Home / Browse projects / Palghar, Maharashtra / Balaji Platinum Block No.10, Type C1, A Wing
Balaji Platinum Block No.10, Type C1, A Wing
RG-MH-23873 · RERA P99000005450 · Last updated on MahaRERA portal: 6 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 4 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Balaji Platinum Block No.10, Type C1, A Wing is a Others project by Tirupati Constructions Co in Palghar, Maharashtra, registered with MahaRERA as P99000005450 on 11 Aug 2017. Possession is promised by 30 Dec 2026. 26 of the 52 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete.
At a glance
Project
- NameBalaji Platinum Block No.10, Type C1, A Wing
- TypeOthers
- Location
- S No.860
- H.No.1 pt & 4 pt & 5
- 6
- 7 pt
- S.No.875
- Village Tembi
- Tembhi
- Vasai
- Palghar
- 401301
- Pincode401301
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000005450
- ReraGenie IDRG-MH-23873
Builder
- NameTirupati Constructions Co
- Entity typePartnership
- GSTIN27AAFFT5112R1ZQ
- PartnersPravin Nanjibhai Shah, Gordhan Prabhudas Tanwani
- Other registrations4 more →
- Completed2 of 5
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on11 Aug 2017
- Promised completion30 Dec 2026
- Revised completionNone
- Buildings1 building record
- Documents filed47 files
Current status
Figures as on 6 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Balaji Platinum A Wing | NA | 9 | 9 | 44 | 8 | 52 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 6 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 11 construction stages are filed complete.
Balaji Platinum A Wing: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 6 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed13
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Balaji Platinum A Wing | NA | Rs 4.69 cr | Rs 4.51 cr |
| - | NA | Rs 82.76 lakh | Rs 79.53 lakh |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | M/S. SHAH GATTANI CONSULTANTS |
| Engineer | M/S. SHAH GATTANI CONSULTANTS |
| Engineer | SK Consultants & Engineers |
| Engineer | Sachin Shivaji Gawde |
| Chartered Accountant | Rutuja Narsingh & Associates |
| Chartered Accountant | Kamdar Desai Patel LLP |
| Partner | Role in project |
|---|---|
| Tirupati Constructions Co | - |
Litigation declared1
| Case | Court | Status |
|---|---|---|
| CIDCO/VVSR/RF/BP-82/E/3915 notice dated 18/05/2009/2009 | The City and Industrial Development Corporation of Maharashtra Ltd | Pending |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Jul 2017 - Commencement CertificateNot on the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
- Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Dec 2026
Documents filed47
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1.pdf | 6 Jun 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 6 Jun 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 6 Jun 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 18 Mar 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 18 Mar 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 18 Mar 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 18 Mar 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 18 Mar 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 18 Mar 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 18 Mar 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 18 Mar 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 18 Mar 2026 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Balaji Platinum A Wing as on 30-06-2023.pdf | 25 Aug 2023 |
| Certificates of CA (Form 3)File: Form 3- Balaji Platinum A Wing as on 30-06-2023.pdf | 25 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A Wing 100 work Certificate .pdf | 28 Apr 2023 |
| Declaration about Commencement CertificateFile: Format D (4).pdf | 12 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A 19.pdf | 12 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A 20.pdf | 12 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A 21-22.pdf | 12 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: 29.pdf | 12 Apr 2023 |
| CERSAI detailsFile: CERSAI- Balaji Platinum Type C1 A Wing.pdf | 12 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - Balaji Platinum Block No 10 Type C1 A Wing FY 2019-20.pdf | 12 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - Balaji Platinum Block No 10 Type C1 A Wing FY 2020-21.pdf | 12 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - Balaji Platinum Block No 10 Type C1 A Wing FY 2021-22.pdf | 12 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: TCC A-WING.pdf | 30 Oct 2019 |
| Certificates of CA (Form 5)File: TCC A-WING.pdf | 8 Oct 2018 |
| Certificates of CA (Form 5)File: TCC A -WING new.pdf | 8 Oct 2018 |
| Layout approvalFile: Plan Tirupati - Block 10.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: TCC A- Wing.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Plan Tirupati - Block 10.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: A- WING.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate A wing.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: A compress.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: CA certificate - A wing.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: Draft Agreement - page 1 to 13.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: Draft Agreement - page 14 to 25.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: Draft Agreement - page 26 to 31.pdf | 31 Jul 2017 |
| OtherFile: DA page no 1 to 40.pdf | 31 Jul 2017 |
| OtherFile: DA page no 41 - 73.pdf | 31 Jul 2017 |
| OtherFile: DA page no 74-109.pdf | 31 Jul 2017 |
| OtherFile: DA page no 110 - 139.pdf | 31 Jul 2017 |
| OtherFile: Layout signed.pdf | 31 Jul 2017 |
| OtherFile: A wing addnl.pdf | 31 Jul 2017 |
| Copy of the legal title reportFile: Legal Title Report.pdf | 29 Jul 2017 |
| Building plan approvalFile: A.pdf | 28 Jul 2017 |
| Building Plan Approval (IOD)File: A.pdf | 28 Jul 2017 |
| PAN CardFile: TCC PAN CARD.pdf | 26 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 47 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Balaji Platinum Block No.10, Type C1, A Wing on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Village Tembi3,200+ in Palghar
SQUARE HOMES
RAMESH CHAMPAKLAL JAIN
DHARTI 3
DHARTIDHAN CONSTRUCTION
ARVIND HEIGHTS
Kumkum Constructions
FAITH APARTMENT
FAITH REALTY
SWAPNA SHILPA TOWER
SWAPNA SHILPA DEVELOPERS
Balaji Platinum Block No.10, Type C, B Wing
Tirupati Constructions Co
See every Palghar project, with the district possession charts
Builder: Tirupati Constructions Co
Tirupati Constructions Co has 5 registrations on MahaRERA, including Balaji Platinum Block No.10, Type C1, A Wing and Balaji Platinum Block No.10, Type C, B Wing. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What are my rights if Balaji Platinum Block No.10, Type C1, A Wing is delayed beyond 30 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Balaji Platinum Block No.10, Type C1, A Wing?
The registered promoter entity is Tirupati Constructions Co, a partnership as per the filing. Its GSTIN 27AAFFT5112R1ZQ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Balaji Platinum Block No.10, Type C1, A Wing?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Balaji Platinum Block No.10, Type C1, A Wing?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Balaji Platinum Block No.10, Type C1, A Wing?
The professionals named in the filing: Architect: M/S. SHAH GATTANI CONSULTANTS; Engineer: M/S. SHAH GATTANI CONSULTANTS; Engineer: SK Consultants & Engineers; Engineer: Sachin Shivaji Gawde; Chartered Accountant: Rutuja Narsingh & Associates; Chartered Accountant: Kamdar Desai Patel LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Balaji Platinum Block No.10, Type C1, A Wing?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback