Registration approved No litigation declared Residential/Group Housing project

AXIS OAKLYN

By AXIS CONCEPT CONSTRUCTION PVT LTD

RG-KA-48690 · RERA PRM/KA/RERA/1251/472/PR/280324/006742 · Last updated on RERA Karnataka portal: 14 Jul 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Mar 2027Possession promisedno revision filed
16 of 16Construction stages doneevery applicable stage filed complete
17 of 56Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 166 documents Report an error

AXIS OAKLYN is a Residential/Group Housing project by AXIS CONCEPT CONSTRUCTION PVT LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/472/PR/280324/006742 on 28 Mar 2024. Possession is promised by 31 Mar 2027. 39 of the 56 units on this registration are recorded sold or booked, and 16 of 16 construction stages are filed complete.

At a glance

Project

  • NameAXIS OAKLYN
  • TypeResidential/Group Housing
  • Location
    • Yelahanka
    • Bengaluru Urban
    • 562157
  • Pincode562157
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/472/PR/280324/006742
  • ReraGenie IDRG-KA-48690

Builder

  • NameAXIS CONCEPT CONSTRUCTION PVT LTD
  • Entity typeCompany
  • CINU45201KA2007PTC043841
  • GSTIN29AAHCA0685P1Z1
  • Authorized SignatoryR HARISH BABU
  • DirectorsR HARISH BABU, R HARISH BABU, A N Jayanthi
  • Project HeadNavaneethakrishnan
  • Other registrations4 more →
  • Declared earlier projects7 →

Key dates

this monthRegisteredMar 2024PromisedMar 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on28 Mar 2024
  • Promised completion31 Mar 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed166 files

Current status

70%39 of 56 units booked
72.7%Of the estimated cost spent so far

Figures as on 14 Jul 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 1---56056

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 16 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 14 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes100%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes100%
Electricity supply transformer and substationYes100%
Storm water drainsYes100%
Use of renewable energyYes100%
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes100%
Street LightingYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes100%
Piped GasNoNot applicable
Water and SanitationYes100%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementNoNot applicable
TerraceYes100%
Outer WallYes100%
Open parking areasYes100%
Provision for lodging of management staff and security staffYes100%
Water conservation and renewable energyYes100%
Common storage spacesYes100%

Land and ownership4

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,350 sq m
Named landowners4
LandownerVillageDistrict
S.M. KRISHNAMMA--
S .K. ANATH KUMAR--
S K Sumithra--
S K Vanishree--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 20.84 cr
Cost incurredRs 15.16 cr
Spent of the estimate72.71%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 20.84 crRs 13.97 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)-Rs 1.19 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectM SURESH KUMAR
EngineerN. MANOHAR
Chartered AccountantG. Pattabhi Reddy

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed166

As listed on the registration, under the names the promoter filed them with; the newest 80 of 166 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/472/PR/280324/006742 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Axis Oaklyn Q1 26-27.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Axis Oaklyn Q1 26-27.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Axis Oaklyn Q1 26-27.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4_CA_Certificate.pdf13 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5_Architect_Certificate.pdf13 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6_Engineer_Certificate.pdf13 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4_CA_Certificate Oaklyn_Q3_FY_2025-26.pdf14 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5_Architect_Certificate Oaklyn_Q3_FY_2025-26.pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6_Engineer_Certificate Oaklyn_Q3_FY_2025-26.pdf14 Jan 2026
Bank Accounts AffidavitFile: 1 Bank Accounts Affidavit1.pdf23 Mar 2024
Source of funds with supporting docsFile: 2 Source of funds with supporting docs.pdf23 Mar 2024
CA Membership CopyFile: 4 CA Membership Copy.pdf23 Mar 2024
Clarification on Borrowing declarationFile: 5 Clarification on Borrowing declaration.pdf23 Mar 2024
Board Report FY 2022-23File: 1 Board Report FY 2022-23.pdf23 Mar 2024
Audit report FY 2022-23File: 2 Audit report FY 2022-23.pdf23 Mar 2024
Balance Sheet 2022-23File: 3 Balance Sheet 2022-23.pdf23 Mar 2024
Cashflow Statement FY 2022-23File: 4 Cashflow Statement FY 2022-23.pdf23 Mar 2024
Profit and Loss FY 2022-23File: 5 Profit and Loss FY 2022-23.pdf23 Mar 2024
Statement fo Income FY 2022-23File: 6 Statement fo Income FY 2022-23.pdf23 Mar 2024
ITR ACK 2022-23File: 7 ITR ACK 2022-23.pdf23 Mar 2024
Financials FY 2022-23File: 8 Financials FY 2022-23.pdf23 Mar 2024
Balance Sheet FY 2021-22File: 1 Balance Sheet FY 2021-22.pdf23 Mar 2024
Profit and Loss FY 2021-22File: 2 Profit and Loss FY 2021-22.pdf23 Mar 2024
ITR FY 2021-22File: 3 ITR FY 2021-22.pdf23 Mar 2024
Audit report FY 2021-22File: 4 Audit report FY 2021-22.pdf23 Mar 2024
Boards Report FY 2021-22File: 5 Boards Report FY 2021-22.pdf23 Mar 2024
Cashflow Statement 2021-22File: 6 Cashflow Statement 2021-22.pdf23 Mar 2024
Financials FY 2021-22File: 7 Financials FY 2021-22.pdf23 Mar 2024
Balance Sheet FY 2020-21File: 1 Balance Sheet FY 2020-21.pdf23 Mar 2024
Profit and Loss 2020-21File: 2 Profit and Loss 2020-21.pdf23 Mar 2024
ITR FY 2020-21File: 3 ITR FY 2020-21.pdf23 Mar 2024
Directors Report FY 2020-21File: 4 Directors Report FY 2020-21.pdf23 Mar 2024
Cashflow statement FY 2020-21File: 5 Cashflow statement FY 2020-21.pdf23 Mar 2024
Audit report FY 2020-21File: 6 Audit report FY 2020-21.pdf23 Mar 2024
Financials FY 2020-21File: 7 Financials FY 2020-21.pdf23 Mar 2024
Clarification on Antara ProjectFile: 1 Clarification on Antara Project.pdf23 Mar 2024
ANTARA OCFile: 2 ANTARA OC.pdf23 Mar 2024
FORM 7 FY 2020-21 AntaraFile: 3 FORM 7 FY 2020-21 Antara.pdf23 Mar 2024
FORM 7 FY 2019-20 AntaraFile: 4 FORM 7 FY 2019-20 Antara.pdf23 Mar 2024
FORM 7 FY 2018-19 AntaraFile: 5 FORM 7 FY 2018-19 Antara.pdf23 Mar 2024
Form-5 Architect - Q4 - 2020 -21 Axis AntaraFile: 6 Form-5 Architect - Q4 - 2020 -21 Axis Antara.pdf23 Mar 2024
Form-6 Engineer - Q4 - 2020 - 21 Axis AntaraFile: 7 Form-6 Engineer - Q4 - 2020 - 21 Axis Antara.pdf23 Mar 2024
Form-4 CA - Q4 - 2020 - 21 Axis AntaraFile: 8 Form-4 CA - Q4 - 2020 - 21 Axis Antara.pdf23 Mar 2024
EC Sy No 46 2004-2024File: 1 EC Sy No 46 2004-2024.pdf23 Mar 2024
Grant Certificate - Title deed of KrishnappaFile: 2 Grant Certificate - Title deed of Krishnappa.pdf23 Mar 2024
IHC 28-1980-81- Title deed of KrishnappaFile: 3 IHC 28-1980-81- Title deed of Krishnappa.pdf23 Mar 2024
Sharing Agreement - 35 per share of S K Ananth KumarFile: 4 Sharing Agreement - 35 per share of S K Ananth Kumar.pdf23 Mar 2024
Khatha ExtractFile: 5 Khatha Extract.pdf23 Mar 2024
Clarification on Single Layout Plot and OrderFile: 1 Clarification on Single Layout Plot and Order.pdf23 Mar 2024
ADLR Survey SketchFile: 2 ADLR Survey Sketch.pdf23 Mar 2024
Area Statement Certified by ArchitectFile: 3 Area Statement Certified by Architect.pdf23 Mar 2024
Affidavit for KSPCB NOCFile: 4 Affidavit for KSPCB NOC.pdf23 Mar 2024
Building LicenseFile: 5 Building License.pdf23 Mar 2024
Form 3 Engineer certificateFile: 2 Form 3 Engineer certificate.pdf23 Mar 2024
Engineer License Self-attestedFile: 4 Engineer License Self-attested.jpeg23 Mar 2024
Guideline Value ReportFile: 5 Guideline Value Report.pdf23 Mar 2024
RTC, survey 46-
Mutation, survey 46-
Encumbrance Certificate, survey 46-
Conversion/Alienation Order, survey 46-
Sale/Title/Gift Deed, survey 46-
JDA, survey 46-
Khatha, survey 46-
Registration CertificateFile: Certificate of Incorporation.pdf-
Organization StructureFile: Organisational Chart.pdf-
Certificate issued by CA Form 1File: Form-1 CA Certificate.pdf-
Certificate issued by Architect Form 2File: Form 2 Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Form 3 Engineer certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non litigation Affidavit.pdf-
Certificate from Chartered AccountFile: Form-1 CA Certificate.pdf-
Balance Sheet 2022 - 2023File: Balance Sheet 2022-23.pdf-
Balance Sheet 2021 - 2022File: Balance Sheet 2021-22.pdf-
Balance Sheet 2020 - 2021File: Balance Sheet 2020-21.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Profit and Loss 2022-23.pdf-

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date2 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
BOCHS AkshayaSy No.24,Begur Village, Begur Hobli, , Bangalore South , Begur Hobli , Bengaluru South , Bengaluru Urban, KarnatakaOngoingNov 2024Not delivered
Axis AntaraKatha No 106, Sy 27/1 and 27/2, yelenahalli villageCompleted-No date filed
AXIS VANAMSy No 127/A,Katha No - 111/127/A, Kothanur Village, Uttarahalli Hobli,Completed-No date filed

How this compares with Bengaluru Urban

70%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep AXIS OAKLYN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmAXIS OAKLYNOther 7Dot size: filed unitsN

Filed coordinates, straight-line distance. 7 registered projects within 2 km.

Builder: AXIS CONCEPT CONSTRUCTION PVT LTD

Axis Concept Construction Pvt Ltd has 5 registrations on RERA Karnataka, including Axis Niran and Axis Vanam. Its filings declare 7 earlier projects, 5 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if AXIS OAKLYN is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of AXIS OAKLYN?

The registered promoter entity is AXIS CONCEPT CONSTRUCTION PVT LTD, a company as per the filing. Its CIN U45201KA2007PTC043841 and GSTIN 29AAHCA0685P1Z1 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in AXIS OAKLYN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AXIS OAKLYN?

The professionals named in the filing: Architect: M SURESH KUMAR; Engineer: N. MANOHAR; Chartered Accountant: G. Pattabhi Reddy. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AXIS OAKLYN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AXIS OAKLYN. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AXIS OAKLYN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.