Balaji Park

By Gurukrupa Developers

RG-MH-94016 · RERA P52100049217 · Last updated on MahaRERA portal: 18 Sep 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
10 of 26Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 55 documents Report an error

Balaji Park is a Plotted project by Gurukrupa Developers in Pune, Maharashtra, registered with MahaRERA as P52100049217 on 3 Feb 2023. Possession was promised by 31 Dec 2023 and is now 34 months past that date. 16 of the 26 units on this registration are recorded sold or booked.

At a glance

Project

  • NameBalaji Park
  • TypePlotted
  • Location
    • Aambale
    • Gat no 1101
    • Ambale
    • Purandhar
    • Pune
    • 412104
  • Pincode412104
  • RERA no.P52100049217
  • ReraGenie IDRG-MH-94016

Builder

  • NameGurukrupa Developers
  • Entity typePartnership
  • PartnersMahesh Eknath Thorat, Ashok Baldeo Sharma, Kunal Ashok Sharma, Jaykumar Puranchandra Sharma
  • Other registrations10 more →
  • Completed4 of 11
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

34 months past promisethis monthRegisteredFeb 2023PromisedDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on3 Feb 2023
  • Promised completion31 Dec 2023
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed55 files

Current status

62%16 of 26 units booked

Figures as on 18 Sep 2025, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 18 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes50%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes50%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes90%
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area7,150 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on5 Aug 2025
LandownerVillageDistrict
Mr Rajkumar Palakdhari YadavMOHAMMADWADIPune

Approvals and building plan

Sanctioning authorityTahsil Karyalay Purandar
Permissible FSI5467.44
Proposed, not sanctioned5,467 sq m

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchUndri Pune

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Sameer B Kokare
EngineerMr Prasad Katake
Chartered AccountantCA Pravin Pise & Associates
Chartered AccountantVaibhav S Bhise
PartnerRole in project
Gurukrupa Developers-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Nov 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Nov 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Nov 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed55

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2023-2024)File: Balaji Park Form 2A (1).pdf18 Sep 2025
Form 1File: Form 1.pdf11 Jul 2025
Form 2File: Form 2.pdf11 Jul 2025
Form 3File: Form 3.pdf11 Jul 2025
Disclosure of Sold and Booked InventoryFile: Dec 2023 Sold Unsold.pdf11 Jul 2025
Form 1File: March 2023 Form 1.pdf3 Jul 2025
Form 2File: March 2023 Form 2.pdf3 Jul 2025
Form 3File: F3-MARCH-23.pdf3 Jul 2025
Disclosure of Sold and Booked InventoryFile: March 2023 Sold Unsold.pdf3 Jul 2025
Form 1File: Jun 2023 Form 1.pdf3 Jul 2025
Form 2File: Jun 2023 Form 2.pdf3 Jul 2025
Form 3File: F3-JUNE-23.pdf3 Jul 2025
Disclosure of Sold and Booked InventoryFile: Jun 2023 Sold Unsold.pdf3 Jul 2025
Form 1File: Sep 2023 Form 1.pdf3 Jul 2025
Form 2File: Sep 2023 Form 2.pdf3 Jul 2025
Form 3File: F3-SEPT -23.pdf3 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sep 2023 Sold Unsold.pdf3 Jul 2025
Form 2A (FY 2022-2023)File: 2A 15.06.2023.pdf3 Jul 2025
Form 5 (FY 2022-2023)File: F5-BALAJI PARK-22-23.pdf3 Jul 2025
Form 5 (FY 2023-2024)File: F5-BALAJI PARK-23-24.pdf3 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: to upload form 2 sep 23.pdf5 Jul 2024
Disclosure of sold/ booked inventoryFile: to upload sold unsold dec 23.pdf5 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Balaji.pdf27 Oct 2023
Disclosure of sold/ booked inventoryFile: DocScanner 19-Oct-2023 2-08 pm (2).pdf19 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Balaji Park F2.pdf1 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf24 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf24 Jun 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold List (1).pdf24 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Balaji Park.pdf17 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf27 Mar 2023
Disclosure of sold/ booked inventoryFile: Sold unsold.pdf27 Mar 2023
Declaration about Commencement CertificateFile: DOC-20230112-WA0018-2-4.pdf25 Jan 2023
Other - TechnicalFile: DOC-20230112-WA0018-2-4.pdf25 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Dic;o Annexure A.pdf14 Jan 2023
Other - TechnicalFile: scan0448_compressed 1.pdf14 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf4 Jan 2023
Layout approvalFile: scan (2)_compressed.pdf24 Nov 2022
Building plan approval or NA orderFile: scan (2)_compressed.pdf24 Nov 2022
PAN CardFile: Company Pan Card.pdf24 Nov 2022
Copy of the legal title reportFile: Format A (4).pdf24 Nov 2022
Copy of the legal title reportFile: SURCH REPORT 24-08-2022_compressed.pdf24 Nov 2022
Details of encumbrances concerned to FinanceFile: Encumbrance (4).pdf24 Nov 2022
Details of encumbrances concerned to LegalFile: Encumbrance (4).pdf24 Nov 2022
Copy of Layout Approval (in case of layout)File: scan (2)_compressed.pdf24 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: scan (2)_compressed.pdf24 Nov 2022
Commencement Certificates / NA Order for plotted developmentFile: SKMBT_C28023011302360_compressed.pdf24 Nov 2022
Declaration about Commencement CertificateFile: 1 Declaration about Commencement Certificate (1) (1) (1).pdf24 Nov 2022
Declaration in FORM BFile: Notary- Promoter.pdf24 Nov 2022
CERSAI detailsFile: CERSAI_Search_Report_200253059131_For_Asset_Based_Search_24_11_2022_12_25_38_899.pdf24 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (7)_compressed.pdf24 Nov 2022
Proforma of Allotment letterFile: Model form of Allotment letter (3)_compressed.pdf24 Nov 2022
Proforma of Agreement for saleFile: Annexure AFS.pdf24 Nov 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A- Bank.pdf24 Nov 2022
Deviation Report with respect to Allotment letterFile: Deviation of Allotment letter.pdf24 Nov 2022
Deviation Report with respect to model copy of AgreementFile: Deviation of Agreement to sell letter (2).pdf24 Nov 2022

How this compares with Pune

62%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Balaji Park on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Gat no 110113,700+ in Pune

Builder: Gurukrupa Developers

Gurukrupa Developers has 11 registrations on MahaRERA, including Primus Residences and PRIMEROSE. Its filings disclose 4 earlier MahaRERA projects: declares 2 of 3 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Balaji Park shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Balaji Park is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Balaji Park?

The registered promoter entity is Gurukrupa Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Balaji Park?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Balaji Park?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Balaji Park?

The professionals named in the filing: Architect: Mr Sameer B Kokare; Engineer: Mr Prasad Katake; Chartered Accountant: CA Pravin Pise & Associates; Chartered Accountant: Vaibhav S Bhise. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Balaji Park?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Balaji Park. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Balaji Park to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.