Home / Browse projects / Pune, Maharashtra / AVENUE SERENITY

Registration lapsed No litigation declared Residential / Group Housing project

AVENUE SERENITY

By AVENUE ASSOCIATES

RG-MH-02550 · RERA P52100007363 · Last updated on MahaRERA portal: 10 Feb 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 28 months past the filed date
  • 2 complaints at MahaRERA
  • Completion date moved by 50 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2024Possession promised28 months past this date
0 of 11Construction stages donefurthest along: Excavation, 95%
2Complaints at MahaRERAon this registration
Jump to the 22 documents Report an error

AVENUE SERENITY is a Residential / Group Housing project by AVENUE ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100007363 on 17 Aug 2017. Possession was promised by 30 Jun 2024 and is now 28 months past that date. The completion date has moved by 50 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameAVENUE SERENITY
  • TypeResidential / Group Housing
  • Location
    • Maval
    • Varale
    • Mawal
    • Pune
    • 410507
  • Pincode410507
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100007363
  • ReraGenie IDRG-MH-02550

Builder

  • NameAVENUE ASSOCIATES
  • Entity typePartnership
  • PartnerLEENA AMIT SHET
  • Declared earlier projects1 →

Key dates

28 months past promisethis monthRegisteredAug 2017First promiseApr 2020Revised toJun 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on17 Aug 2017
  • Promised completion30 Jun 2024
  • Revised completionRevised to 30 Jun 2024 (originally 30 Apr 2020)
  • Buildings1 building record
  • Documents filed22 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AVENUE SERENITYNA10000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Feb 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 95%.

AVENUE SERENITY: 44% average across the applicable activities

ActivityProgress
Excavation95%
Basement (if any)90%
Podiums (if any)0%
Plinth90%
Stilt Floor60%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 Feb 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes10%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes15%
Street LightingNoNot applicable
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes10%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed6

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots6
Open Space6

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,000 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
VILAS JAYANTILAL SHAHSwargatePune
SUMATILAL TARACHAND SHAHTalegaon Dabhade (M Cl)Pune
NITIN SUMATILAL SHAHTalegaon Dabhade (M Cl)Pune
SACHIN SHAHTalegaon Dabhade (M Cl)Pune

Approvals and building plan

Permissible FSI2130.83
Proposed, not sanctioned1,719 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAundh Pune 411007

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectA DESIGN STUDIO
ArchitectVINOD DHUSIA ARCHITECTS
EngineerSPECTRUM CONSULTANTS
PartnerRole in project
AVENUE ASSOCIATES-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100005487Apr 2020 → Apr 2020

Reason as filed by the promoterWe started our project Avenue Serenity when RERA was not applicable and we had the project sanctioned from PMRDA within basic FSI rules. Then in July 2017, we uploaded the project under RERA. As per the routine practice we needed revise sanction for amenity space handover and hence we submitted file to PMRDA dated 03.07.2017, the copy of inward has been attached. The usual time required had lapsed by par, hence we took rigorous follow up to get the status of handover process. Then we realised that our whole submitted proposal was found to be missing from the concerned office and now they have

EXT52100009209Apr 2020 → Dec 2023

Reason as filed by the promoterDUE TO COVID 19 THATS WHY GETTING LATE TO THE COMPLETION PROCESS.

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC005000000238645Jainarayan VishwakarmaM/s. Avenue Associates through its Partners 1) Mrs. Leena Amit Shet 2) Mrs. Neha Abhijeet Kate07/04/2023
CC005000000238644Bijendra Kailashnath VishwakarmaM/s. Avenue Associates 1) Mrs. Leena Amit Shet 2) Mrs. Neha Abhijeet Kate07/04/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed22

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_compressed (1).pdf10 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - AVENUE SERENITY_compressed.pdf10 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA CERTIFICATE Form 5 20-21.pdf10 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: 5A 17-18.pdf26 Feb 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 5A 18-19.pdf26 Feb 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 5A 19-20.pdf26 Feb 2021
Layout approvalFile: Sanctioned plan.pdf29 Jul 2017
Details of encumbrancesFile: Encumbrance certificate.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Sanctioned plan.pdf29 Jul 2017
Declaration in FORM BFile: Form B Promoter Abhijit Kate.pdf29 Jul 2017
Certificates of CA (Form 3)File: CA Certificate.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certficate.pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf27 Jul 2017
Proforma of Allotment letterFile: Allotment Letter - Format.pdf26 Jul 2017
Building plan approvalFile: building plan approval.pdf22 Jul 2017
Building plan approvalFile: building plan approval 1.pdf22 Jul 2017
PAN CardFile: PAN - Avenue Associates.pdf22 Jul 2017
Copy of the legal title reportFile: Legal Title Report- Associates.pdf22 Jul 2017
Building Plan Approval (IOD)File: building plan approval.pdf22 Jul 2017
Building Plan Approval (IOD)File: building plan approval 1.pdf22 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate- Associates.pdf22 Jul 2017
Proforma of Allotment letterFile: Proforma of Agreement for Sale.pdf22 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Avenue BlossomRam Indu Park Baner.9CompletedMay 2012Apr 2012

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 50 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AVENUE SERENITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Maval13,700+ in Pune

2 kmAVENUE SERENITYCompleted 4Lapsed / revoked 4Other 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 11 registered projects within 2 km.

Builder: AVENUE ASSOCIATES

AVENUE ASSOCIATES has 1 registration on MahaRERA, including AVENUE SERENITY. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that AVENUE SERENITY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if AVENUE SERENITY is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AVENUE SERENITY?

The registered promoter entity is AVENUE ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AVENUE SERENITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AVENUE SERENITY?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for AVENUE SERENITY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AVENUE SERENITY?

The professionals named in the filing: Architect: A DESIGN STUDIO; Architect: VINOD DHUSIA ARCHITECTS; Engineer: SPECTRUM CONSULTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AVENUE SERENITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AVENUE SERENITY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AVENUE SERENITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.