdf | 4 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3.pdf | 4 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1.pdf | 3 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2.pdf | 3 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Bandal Vedbhumi_PhaseII disclosure of sold booked inventory.pdf | 3 Jan 2024 |
| Certificates of CA (Form 3)File: FORM-3_compressed.pdf | 3 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects certificate_Vedbhumi_Phase _II_compressed.pdf | 7 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2 Vedbhumi_Phase_2_compressed.pdf | 7 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory_Vedbhumi _Phase II.pdf | 7 Oct 2023 |
| Certificates of CA (Form 3)File: FORM-3_compressed.pdf | 7 Oct 2023 |
| Declaration in FORM BFile: Affidavit_Declartion _Bandal Vedbhumi_PhaseII_compressed.pdf | 19 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1-Architect Certificate_Phase 2_23-06-2023.pdf | 6 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-Engg certificate June23_compressed.pdf | 6 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Clarification_Declartion for not submitting Form 2A_vedbhumi.pdf | 6 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booking inventory_Vedbhumi_Phase_II.pdf | 6 Jul 2023 |
| Certificates of CA (Form 3)File: FORM-3 -CA Certificate June23_compressed.pdf | 6 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5 (FY 22-23).pdf | 6 Jul 2023 |
| Certificates of CA (Form 3)File: RERA FORM-3 (JUNE-22).pdf | 14 Jun 2023 |
| Certificates of CA (Form 3)File: RERA FORM-3 (SEPT-22).pdf | 14 Jun 2023 |
| Certificates of CA (Form 3)File: FORM-3 (FY 22-23)-6.pdf | 14 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1-Architect Certificate_Phase 2_31-03-2018-1.pdf | 13 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1-Architect Certificate_Phase 2_31-03-2019-2.pdf | 13 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1-Architect Certificate_Phase 2_31-03-2020-3.pdf | 13 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1-Architect Certificate_Phase 2_31-03-2021-4.pdf | 13 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1-Architect Certificate_Phase 2 31-12-2021-5.pdf | 13 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1-Architect Certificate_Phase 2 31-03-2022-6.pdf | 13 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1-Architect Certificate_Phase 2_30-06-2022-7.pdf | 13 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1-Architect Certificate_Phase 2_30-09-2022-8.pdf | 13 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1-Architect Certificate_Phase 2_31-03-2023-9.pdf | 13 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate_Vedbhumi_Mar2018-1.pdf | 13 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate_Vedbhumi_Mar2019-2.pdf | 13 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate_Vedbhumi_Mar2020-3.pdf | 13 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate_Vedbhumi_Mar2021-4.pdf | 13 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate_Vedbhumi_21Dec21-5.pdf | 13 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate_Vedbhumi_Mar2022-6.pdf | 13 Jun 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 132 filed documents as one ZIP, foldered, with a manifest
Keep BANDAL VED BHUMI-PHASE 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bhoste5,900+ in Raigarh
AvenueS
SILVER HOMES ENTERPRISES
SAGAR VIHAR
CORE DEVELOPERS
PUNIR GAURAV - B WING
Punir Gaurav Developers Pvt Ltd.
GANLEELA APARTMENT
VISHAL VIMAL JAIN
KOHINOOR CITY PHASE 1
KOHINOOR ASSOCIATES
Kundan Darshan Apartment
Amarkumar Javerchand Jain
See every Raigarh project, with the district possession charts
Builder: Nilesh Kisanrao Bandal
Nilesh Kisanrao Bandal has 2 registrations on MahaRERA, including BANDAL VED BHUMI-PHASE 2 and VEDSINDHU. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if BANDAL VED BHUMI-PHASE 2 is delayed beyond 28 Apr 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of BANDAL VED BHUMI-PHASE 2?
The registered promoter entity is Nilesh Kisanrao Bandal, an individual as per the filing. Its GSTIN 27AEQPB0988L1ZY can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in BANDAL VED BHUMI-PHASE 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for BANDAL VED BHUMI-PHASE 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at BANDAL VED BHUMI-PHASE 2?
The professionals named in the filing: Architect: Ar. Nitin Mahadeorao Waghmare. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in BANDAL VED BHUMI-PHASE 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.