ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Atmosphere - C Wing

Completed No litigation declared Others project

Atmosphere - C Wing

By JRS Associates

RG-MH-09082 · RERA P52100000821 · Last updated on MahaRERA portal: 20 Jun 2023

Source: official MahaRERA filing

Red flags

  • 23 complaints at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
23Complaints at MahaRERAon this registration
Jump to the 65 documents Report an error

Atmosphere - C Wing is a Others project by JRS Associates in Pune, Maharashtra, registered with MahaRERA as P52100000821 on 23 Jul 2017. The registration is recorded completed; possession was promised by 30 Dec 2021. The completion date has moved by 24 months from the original filing. 23 complaints are on record with the regulator.

At a glance

Project

  • NameAtmosphere - C Wing
  • TypeOthers
  • Location
    • KATRAJ MUMBAI BYPASS
    • AMBEGAON
    • AMBEGAON Bk
    • Haveli
    • Pune
    • 411046
  • Pincode411046
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100000821
  • ReraGenie IDRG-MH-09082

Builder

  • NameJRS Associates
  • Entity typePartnership
  • PartnersJAYANILAL PUNAMCHAND JAIN, Ajay Shrenik Shah

Key dates

this monthRegisteredJul 2017First promiseDec 2019Revised toDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on23 Jul 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed65 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C - WingNA180000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jun 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

C - Wing: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 Jun 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed93

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots93
Closed/Covered73
Open Space20

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area743 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI5000.0
Proposed, not sanctioned5,000 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSahakar Nagar, Pune

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr Siddarth Harishchandrakar
PartnerRole in project
JRS Associates-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100003655Dec 2019 → Dec 2020

Reason as filed by the promoterWe have acquired and loaded the allowable TDR on same building, we approached PMC for Revised sanction for the project for which PMC has obliged, hence we are applying for revision of details in our registered project. (The revised sanction plan of PMC is also uploaded in the RERA website). We have already applied for Part Completion of Initial RERA Approved Project of 54 Flats but since there is a new requirement of an No Objection Certificate from Ministry of Defence, South block (gandhinagar), we have to wait for a longer period of time. The said department is heavily loaded and understaffe

Complaints filed with MahaRERA23

Case no.ComplainantRespondentFiled
CC005000000259151Tushar Sopan GogawaleJRS Associates23/07/2023
CC005000000259176Manish Dinesh ShethJRS Associates23/07/2023
CC005000000259177Darshan Rajendra DeoreJRS Associates23/07/2023
CC005000000259178Jyoti Tushar ShethJRS Associates23/07/2023
CC005000000259181Sameer Prabhakar JumleJRS Associates23/07/2023
CC005000000259179Yogesh Manohar ChaudhariJRS Associates23/07/2023
CC005000000259180Aniket Sadashiv KulkarniJRS Associates23/07/2023
CC005000000259182Ameya Ambadasrao ShiurkarJRS Associates23/07/2023
CC005000000259184Saurabh Pureshottam UpganlawarJRS Associates23/07/2023
CC005000000259186Omkar Bhagawan KotawadekarJRS Associates23/07/2023
CC005000000259187Indrabhan chimaji satputeJRS Associate24/07/2023
CC005000000259188Ajay Hemant DeshmukhJRS Associates23/07/2023
CC005000000259189Usha vasant gokhaleJRS Associates23/07/2023
CC005000000259190Bandu Murlidhar JoshiJRS Assoicates23/07/2023
CC005000000259192Pramod Dhansing DhaneJRS Associates23/07/2023
CC005000000259191sayaji ganpat shriramJRS Associates23/07/2023
CC005000000259193Geetajali Ashutosh ChavanJRS Associates23/07/2023
CC005000000259194Swapnil Arjun MoreJRS Associates29/07/2023
CC005000000259195Santosh Lalasaheb ShindeJRS Associates23/07/2023
CC005000000259196Mahesh Madanrao JadhavJRS Associates23/07/2023
CC005000000259223Ganesh Ramnath MithareJRS Associates28/07/2023
CC005000000259232Shubhada Aniruddha AbhyankarJRS Associates29/07/2023
CC005000000259243Amol BobadeJRS Associates02/08/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Feb 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Feb 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Feb 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Feb 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 2 Nov 2021

Documents filed65

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of ConveyanceFile: Declaration 2022 (1)_1_11zon.pdf20 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5_JRS_20-21.pdf20 Jun 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 dated 01012022_compressed (1).pdf5 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect Certificate.pdf25 Feb 2022
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf25 Feb 2022
Disclosure of sold/ booked inventoryFile: JRS Sold Unsold_Q2_compressed.pdf2 Nov 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Atmosphere C wing Residential Completion Certificate1.pdf2 Nov 2021
Architect’s Certificate on Completion of Project (Form 4)File: Form-4.pdf2 Nov 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Declaration deed Nov 8743-2012-compressed_compressed.pdf2 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A.pdf10 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: JRS FORM 5.pdf10 Jun 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Ar.pdf10 Jun 2021
Details of encumbrancesFile: Magma Loan- No objection Certificate.pdf28 May 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A-Dec18.pdf18 Dec 2019
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A_Mar19.pdf18 Dec 2019
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A_Jun19.pdf18 Dec 2019
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A_Sep19.pdf18 Dec 2019
Certificates of CA (Form 5)File: Form 5_CA Certificate_Final.pdf18 Dec 2019
Certificates of CA (Form 5)File: Form 5_JRS.pdf18 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5_JRS.pdf18 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect certificate.pdf26 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 ER Certificate.pdf26 Aug 2019
Certificates of CA (Form 3)File: Form 3.pdf26 Aug 2019
Layout approvalFile: 1.pdf19 Feb 2019
Building plan approvalFile: 2.pdf19 Feb 2019
Building plan approvalFile: 3.pdf19 Feb 2019
Building plan approvalFile: 4.pdf19 Feb 2019
Building plan approvalFile: 4.pdf19 Feb 2019
Building plan approvalFile: 5.pdf19 Feb 2019
Building plan approvalFile: 6.pdf19 Feb 2019
Building plan approvalFile: 7.pdf19 Feb 2019
Copy of the legal title reportFile: Search and title_Compressed.pdf19 Feb 2019
Details of encumbrancesFile: maGMA MORTGAGE pdf.pdf19 Feb 2019
Details of encumbrancesFile: maGMA MORTGAGE pdf.pdf19 Feb 2019
Copy of Layout Approval (in case of layout)File: 1.pdf19 Feb 2019
Building Plan Approval (IOD)File: 2.pdf19 Feb 2019
Building Plan Approval (IOD)File: 3.pdf19 Feb 2019
Building Plan Approval (IOD)File: 4.pdf19 Feb 2019
Building Plan Approval (IOD)File: 4.pdf19 Feb 2019
Building Plan Approval (IOD)File: 5.pdf19 Feb 2019
Building Plan Approval (IOD)File: 6.pdf19 Feb 2019
Building Plan Approval (IOD)File: 7.pdf19 Feb 2019
Commencement Certificates / NA Order for plotted developmentFile: comemcement 2019-ilovepdf-compressed.pdf19 Feb 2019
Proforma of Allotment letterFile: Draft RERA Agreement C WIng.pdf19 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate- percentage completion.pdf29 Sep 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate- percentage completion.pdf29 Sep 2018
Certificates of CA (Form 5)File: Form 5_CA Certificate_Final.pdf29 Sep 2018
PAN CardFile: jrs pan card.pdf2 May 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Cert - C Bldg.pdf2 May 2018
Copy of the legal title reportFile: search and title.pdf19 Jul 2017
Details of encumbrancesFile: Encumberence.pdf19 Jul 2017
Declaration in FORM BFile: Form B.pdf19 Jul 2017
Proforma of Allotment letterFile: Agreement.pdf19 Jul 2017
Proforma of Allotment letterFile: ALLOTMENT LETTER .pdf19 Jul 2017
Layout approvalFile: Plan 001-C.pdf9 Jul 2017
Building plan approvalFile: Plan 002- C.pdf9 Jul 2017
Building plan approvalFile: Plan 003-C.pdf9 Jul 2017
Building plan approvalFile: Plan 004-C.pdf9 Jul 2017
Copy of Layout Approval (in case of layout)File: Plan 001-C.pdf9 Jul 2017
Building Plan Approval (IOD)File: Plan 002- C.pdf9 Jul 2017
Building Plan Approval (IOD)File: Plan 003-C.pdf9 Jul 2017
Building Plan Approval (IOD)File: Plan 004-C.pdf9 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect's Certificate (RERA).pdf9 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineer's Certificate (RERA).pdf9 Jul 2017
Certificates of CA (Form 3)File: Form 3 -Gugale and Associates RERA.pdf9 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Atmosphere - C Wing on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near AMBEGAON13,700+ in Pune

2 kmAtmosphere - C WingCompleted 83Lapsed / revoked 38Other 74Dot size: filed unitsN

Filed coordinates, straight-line distance. 195 registered projects within 2 km.

Builder: JRS Associates

JRS Associates has 1 registration on MahaRERA, including Atmosphere - C Wing. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Atmosphere - C Wing is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Atmosphere - C Wing?

The registered promoter entity is JRS Associates, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Atmosphere - C Wing?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Atmosphere - C Wing?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Atmosphere - C Wing?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Atmosphere - C Wing?

The professionals named in the filing: Architect: Ar Siddarth Harishchandrakar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Atmosphere - C Wing?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Atmosphere - C Wing. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Atmosphere - C Wing to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.