ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / AVANI AAYAM

Valid until 30 Apr 2028 Residential/Group Housing project

AVANI AAYAM

By DEV SHREE DEVELOPERS

RG-GJ-40855 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA12115/070723 · Last updated on GujRERA portal: 7 Apr 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2028Possession promisedno revision filed
9 of 18Construction stages doneacross 2 buildings; furthest along: Stilt Floor, 90%
35 of 52Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

AVANI AAYAM is a Residential/Group Housing project by DEV SHREE DEVELOPERS in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA12115/070723 on 7 Jul 2023. Possession is promised by 30 Apr 2028. 17 of the 52 units on this registration are recorded sold or booked, and 9 of 18 construction stages are filed complete.

At a glance

Project

  • NameAVANI AAYAM
  • TypeResidential/Group Housing
  • Location
    • AVANI AAYAM Opp. Vinayk Sky Deck
    • Raysan Gandhinagar
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA12115/070723
  • ReraGenie IDRG-GJ-40855

Builder

  • NameDEV SHREE DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJul 2023PromisedApr 2028

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2028
  • Registered on7 Jul 2023
  • Promised completion30 Apr 2028
  • Revised completionNone
  • Buildings2 building records
  • Documents filed40 files

Current status

33%17 of 52 units booked
88.0%Of the estimated cost spent so far

Figures as on 7 Apr 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---26026
B---26026

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 7 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Stilt Floor, at 90%.

A79%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor90%
Slabs of Super Structure90%
Internal walls, internal plaster, floorings, doors and windows within flats90%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing40%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%
B89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats80%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing55%

Progress on shared amenities19

As on 7 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)NoNot applicable
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,240 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 54.00 cr
Cost incurredRs 47.50 cr
Spent of the estimate87.96%
BuildingWingEstimatedIncurred
ANARs 27.00 crRs 23.25 cr
BNARs 27.00 crRs 24.25 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Architect9 th Street Architect
EngineerASHISH J PATEL

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA12115/070723 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)7 Apr 2026
Engineer's certificate (Form 2)28 Mar 2026
Engineer's certificate annexure28 Mar 2026
Architect's certificate (Form 1)18 Mar 2026
Site photograph, A17 Mar 2026
Site photograph, B17 Mar 2026
RERA registration certificate7 Jul 2023
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

33%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep AVANI AAYAM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Gandhinagar1,600+ in Gandhinagar

2 kmAVANI AAYAMOther 270Dot size: filed unitsN

Filed coordinates, straight-line distance. 270 registered projects within 2 km.

Builder: DEV SHREE DEVELOPERS

DEV SHREE DEVELOPERS has 1 registration on GujRERA, including AVANI AAYAM. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if AVANI AAYAM is delayed beyond 30 Apr 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of AVANI AAYAM?

The registered promoter entity is DEV SHREE DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in AVANI AAYAM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AVANI AAYAM?

The professionals named in the filing: Architect: 9 th Street Architect; Engineer: ASHISH J PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AVANI AAYAM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AVANI AAYAM. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AVANI AAYAM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.