ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / Avirat Giriraj

Valid until 30 Nov 2027 Mixed Development project

Avirat Giriraj

By GIRIRAJ ENTERPRISE LLP

RG-GJ-06756 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA12394/091023 · Last updated on GujRERA portal: 11 Sep 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Nov 2027Possession promisedno revision filed
1 of 10Construction stages donefurthest along: Slabs of Super Structure, 90%
231 of 326Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

Avirat Giriraj is a Mixed Development project by GIRIRAJ ENTERPRISE LLP in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA12394/091023 on 9 Oct 2023. Possession is promised by 30 Nov 2027. 95 of the 326 units on this registration are recorded sold or booked, and 1 of 10 construction stages are filed complete.

At a glance

Project

  • NameAvirat Giriraj
  • TypeMixed Development
  • Location
    • Avirat Giriraj
    • Nr Amrakunj Arastu
    • Opp. Panchshlok Homes
    • Chandkheda-Tragad
    • Zundal
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA12394/091023
  • ReraGenie IDRG-GJ-06756

Builder

  • NameGIRIRAJ ENTERPRISE LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM

Key dates

this monthRegisteredOct 2023PromisedNov 2027

Key facts

Registration and timeline

  • StatusValid until 30 Nov 2027
  • Registered on9 Oct 2023
  • Promised completion30 Nov 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed41 files

Current status

29%95 of 326 units booked
16.4%Of the estimated cost spent so far

Figures as on 11 Sep 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A+B+C+D+E+F---30818326

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 11 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 10 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 90%.

A+B+C+D+E+F: 56% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)40%
Plinth75%
Stilt Floor0%
Slabs of Super Structure90%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats30%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%

Progress on shared amenities19

As on 11 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes25%
Water supplyYes25%
Sewerage (chamber, lines, septic tank, STP)Yes40%
Storm water drainsYes40%
Landscaping and tree plantingYes25%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes40%
Solid waste management and disposalYes30%
Water conservation, rain water harvestingYes50%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes45%
Electrical meter room, sub-station, receiving stationYes40%
Fire fightingYes35%
Drinking water facilitiesYes10%
Emergency evacuationYes10%
Use of renewable energyYes20%
SecurityYes10%
Letter boxYes10%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,856 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 67.10 cr
Cost incurredRs 11.02 cr
Spent of the estimate16.42%
BuildingWingEstimatedIncurred
A+B+C+D+E+FNARs 67.10 crRs 11.02 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKartik Bijlani
EngineerViren D Parekh

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA12394/091023 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)11 Sep 2025
Accountant's certificate (Form 3)11 Sep 2025
Site photograph, A+B+C+D+E+F8 Aug 2025
Engineer's certificate (Form 2)3 Oct 2024
Engineer's certificate annexure3 Oct 2024
RERA registration certificate9 Oct 2023
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

29%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep Avirat Giriraj on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Gandhinagar1,600+ in Gandhinagar

2 kmAvirat GirirajOther 92Dot size: filed unitsN

Filed coordinates, straight-line distance. 92 registered projects within 2 km.

Builder: GIRIRAJ ENTERPRISE LLP

GIRIRAJ ENTERPRISE LLP has 1 registration on GujRERA, including Avirat Giriraj. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if Avirat Giriraj is delayed beyond 30 Nov 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Avirat Giriraj?

The registered promoter entity is GIRIRAJ ENTERPRISE LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Avirat Giriraj?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Avirat Giriraj?

The professionals named in the filing: Architect: Kartik Bijlani; Engineer: Viren D Parekh. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Avirat Giriraj?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Avirat Giriraj. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Avirat Giriraj to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.