ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / BALAJI VISHWA BUILDING D AND E

Registration lapsed No litigation declared Residential / Group Housing project

BALAJI VISHWA BUILDING D AND E

By IDEAL PROPERTIES

RG-MH-17160 · RERA P52100028409 · Last updated on MahaRERA portal: 9 Feb 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 13 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2025Possession promised13 months past this date
6 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 95%
43 of 150Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 214 documents Report an error

BALAJI VISHWA BUILDING D AND E is a Residential / Group Housing project by IDEAL PROPERTIES in Pune, Maharashtra, registered with MahaRERA as P52100028409 on 2 Mar 2021. Possession was promised by 30 Sep 2025 and is now 13 months past that date. The completion date has moved by 12 months from the original filing. 107 of the 150 units on this registration are recorded sold or booked, and 6 of 22 construction stages are filed complete.

At a glance

Project

  • NameBALAJI VISHWA BUILDING D AND E
  • TypeResidential / Group Housing
  • Location
    • BORHADEWADI
    • MOSHI- BORHADEWADI
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • RERA no.P52100028409
  • ReraGenie IDRG-MH-17160

Builder

  • NameIDEAL PROPERTIES
  • Entity typePartnership
  • PartnersPRAKASH ANKUSH THORAT, PRASHANT BHIVSEN BAGAL, HANUMANT GOPALA GAIKWAD, SHARAD PANDURANG DIGHE, TANAJI DAMODAR WAGHOLE
  • Other registrations3 more →
  • No longer live3 lapsed, de-registered or revoked

Key dates

13 months past promisethis monthRegisteredMar 2021First promiseSep 2024Revised toSep 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on2 Mar 2021
  • Promised completion30 Sep 2025
  • Revised completionRevised to 30 Sep 2025 (originally 30 Sep 2024)
  • Buildings2 building records
  • Documents filed214 files

Current status

71%107 of 150 units booked

Figures as on 9 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BALAJI VISHWA BUILDING DNA121283083
BUILDING VISHWA BUILDING ENA131267067

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 9 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 95%.

BALAJI VISHWA BUILDING D74%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
BUILDING VISHWA BUILDING E74%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities16

As on 9 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes40%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes80%
Street LightingYes20%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes90%
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingYes80%
Energy managemcntYes20%
Fire protection and fire safety requirementsYes20%
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
OthersYes40%

Land and ownership7

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,488 sq m
Land owned byThe promoter, with other names on the file
Named landowners7
Encumbrance on the landDeclared none
Declared on2 Apr 2026
LandownerVillageDistrict
ADINATH DATTATRAY BORATEChakan (CT)Pune
DASHRATH RAGHU BORATEPimpri Chinchawad (M Corp.)Pune
MACHHINDRA DASHRATH BORATEPimpri Chinchawad (M Corp.)Pune
SAGAR SUBHASH BORATEPimpri Chinchawad (M Corp.)Pune
NIKHIL SUBHASH BORATEPimpri Chinchawad (M Corp.)Pune
SANGITA VILAS BORATEPimpri Chinchawad (M Corp.)Pune
TUSHAR VILAS BORATEPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI27270.0
Proposed, not sanctioned25,961 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAUNDH

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTEJOMAY CONSULTANCY
ArchitectM/S. Sachin Ladkat & Associate
EngineerRATHI'S GROUP
Chartered AccountantCA VAIBHAV MODI
Chartered AccountantPradnya Gandhi
PartnerRole in project
IDEAL PROPERTIES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024631Sep 2024 → Sep 2025

Reason as filed by the promoterDue to non-availability of labor and other resources, self declaration is also attached

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Oct 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Apr 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Apr 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed214

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 214 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1.pdf9 Feb 2026
Form 2File: Form 2.pdf9 Feb 2026
Form 3File: Form 3-Q1.pdf9 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Of Inventory-Q1.pdf9 Feb 2026
Form 1File: Form1.pdf9 Feb 2026
Form 2File: Form 2.pdf9 Feb 2026
Form 3File: Form 3-Q2.pdf9 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory-Q2.pdf9 Feb 2026
Form 1File: Form 1.pdf3 Dec 2025
Form 2File: Form 2.pdf3 Dec 2025
Form 3File: Form 3.pdf3 Dec 2025
Disclosure of Sold and Booked InventoryFile: Disclosures Of Inventory.pdf3 Dec 2025
Proforma of Agreement for saleFile: Agreement to Sell Draft.pdf29 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - 23-24 Signed.pdf11 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - 23-24 Signed.pdf11 Oct 2024
Declaration in FORM BFile: Form-'B'.pdf9 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf9 Oct 2024
Disclosure of sold/ booked inventoryFile: 2sold dicscl D wing.pdf9 Oct 2024
Disclosure of sold/ booked inventoryFile: 3sold disc E wing.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert 30 June 24.pdf9 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert 30 June 24.pdf9 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Upto 30-6-2024.pdf9 Oct 2024
Declaration in FORM BFile: Form-'B'.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert 30 June 24.pdf9 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Upto 30-6-2024.pdf9 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert 30 June 24.pdf9 Oct 2024
Disclosure of sold/ booked inventoryFile: 2sold dicscl D wing.pdf9 Oct 2024
Disclosure of sold/ booked inventoryFile: 3sold disc E wing.pdf9 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf9 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Ideal Mar24.pdf25 May 2024
Proforma of Agreement for saleFile: Draft Format.pdf26 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 sign copy 22-23.pdf8 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 sign copy 23-24.pdf8 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf8 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - 22-23 signed.pdf8 Feb 2024
Disclosure of sold/ booked inventoryFile: Disclosure of inventory.pdf28 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 22-23 Uploaded in rera.pdf28 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: Revised Commencement_compressed.pdf27 Apr 2023
Building plan approvalFile: 35_compressed.pdf17 Apr 2023
Layout approvalFile: Revised Layout.pdf17 Apr 2023
Building plan approvalFile: 1_compressed.pdf17 Apr 2023
Building plan approvalFile: 2_compressed.pdf17 Apr 2023
Building plan approvalFile: 3_compressed.pdf17 Apr 2023
Building plan approvalFile: 4_compressed.pdf17 Apr 2023
Building plan approvalFile: 5_compressed.pdf17 Apr 2023
Building plan approvalFile: 6_compressed.pdf17 Apr 2023
Building plan approvalFile: 7_compressed.pdf17 Apr 2023
Building plan approvalFile: 8_compressed.pdf17 Apr 2023
Building plan approvalFile: 9_compressed.pdf17 Apr 2023
Building plan approvalFile: 10_compressed.pdf17 Apr 2023
Building plan approvalFile: 11_compressed.pdf17 Apr 2023
Building plan approvalFile: 12_compressed.pdf17 Apr 2023
Building plan approvalFile: 13_compressed.pdf17 Apr 2023
Building plan approvalFile: 14_compressed.pdf17 Apr 2023
Building plan approvalFile: 15_compressed.pdf17 Apr 2023
Building plan approvalFile: 16_compressed.pdf17 Apr 2023
Building plan approvalFile: 17_compressed.pdf17 Apr 2023
Building plan approvalFile: 18_compressed.pdf17 Apr 2023
Building plan approvalFile: 19_compressed.pdf17 Apr 2023
Building plan approvalFile: 20_compressed.pdf17 Apr 2023
Building plan approvalFile: 21_compressed.pdf17 Apr 2023
Building plan approvalFile: 22_compressed.pdf17 Apr 2023
Building plan approvalFile: 23_compressed.pdf17 Apr 2023
Building plan approvalFile: 24_compressed.pdf17 Apr 2023
Building plan approvalFile: 24_compressed.pdf17 Apr 2023
Building plan approvalFile: 26_compressed.pdf17 Apr 2023
Building plan approvalFile: 27_compressed.pdf17 Apr 2023
Building plan approvalFile: 27_compressed.pdf17 Apr 2023
Building plan approvalFile: 29_compressed.pdf17 Apr 2023
Building plan approvalFile: 29_compressed.pdf17 Apr 2023
Building plan approvalFile: 31_compressed.pdf17 Apr 2023
Building plan approvalFile: 31_compressed.pdf17 Apr 2023
Building plan approvalFile: 33_compressed.pdf17 Apr 2023
Building plan approvalFile: 33_compressed.pdf17 Apr 2023
Copy of Layout Approval (in case of layout)File: Revised Layout.pdf17 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: 1_compressed.pdf17 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: 2_compressed.pdf17 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: 3_compressed.pdf17 Apr 2023

How this compares with Pune

71%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BALAJI VISHWA BUILDING D AND E on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MOSHI- BORHADEWADI13,700+ in Pune

Builder: IDEAL PROPERTIES

IDEAL PROPERTIES has 4 registrations on MahaRERA, including BALAJI VISHWA BUILDING C and IDEAL RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that BALAJI VISHWA BUILDING D AND E shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if BALAJI VISHWA BUILDING D AND E is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BALAJI VISHWA BUILDING D AND E?

The registered promoter entity is IDEAL PROPERTIES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BALAJI VISHWA BUILDING D AND E?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BALAJI VISHWA BUILDING D AND E?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BALAJI VISHWA BUILDING D AND E?

The professionals named in the filing: Architect: TEJOMAY CONSULTANCY; Architect: M/S. Sachin Ladkat & Associate; Engineer: RATHI'S GROUP; Chartered Accountant: CA VAIBHAV MODI; Chartered Accountant: Pradnya Gandhi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BALAJI VISHWA BUILDING D AND E?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BALAJI VISHWA BUILDING D AND E. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BALAJI VISHWA BUILDING D AND E to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.