Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
May 2027Possession promisedmoved 12 months from the original
5 of 13Construction stages donefurthest along: Masonry Construction, 96%
17 of 76Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 190 documents Report an error

Atmos Silverwoods is a Residential/Group Housing project by ATMOS CONSTRUCTIONS PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/472/PR/080823/006129 on 8 Aug 2023. Possession is promised by 31 May 2027. The completion date has moved by 12 months from the original filing. 59 of the 76 units on this registration are recorded sold or booked, and 5 of 13 construction stages are filed complete.

At a glance

Project

  • NameAtmos Silverwoods
  • TypeResidential/Group Housing
  • Location
    • Yelahanka
    • Bengaluru Urban
    • 562157
  • Pincode562157
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/472/PR/080823/006129
  • ReraGenie IDRG-KA-64989

Builder

  • NameATMOS CONSTRUCTIONS PRIVATE LIMITED
  • Entity typeCompany
  • CINU70109KA2022PTC168197
  • GSTIN29AAXCA9384P1Z7
  • Authorized SignatoryPabbareddy Sai Praneeth Reddy
  • CeoPabbareddy Sai Praneeth Reddy
  • DirectorsPabbareddy Sai Praneeth Reddy, Chilumula Nidhi
  • Project HeadL Rangaswamy Reddy
  • Other registrations1 more →

Key dates

this monthRegisteredAug 2023First promiseMay 2026Revised toMay 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on8 Aug 2023
  • Promised completion31 May 2027
  • Revised completionRevised to 31 May 2027 (originally 31 May 2026)
  • Buildings5 building records
  • Documents filed190 files

Current status

78%59 of 76 units booked
56.5%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---10010
B---30030
C---27027
D---202
E---707

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 13 construction stages are filed complete. The stage furthest along is Masonry Construction, at 96%.

Building: 65% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction96%
Plastering inside , outside & Ceiling78%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification82%
Dadoing, Skirting, Flooring, Tiles work (All types)25%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing50%
Painting20%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes25%
Sewage and Drainage SystemYes25%
Water conservation/rain water harvesting/recharge of ground waterYes5%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes10%
Electricity supply transformer and substationYes50%
Storm water drainsYes5%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes50%
Community HallNoNot applicable
Outdoor Sports facilityYes75%
Indoor Sports facilityYes100%
Swimming PoolYes0%
GymYes0%
ParksYes90%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningYes0%
StaircasesYes0%
LiftsNoNot applicable
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes0%
Outer WallYes0%
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership7

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area16,339 sq m
Named landowners7
LandownerVillageDistrict
M/S.Shri. Maruthi properties--
M/S.Shri. Maruthi properties--
M/S.Shri. Maruthi properties--
M/S.Shri. Maruthi properties--
M/S.Shri. Maruthi properties--
M/S.Shri. Maruthi properties--
M/S.Shri. Maruthi properties--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 96.80 cr
Cost incurredRs 54.73 cr
Spent of the estimate56.54%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 79.00 crRs 26.00 cr
On-site expenditure-Site OverheadRs 7.50 crRs 7.54 cr
Payment of taxesRs 7.50 crRs 3.89 cr
On-site expenditure-Consultants FeesRs 2.80 crRs 1.58 cr
On-site expenditure-Salaries of workers-Rs 10.46 cr
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)-Rs 3.56 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSantosh B Shetty
EngineerRoshan
Chartered AccountantManjunath N

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/472/PR/260418/006129May 2026 → May 2027

Reason as filed by the promoterothers; Shortage of Building Materials, Concrete, Jalli etc; Shortage of Labour; Transport strike - Delay in Delivery of Material; Force Majeure; Force Majeure; Force Majeure; Force Majeure; Force Majeure; Force Majeure; Force Majeure

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed190

As listed on the registration, under the names the promoter filed them with; the newest 80 of 190 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/472/PR/080823/006129 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Q2 FY 26-27.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Q2 FY 26-27.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Q2 FY 26-27.pdf15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Q1 FY 26-27.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Q1 FY 26-27.PDF15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Q1 FY 26-27.pdf15 Jul 2026
Sold and unsold units detailsFile: Letter - RERA - Atmos Silverwoods - unsold units.pdf17 Apr 2026
Notarized affidavit Form BFile: Form B_compressed.pdf17 Apr 2026
Form Ex 7_compressedFile: Form Ex 7_compressed.pdf17 Apr 2026
Notarized affidavit for ApprovalsFile: Affidavit - RERA - Atmos Silverwoods.pdf17 Apr 2026
Engineer licenseFile: CE Certificate Vinod (1).pdf17 Apr 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Silver Woods Q4.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Silver Woods Q4.PDF15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Silver woods engi.pdf15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: ca compressed.pdf19 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: arc.pdf19 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: eng compressed.pdf19 Feb 2026
Details of sources of funds Atmos Silverwoods letter dated 07 08 2023File: Details of sources of funds Atmos Silverwoods letter dated 07 08 2023.pdf7 Aug 2023
HDFC bank statementFile: HDFC bank statement.pdf7 Aug 2023
Suporting documents for LoanFile: Suporting documents for Loan.pdf7 Aug 2023
Receipts from promters as per booksFile: Receipts from promters as per books.pdf7 Aug 2023
Declaration for RERA designated accountFile: Declaration for RERA designated account.pdf2 Aug 2023
Supporting letter for financial involvement of promoterFile: Financial Supporting Letter - Atmos.pdf11 Jul 2023
Bank funding approval letterFile: Project Loan Approval Letter.pdf11 Jul 2023
Project Loan sanction LetterFile: Project Loan Approval Letter.pdf21 Jun 2023
Latest Account Statement for Sources of FundsFile: Account Statement for financial stability.pdf21 Jun 2023
partners profit and loss account and balance sheet, 2019-20, 2020-21 & 2021-22 with CA UDIN along wiFile: Certificate of Incorporation.pdf21 Jun 2023
Change of land use copyFile: CLU 1.pdf21 Jun 2023
change of land use copyFile: CLU 2.pdf21 Jun 2023
Survey Sketch supporting for Kharab areaFile: Survey Sketch.pdf21 Jun 2023
Village MapFile: Village Map.pdf21 Jun 2023
Demarked Village MapFile: Demarked Village Map.pdf21 Jun 2023
source of fund supporting documentsFile: 1 source of fund supporting documents.pdf9 Jun 2023
Declaration for P&L AccountFile: 2 Declaration for P&L Account.pdf9 Jun 2023
KAT order No KAT(A)856 2007 dated 31 01 20218File: 3 KAT order No KAT(A)856 2007 dated 31 01 20218.pdf9 Jun 2023
Cancellation deed Sy no 126 6File: 4 Cancellation deed Sy no 126 6.pdf9 Jun 2023
Cancellation deedFile: 5 Cancellation deed.pdf9 Jun 2023
EC Sy No 126 7File: 6 EC Sy No 126 7.pdf9 Jun 2023
PLAN APPROVALFile: 7 PLAN APPROVAL.pdf9 Jun 2023
Ground Floor PlanFile: 7 Ground Floor Plan.pdf9 Jun 2023
First Floor PlanFile: 7 First Floor Plan.pdf9 Jun 2023
Second Floor PlanFile: 7 Second Floor Plan.pdf9 Jun 2023
Terrace Floor PlanFile: 7 Terrace Floor Plan.pdf9 Jun 2023
CDPFile: 10 CDP.pdf9 Jun 2023
Village mapFile: 11 Village map.pdf9 Jun 2023
Commencement certificateFile: 12 Commencement certificate.pdf9 Jun 2023
Structural StabilityFile: 16 Structural Stability.pdf9 Jun 2023
STPFile: 18 STP.pdf9 Jun 2023
sale deed dated 12 05 2016File: 5 sale deed dated 12 05 2016.pdf9 Jun 2023
Water NOC with fee recFile: Water NOC with fee rec.pdf9 Jun 2023
RTC, survey 126/5-
Mutation, survey 126/5-
Encumbrance Certificate, survey 126/5-
Conversion/Alienation Order, survey 126/5-
Sale/Title/Gift Deed, survey 126/5-
JDA, survey 126/5-
Khatha, survey 126/5-
RTC, survey 126/10-
Mutation, survey 126/10-
Encumbrance Certificate, survey 126/10-
Conversion/Alienation Order, survey 126/10-
Sale/Title/Gift Deed, survey 126/10-
JDA, survey 126/10-
Khatha, survey 126/10-
RTC, survey 126/6-
Mutation, survey 126/6-
Encumbrance Certificate, survey 126/6-
Conversion/Alienation Order, survey 126/6-
Sale/Title/Gift Deed, survey 126/6-
JDA, survey 126/6-
Khatha, survey 126/6-
RTC, survey 126/7-
Mutation, survey 126/7-
Encumbrance Certificate, survey 126/7-
Conversion/Alienation Order, survey 126/7-
Sale/Title/Gift Deed, survey 126/7-
JDA, survey 126/7-
Khatha, survey 126/7-
RTC, survey 126/12-
Mutation, survey 126/12-

How this compares with Bengaluru Urban

78%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Atmos Silverwoods on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmAtmos SilverwoodsOther 4Dot size: filed unitsN

Filed coordinates, straight-line distance. 4 registered projects within 2 km.

Builder: ATMOS CONSTRUCTIONS PRIVATE LIMITED

ATMOS CONSTRUCTIONS PRIVATE LIMITED has 2 registrations on RERA Karnataka, including Atmos Silverwoods and ATMOS TROPICALWOODS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Atmos Silverwoods is delayed beyond 31 May 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Atmos Silverwoods?

The registered promoter entity is ATMOS CONSTRUCTIONS PRIVATE LIMITED, a company as per the filing. Its CIN U70109KA2022PTC168197 and GSTIN 29AAXCA9384P1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Atmos Silverwoods?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Atmos Silverwoods?

The professionals named in the filing: Architect: Santosh B Shetty; Engineer: Roshan; Chartered Accountant: Manjunath N. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Atmos Silverwoods?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Atmos Silverwoods. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Atmos Silverwoods to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.