Home / Browse projects / Pune, Maharashtra / Aston Plaza Phase II

Registered No litigation declared Commercial project

Aston Plaza Phase II

By SKP Corp Private Limited

RG-MH-99896 · RERA P52100017499 · Last updated on MahaRERA portal: 21 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 70 months
  • 5 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jul 2027Possession promisedmoved 70 months from the original
5 of 11Construction stages donefurthest along: Slabs of Super Structure, 90%
10 of 63Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 107 documents Report an error

Aston Plaza Phase II is a Commercial project by SKP Corp Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100017499 on 23 Aug 2018. Possession is promised by 31 Jul 2027. The completion date has moved by 70 months from the original filing. 53 of the 63 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameAston Plaza Phase II
  • TypeCommercial
  • Location
    • Katraj Ambegaon Road
    • Ambegaon Bk
    • Haveli
    • Pune
    • 411046
  • Pincode411046
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100017499
  • ReraGenie IDRG-MH-99896

Builder

  • NameSKP Corp Private Limited
  • Entity typeCompany
  • Other registrations3 more →
  • Completed2 of 4
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2018First promiseSep 2021Revised toJul 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Aug 2018
  • Promised completion31 Jul 2027
  • Revised completionRevised to 31 Jul 2027 (originally 30 Sep 2021)
  • Buildings1 building record
  • Documents filed107 files

Current status

84%53 of 63 units booked
92.1%Work done, per cost certificate

Figures as on 21 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Aston Plaza Phase IINA5506363

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 90%.

Aston Plaza Phase II: 94% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%

Progress on shared amenities15

As on 21 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyYes85%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes70%
Street LightingYes80%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes85%
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingYes70%
Energy managemcntYes50%
Fire protection and fire safety requirementsYes85%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed463

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots463
Closed/Covered200
Open Space263

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,507 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI8635.91
Proposed, not sanctioned8,636 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWakadewadi, Pune
Estimated costRs 49.59 cr
Cost incurredRs 45.66 cr
Work done92.07%
BuildingWingEstimatedIncurred
Aston Plaza Phase IINARs 44.75 crRs 41.51 cr
-NARs 4.84 crRs 4.15 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectManoj Tatooskar
EngineerPrashant RANANAWARE
Chartered AccountantDharini Naswa and Associates
Chartered AccountantSSAP and Associates LLP
PartnerRole in project
SKP Corp Private Limited-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P52100017499/WarSep 2021 → Jul 2027

Reason as filed by the promoterNA

EXT52100009253Sep 2021 → Sep 2022

Reason as filed by the promoterDue to post pandemic situation market condition is not favorable and therefore the sales is slow for commercial properties. The work progress is slow and therefore the estimated time for completion is requested to be increased by one (1) year period.

EXT52100015232Sep 2021 → Mar 2024

Reason as filed by the promoterThe slow market condition and a slump in the real estate market during the period created acute economic crises which ultimately slowed down the sale transactions. However, somehow we were managing and pulling ourselves to complete the project in the scheduled time. The market conditions were getting better but due to the emergence of the Covid-19 outbreak, we faced a massive downfall affecting the project. we are committed to providing our customers with what was promised to them with the utmost standard. The customers support us and thus provided consent for an extension. Therefore, we reque

EXT52100027638Sep 2021 → Mar 2026

Reason as filed by the promoter1. Project is 70% Completed. 2. The Project has received Part OC on 26/03/2024. 3. Consent of 70.59 % of Allottees Uploaded for extension 4. Form B Uploaded in other Tab 1 and also in Main application. 5. PERT Chart is Uploaded in other tab 2 and also in Other Technical tab in main application 6. Explanatory note For delay in project completion uploaded in other Tab 7. QPR is Uploaded till Date

EA30042620783Sep 2021 → Mar 2027

Reason as filed by the promoter1. The project stands at 95% completion. 2. The consent of 58.49% of allottees has been uploaded in support of this extension application. 3. Form B uploaded. 4. PERT for the remaining completion work is uploaded in the Application. 5. The Project got delayed due to following reasons: a) Unfavourable market conditions affecting sales, cash flow, and project scheduling. b) Financial constraints leading to delays in procurement and site execution. c) Shortage of skilled labour and construction materials. d) Increased construction costs, especially post-pandemic labour expenses. e) Unseasonal and

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Aug 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Aug 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Aug 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Apr 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 27 Mar 2024

Documents filed107

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 107 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Achitect Certificate Aston Plaza Phase II.pdf21 Aug 2026
Withdrawal Update Form 2File: Form2-AP-Jan 2026 - Mar 2026.pdf21 Aug 2026
Withdrawal Update Form 3File: Ason Plaza Form 3- June 26.pdf21 Aug 2026
Layout approvalFile: Layoout plan Page 1.pdf20 Aug 2026
Building plan approvalFile: Building Plan Page 2.pdf20 Aug 2026
Building plan approvalFile: Building Plan Page 3.pdf20 Aug 2026
Building plan approvalFile: Building Plan Page 4.pdf20 Aug 2026
Building plan approvalFile: Building Plan Page 5.pdf20 Aug 2026
Building plan approvalFile: Section Elevation Building Plan Page 6.pdf20 Aug 2026
Layout approvalFile: LAYOUT PLAN...pdf20 May 2026
Building plan approvalFile: BASEMENT 1 and BASEMENT 2 PLAN.pdf20 May 2026
Building plan approvalFile: GROUND and FIRST FLOOR.pdf20 May 2026
Building plan approvalFile: SECOND and THIRD FLOOR.pdf20 May 2026
Building plan approvalFile: 4TH 5TH and 6TH FLOOR PLAN.pdf20 May 2026
Form 2A (FY 2025-2026)File: Form 2A - Aston Plaza II - FY 2025-26.pdf30 Apr 2026
Withdrawal Update Form 1File: ASTON PLAZA PHASE II -FORM 1.pdf17 Apr 2026
Withdrawal Update Form 2File: Form2-AP-Jan 2026 - Mar 2026.pdf17 Apr 2026
Withdrawal Update Form 3File: SKPPL-ASTON PLAZA-FORM 3-31-03-26.pdf17 Apr 2026
Withdrawal Update Form 1File: Aston Plaza-form 1.pdf16 Jan 2026
Withdrawal Update Form 2File: Form2-AP-Oct 2025 - Dec 2025.pdf16 Jan 2026
Withdrawal Update Form 3File: Aston Plaza Form 3- 31-12-25.pdf16 Jan 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate Aston Plaza Phase -II sept.pdf17 Oct 2025
Withdrawal Update Form 2File: Form2-AP-July 2025-Sep 2025.pdf17 Oct 2025
Withdrawal Update Form 3File: Aston Plaza - CA Cerificate.pdf17 Oct 2025
Form 5 (FY 2024-2025)File: Aston Plaza - Form 5.pdf17 Oct 2025
Certificates of CA (Form 3)File: Form 3 - Aston Plaza Ph 2.pdf2 May 2025
Declaration in FORM BFile: Form B.pdf19 Mar 2025
Other - TechnicalFile: PERT Chart.pdf19 Mar 2025
Details of encumbrances concerned to FinanceFile: Encumbrance report.pdf19 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19).pdf19 Feb 2025
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate - Aston Plaza Ph-II (1).pdf19 Feb 2025
CERSAI detailsFile: Declaration for CERSAI.pdf19 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration about Separate Bank Account - Aston Plaza-II.pdf19 Feb 2025
Details of encumbrances concerned to LegalFile: Encumbrance report.pdf19 Feb 2025
Proforma of Agreement for saleFile: 1 Proforma of Allotment letter.pdf19 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf19 Feb 2025
Disclosure for secured/unsecured finance availed for the projectFile: Encumbrance report.pdf19 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Aston Plaza Form 5.pdf20 Jan 2025
Certificates of CA (Form 3)File: Form 3 - Aston Plaza-II.pdf17 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Aston Plaza - II - Form 2.pdf17 Jan 2025
Disclosure of sold/ booked inventoryFile: Aston Plaza Ph -II Sold Inverntory 31-12-2024.pdf17 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Aston Plaza - II - Form 2A.pdf17 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 - ASTON PLAZA - 31-3-2024 SIGNED.pdf17 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Aston Plaza Phase -II.pdf13 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Aston Plaza Phase -II.pdf17 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2-AstonPlaza-Jan24-Mar24 (2).pdf17 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A-AstonPlaza-Jan24-Mar24.pdf17 Apr 2024
Disclosure of sold/ booked inventoryFile: Aston Plaza - Sold Inventory as on 31-03-2024.pdf17 Apr 2024
Certificates of CA (Form 3)File: Aston Plaza - CA Cerificate.pdf17 Apr 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Aston Plaza - Part Occupancy Certificate dtd 26-03-2024.pdf27 Mar 2024
Building plan approvalFile: Aton Plaza Layout Plan.pdf20 Feb 2024
Building Plan Approval (IOD)File: Aton Plaza Layout Plan.pdf20 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Aston Plaza Phase -II Dec -2023_.pdf7 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2-AstonPlaza-04-01-2024.pdf7 Feb 2024
Disclosure of sold/ booked inventoryFile: Aston Plaza - Sold Inventory till Dec 2023.pdf7 Feb 2024
Certificates of CA (Form 3)File: Form 3 - Aston Plaza Ph II.pdf7 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Aston Plaza Phase -II.pdf14 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2-AP-Jan-March2023.pdf14 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2-AP-July-September2023 (2).pdf14 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A-AP-July-September2023.pdf14 Oct 2023
Disclosure of sold/ booked inventoryFile: Aston Plaza till 30-09-2023.pdf14 Oct 2023
Certificates of CA (Form 3)File: SKPPL - ASTON PLAZA - FORM 3 - 31-3-23.pdf14 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 ASTON PLAZA 31-3-2023.pdf14 Oct 2023
Disclosure of sold/ booked inventoryFile: Aston Plaza PH II .pdf18 Aug 2023
Disclosure of sold/ booked inventoryFile: Aston Plaza II- Rera.pdf20 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Aston Plaza Phase -II.pdf17 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 AP II Jan23-Mar23.pdf31 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A AP II Jan23-Mar23.pdf31 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate form 1 for Aston Plaza Phase -II.pdf7 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate Aston Plaza Dec2022.pdf7 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate Aston Plaza Dec2022.pdf7 Jan 2023
Disclosure of sold/ booked inventoryFile: Rera - Aston Plaza PH II.pdf7 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate Aston Plaza.pdf22 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality assurance certificate Aston plaza.pdf22 Oct 2022
Certificates of CA (Form 3)File: ASTON PLAZA PHASE II RERA FORM 3.pdf22 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA FORM 5 ASTON PLAZA PHASE II.pdf13 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Aston Plaza Phase- II.pdf7 Oct 2022
Disclosure of sold/ booked inventoryFile: Astone Plaza II.pdf7 Oct 2022
Certificates of CA (Form 3)File: ASTONPLAZA PHASE II FORM 3.pdf7 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Certificate - Aston Plaza Phase - II.pdf7 Apr 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Silver MistPlot No. 3 Sadashiv Peth Pune30CompletedApr 2016Apr 2016

How this compares with Pune

84%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 70 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Aston Plaza Phase II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ambegaon Bk13,700+ in Pune

2 kmAston Plaza Phase IICompleted 82Lapsed / revoked 35Other 55Dot size: filed unitsN

Filed coordinates, straight-line distance. 172 registered projects within 2 km.

Builder: SKP Corp Private Limited

SKP Corp Private Limited has 4 registrations on MahaRERA, including ASTON PLAZA PHASE I and SKY Pavilion Phase I. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Aston Plaza Phase II is delayed beyond 31 Jul 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Aston Plaza Phase II?

The registered promoter entity is SKP Corp Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Aston Plaza Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Aston Plaza Phase II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Aston Plaza Phase II?

The professionals named in the filing: Architect: Manoj Tatooskar; Engineer: Prashant RANANAWARE; Chartered Accountant: Dharini Naswa and Associates; Chartered Accountant: SSAP and Associates LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Aston Plaza Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Aston Plaza Phase II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Aston Plaza Phase II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.