Home / Browse projects / Bengaluru Urban, Karnataka / Atmos Silverwoods
Atmos Silverwoods
By ATMOS CONSTRUCTIONS PRIVATE LIMITED
RG-KA-64989 · RERA PRM/KA/RERA/1251/472/PR/080823/006129 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
Saved.
Atmos Silverwoods is a Residential/Group Housing project by ATMOS CONSTRUCTIONS PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/472/PR/080823/006129 on 8 Aug 2023. Possession is promised by 31 May 2027. The completion date has moved by 12 months from the original filing. 59 of the 76 units on this registration are recorded sold or booked, and 5 of 13 construction stages are filed complete.
At a glance
Project
- NameAtmos Silverwoods
- TypeResidential/Group Housing
- Location
- Yelahanka
- Bengaluru Urban
- 562157
- Pincode562157
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/472/PR/080823/006129
- ReraGenie IDRG-KA-64989
Builder
- NameATMOS CONSTRUCTIONS PRIVATE LIMITED
- Entity typeCompany
- CINU70109KA2022PTC168197
- GSTIN29AAXCA9384P1Z7
- Authorized SignatoryPabbareddy Sai Praneeth Reddy
- CeoPabbareddy Sai Praneeth Reddy
- DirectorsPabbareddy Sai Praneeth Reddy, Chilumula Nidhi
- Project HeadL Rangaswamy Reddy
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on8 Aug 2023
- Promised completion31 May 2027
- Revised completionRevised to 31 May 2027 (originally 31 May 2026)
- Buildings5 building records
- Documents filed190 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | - | - | - | 10 | 0 | 10 |
| B | - | - | - | 30 | 0 | 30 |
| C | - | - | - | 27 | 0 | 27 |
| D | - | - | - | 2 | 0 | 2 |
| E | - | - | - | 7 | 0 | 7 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 13 construction stages are filed complete. The stage furthest along is Masonry Construction, at 96%.
Building: 65% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | Not applicable |
| RCC or MS Framed structure | 100% |
| Masonry Construction | 96% |
| Plastering inside , outside & Ceiling | 78% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 82% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 25% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 50% |
| Painting | 20% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | Not applicable |
| Internal and External work including landscapes as per sanctioned drawings | Not applicable |
Progress on shared amenities40
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 25% |
| Sewage and Drainage System | Yes | 25% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 5% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | Yes | 10% |
| Electricity supply transformer and substation | Yes | 50% |
| Storm water drains | Yes | 5% |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | Yes | 50% |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | Yes | 75% |
| Indoor Sports facility | Yes | 100% |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 0% |
| Parks | Yes | 90% |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning | Yes | 0% |
| Staircases | Yes | 0% |
| Lifts | No | Not applicable |
| Corridor/Lobbies | No | Not applicable |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | No | Not applicable |
| Basement | No | Not applicable |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas | Yes | 0% |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership7
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| M/S.Shri. Maruthi properties | - | - |
| M/S.Shri. Maruthi properties | - | - |
| M/S.Shri. Maruthi properties | - | - |
| M/S.Shri. Maruthi properties | - | - |
| M/S.Shri. Maruthi properties | - | - |
| M/S.Shri. Maruthi properties | - | - |
| M/S.Shri. Maruthi properties | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 79.00 cr | Rs 26.00 cr |
| On-site expenditure-Site Overhead | Rs 7.50 cr | Rs 7.54 cr |
| Payment of taxes | Rs 7.50 cr | Rs 3.89 cr |
| On-site expenditure-Consultants Fees | Rs 2.80 cr | Rs 1.58 cr |
| On-site expenditure-Salaries of workers | - | Rs 10.46 cr |
| On-site expenditure-Cost Of Services(Water, Electricity, Sewage) | - | Rs 3.56 cr |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Santosh B Shetty |
| Engineer | Roshan |
| Chartered Accountant | Manjunath N |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterothers; Shortage of Building Materials, Concrete, Jalli etc; Shortage of Labour; Transport strike - Delay in Delivery of Material; Force Majeure; Force Majeure; Force Majeure; Force Majeure; Force Majeure; Force Majeure; Force Majeure
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed190
As listed on the registration, under the names the promoter filed them with; the newest 80 of 190 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/472/PR/080823/006129 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Q2 FY 26-27.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Q2 FY 26-27.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Q2 FY 26-27.pdf | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Q1 FY 26-27.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Q1 FY 26-27.PDF | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Q1 FY 26-27.pdf | 15 Jul 2026 |
| Sold and unsold units detailsFile: Letter - RERA - Atmos Silverwoods - unsold units.pdf | 17 Apr 2026 |
| Notarized affidavit Form BFile: Form B_compressed.pdf | 17 Apr 2026 |
| Form Ex 7_compressedFile: Form Ex 7_compressed.pdf | 17 Apr 2026 |
| Notarized affidavit for ApprovalsFile: Affidavit - RERA - Atmos Silverwoods.pdf | 17 Apr 2026 |
| Engineer licenseFile: CE Certificate Vinod (1).pdf | 17 Apr 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Silver Woods Q4.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Silver Woods Q4.PDF | 15 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Silver woods engi.pdf | 15 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: ca compressed.pdf | 19 Feb 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: arc.pdf | 19 Feb 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: eng compressed.pdf | 19 Feb 2026 |
| Details of sources of funds Atmos Silverwoods letter dated 07 08 2023File: Details of sources of funds Atmos Silverwoods letter dated 07 08 2023.pdf | 7 Aug 2023 |
| HDFC bank statementFile: HDFC bank statement.pdf | 7 Aug 2023 |
| Suporting documents for LoanFile: Suporting documents for Loan.pdf | 7 Aug 2023 |
| Receipts from promters as per booksFile: Receipts from promters as per books.pdf | 7 Aug 2023 |
| Declaration for RERA designated accountFile: Declaration for RERA designated account.pdf | 2 Aug 2023 |
| Supporting letter for financial involvement of promoterFile: Financial Supporting Letter - Atmos.pdf | 11 Jul 2023 |
| Bank funding approval letterFile: Project Loan Approval Letter.pdf | 11 Jul 2023 |
| Project Loan sanction LetterFile: Project Loan Approval Letter.pdf | 21 Jun 2023 |
| Latest Account Statement for Sources of FundsFile: Account Statement for financial stability.pdf | 21 Jun 2023 |
| partners profit and loss account and balance sheet, 2019-20, 2020-21 & 2021-22 with CA UDIN along wiFile: Certificate of Incorporation.pdf | 21 Jun 2023 |
| Change of land use copyFile: CLU 1.pdf | 21 Jun 2023 |
| change of land use copyFile: CLU 2.pdf | 21 Jun 2023 |
| Survey Sketch supporting for Kharab areaFile: Survey Sketch.pdf | 21 Jun 2023 |
| Village MapFile: Village Map.pdf | 21 Jun 2023 |
| Demarked Village MapFile: Demarked Village Map.pdf | 21 Jun 2023 |
| source of fund supporting documentsFile: 1 source of fund supporting documents.pdf | 9 Jun 2023 |
| Declaration for P&L AccountFile: 2 Declaration for P&L Account.pdf | 9 Jun 2023 |
| KAT order No KAT(A)856 2007 dated 31 01 20218File: 3 KAT order No KAT(A)856 2007 dated 31 01 20218.pdf | 9 Jun 2023 |
| Cancellation deed Sy no 126 6File: 4 Cancellation deed Sy no 126 6.pdf | 9 Jun 2023 |
| Cancellation deedFile: 5 Cancellation deed.pdf | 9 Jun 2023 |
| EC Sy No 126 7File: 6 EC Sy No 126 7.pdf | 9 Jun 2023 |
| PLAN APPROVALFile: 7 PLAN APPROVAL.pdf | 9 Jun 2023 |
| Ground Floor PlanFile: 7 Ground Floor Plan.pdf | 9 Jun 2023 |
| First Floor PlanFile: 7 First Floor Plan.pdf | 9 Jun 2023 |
| Second Floor PlanFile: 7 Second Floor Plan.pdf | 9 Jun 2023 |
| Terrace Floor PlanFile: 7 Terrace Floor Plan.pdf | 9 Jun 2023 |
| CDPFile: 10 CDP.pdf | 9 Jun 2023 |
| Village mapFile: 11 Village map.pdf | 9 Jun 2023 |
| Commencement certificateFile: 12 Commencement certificate.pdf | 9 Jun 2023 |
| Structural StabilityFile: 16 Structural Stability.pdf | 9 Jun 2023 |
| STPFile: 18 STP.pdf | 9 Jun 2023 |
| sale deed dated 12 05 2016File: 5 sale deed dated 12 05 2016.pdf | 9 Jun 2023 |
| Water NOC with fee recFile: Water NOC with fee rec.pdf | 9 Jun 2023 |
| RTC, survey 126/5 | - |
| Mutation, survey 126/5 | - |
| Encumbrance Certificate, survey 126/5 | - |
| Conversion/Alienation Order, survey 126/5 | - |
| Sale/Title/Gift Deed, survey 126/5 | - |
| JDA, survey 126/5 | - |
| Khatha, survey 126/5 | - |
| RTC, survey 126/10 | - |
| Mutation, survey 126/10 | - |
| Encumbrance Certificate, survey 126/10 | - |
| Conversion/Alienation Order, survey 126/10 | - |
| Sale/Title/Gift Deed, survey 126/10 | - |
| JDA, survey 126/10 | - |
| Khatha, survey 126/10 | - |
| RTC, survey 126/6 | - |
| Mutation, survey 126/6 | - |
| Encumbrance Certificate, survey 126/6 | - |
| Conversion/Alienation Order, survey 126/6 | - |
| Sale/Title/Gift Deed, survey 126/6 | - |
| JDA, survey 126/6 | - |
| Khatha, survey 126/6 | - |
| RTC, survey 126/7 | - |
| Mutation, survey 126/7 | - |
| Encumbrance Certificate, survey 126/7 | - |
| Conversion/Alienation Order, survey 126/7 | - |
| Sale/Title/Gift Deed, survey 126/7 | - |
| JDA, survey 126/7 | - |
| Khatha, survey 126/7 | - |
| RTC, survey 126/12 | - |
| Mutation, survey 126/12 | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Atmos Silverwoods on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 4 registered projects within 2 km.
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
EMBASSY VERDE
EMBASSY DEVELOPMENTS LIMITED
Aeropolis, a project of Sattva Group
TRINAYANI REALTOR PRIVATE LIMITED
DS MAX SKY SHLOKAM
DS Max Properties Private Limited
EMBASSY SOUTH RESERVE
SUMMIT DEVELOPMENTS LIMITED
Bhartiya Garden Estate Phase-1
Bhartiya Urban Pvt Ltd
See every Bengaluru Urban project, with the district possession charts
Builder: ATMOS CONSTRUCTIONS PRIVATE LIMITED
ATMOS CONSTRUCTIONS PRIVATE LIMITED has 2 registrations on RERA Karnataka, including Atmos Silverwoods and ATMOS TROPICALWOODS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Atmos Silverwoods is delayed beyond 31 May 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Atmos Silverwoods?
The registered promoter entity is ATMOS CONSTRUCTIONS PRIVATE LIMITED, a company as per the filing. Its CIN U70109KA2022PTC168197 and GSTIN 29AAXCA9384P1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Atmos Silverwoods?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Atmos Silverwoods?
The professionals named in the filing: Architect: Santosh B Shetty; Engineer: Roshan; Chartered Accountant: Manjunath N. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Atmos Silverwoods?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback