Home / Browse projects / Bengaluru Urban, Karnataka / Assetz Mizumi Reserve Tower A3 A5
Assetz Mizumi Reserve Tower A3 A5
By APG COMMUNITY DEVELOPMENT PRIVATE LIMITED
RG-KA-27570 · RERA PRM/KA/RERA/1251/308/PR/130526/008650 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- Litigation declared, 4 cases
Clear
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Assetz Mizumi Reserve Tower A3 A5 is a Residential/Group Housing project by APG COMMUNITY DEVELOPMENT PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/130526/008650 on 13 May 2026. Possession is promised by 31 Mar 2031. 15 of the 264 units on this registration are recorded sold or booked, and 2 of 18 construction stages are filed complete.
At a glance
Project
- NameAssetz Mizumi Reserve Tower A3 A5
- TypeResidential/Group Housing
- Location
- Anekal
- Bengaluru Urban
- 560068
- Pincode560068
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/308/PR/130526/008650
- ReraGenie IDRG-KA-27570
Builder
- NameAPG COMMUNITY DEVELOPMENT PRIVATE LIMITED
- Entity typeCompany
- CINU45203KA2014PTC077653
- GSTIN29AANCA1479M1ZZ
- Authorized SignatoryAkshay Kishore Dewani
- CeoAkshay Kishore Dewani
- DirectorsAkshay Kishore Dewani, Sanjay Sudhakar Torgal
- Project HeadGurumurthy N
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on13 May 2026
- Promised completion31 Mar 2031
- Revised completionNone
- Buildings2 building records
- Documents filed333 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TOWER 3 | - | - | - | 176 | 0 | 176 |
| Tower 5 | - | - | - | 88 | 0 | 88 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 18 construction stages are filed complete. The stage furthest along is Upto Plinth Level, at 35%.
Building: 14% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 35% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 0% |
| Retaining wall (All types) | 10% |
| RCC or MS Framed structure | 0% |
| Masonry Construction | 0% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | 0% |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | Yes | 0% |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | Yes | 0% |
| Community Hall | Yes | 0% |
| Outdoor Sports facility | Yes | 0% |
| Indoor Sports facility | Yes | 0% |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 0% |
| Parks | Yes | 0% |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | Yes | 0% |
| Staircases | Yes | 0% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | Yes | 0% |
| Fire escapes | Yes | 0% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 0% |
| Basement | Yes | 0% |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas | Yes | 0% |
| Provision for lodging of management staff and security staff | Yes | 0% |
| Water conservation and renewable energy | Yes | 0% |
| Common storage spaces | No | Not applicable |
Land and ownership26
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Mrs. Shilpa Rama Ganesh | - | - |
| Mrs. Shilpa Rama Ganesh | - | - |
| Sri. Priya Krishna | - | - |
| Jayamma | - | - |
| Sri. Priya Krishna | - | - |
| Sri. Priya Krishna | - | - |
| Raju | - | - |
| Arun Kumar | - | - |
| Arun Kumar | - | - |
| Arun Kumar | - | - |
| Raju | - | - |
| Sri. PriyaKrishna | - | - |
| Arun Kumar | - | - |
| Sri. Priya Krishna | - | - |
| Arun Kumar | - | - |
| Sri. PriyaKrishna | - | - |
| Pradeep Krishnappa | - | - |
| Sri. Priya Krishna | - | - |
| N. Girish Kumar | - | - |
| Mr. G. R. Byresh | - | - |
| Sri. Ramesh | - | - |
| Sri. Priya Krishna | - | - |
| Sri. Ramesh | - | - |
| Mr Naveen Reddy | - | - |
| Mr. Prathap Reddy | - | - |
| Mr. G. R. Byresh | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 206.63 cr | Rs 27.03 cr |
| On-site expenditure-Site Overhead | Rs 17.75 cr | Rs 7.97 cr |
| Approval | Rs 17.16 cr | Rs 5.18 cr |
| Principal sum and interest payable to financial institutions-Scheduled Banks | Rs 13.76 cr | Rs 10.62 cr |
| On-site expenditure-Consultants Fees | Rs 4.74 cr | Rs 63.81 lakh |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sandeep Rajendran |
| Engineer | B E Pruthviraja |
| Chartered Accountant | Y S Shetty & Company |
Litigation declared4
| Case | Court | Status |
|---|---|---|
| O.S. No. 109 of 2006 | Senior Civil Judge, Anekal | - |
| O.S. No. 25577 of 2023 | City Civil Judge, Mayo Hall | - |
| O.S. No. 5489 of 2024 | Principal City Civil & Sessions Judge, Bengaluru | - |
| O.S. NO. 157 OF 2012 | Principal Senior Civil Judge, Anekal | - |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed333
As listed on the registration, under the names the promoter filed them with; the newest 80 of 333 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/130526/008650 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Chartered Assetz Mizumi Reserve Tower A3 A5.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect Assetz Mizumi Reserve Tower A3 A5.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6 Engineer Assetz Mizumi Reserve Tower A3 A5.pdf | 15 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 15 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Oct 2026 |
| Q2 2026-27 KSPCB- MOEF (Above 50 Acres) | 15 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 15 Oct 2026 |
| Q2 2026-27 Fire and Safety | 15 Oct 2026 |
| Q2 2026-27 Airport Authority of India | 15 Oct 2026 |
| Q2 2026-27 BSNL/Telecommunication Department | 15 Oct 2026 |
| Q2 2026-27 Preventive Order (Injunction / Interim Order / Final Order / Stay OrderFile: Disposal order dated 06 07 2026.pdf | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Chartered Assetz Mizumi Reserve Tower A3 A5.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect Assetz Mizumi Reserve Tower A3 A5.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6 Engineer Assetz Mizumi Reserve Tower A3 A5.pdf | 15 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 15 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Jul 2026 |
| Q1 2026-27 KSPCB- MOEF (Above 50 Acres) | 15 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 15 Jul 2026 |
| Q1 2026-27 Fire and Safety | 15 Jul 2026 |
| Q1 2026-27 Airport Authority of India | 15 Jul 2026 |
| Q1 2026-27 BSNL/Telecommunication Department | 15 Jul 2026 |
| Q1 2026-27 Preventive Order (Injunction / Interim Order / Final Order / Stay OrderFile: Disposal order dated 06.07.2026.pdf | 15 Jul 2026 |
| Clarification regarding Loan deposited in 70% accountFile: Annexure 1-Clarification regarding Loan deposited in 70% account.pdf | 8 May 2026 |
| Sources of FundFile: Annexure 2-Sources of Fund.pdf | 8 May 2026 |
| Advocate Search Report Sy No 5-1File: Annexure 3A- Advocate Search Report Sy No 5-1.pdf | 8 May 2026 |
| Advocate Search Report Sy No 5-4File: Annexure 3B- Advocate Search Report Sy No 5-4.pdf | 8 May 2026 |
| Advocate Search Report Sy No 5-5File: Annexure 3C- Advocate Search Report Sy No 5-5.pdf | 8 May 2026 |
| Advocate Search Report Sy No 6File: Annexure 3D- Advocate Search Report Sy No 6.pdf | 8 May 2026 |
| Advocate Search Report Sy No 7File: Annexure 3E- Advocate Search Report Sy No 7.pdf | 8 May 2026 |
| Advocate Search Report Sy No 8-1File: Annexure 3F- Advocate Search Report Sy No 8-1.pdf | 8 May 2026 |
| Advocate Search Report Sy No 8-4File: Annexure 3G- Advocate Search Report Sy No 8-4.pdf | 8 May 2026 |
| Advocate Search Report Sy No 8-5File: Annexure 3H- Advocate Search Report Sy No 8-5.pdf | 8 May 2026 |
| Advocate Search Report Sy No 173-1File: Annexure 3I- Advocate Search Report Sy No 173-1.pdf | 8 May 2026 |
| Advocate Search Report Sy No 173-2File: Annexure 3J- Advocate Search Report Sy No 173-2.pdf | 8 May 2026 |
| Advocate Search Report Sy No 175File: Annexure 3K- Advocate Search Report Sy No 175.pdf | 8 May 2026 |
| Advocate Search Report Sy No 177-1File: Annexure 3K- Advocate Search Report Sy No 177-1.pdf | 8 May 2026 |
| Advocate Search Report Sy No 176File: Annexure 3L- Advocate Search Report Sy No 176.pdf | 8 May 2026 |
| Advocate Search Report Sy No 177-1-1File: Annexure 3M- Advocate Search Report Sy No 177-1-1.pdf | 8 May 2026 |
| Advocate Search Report Sy No 177-2File: Annexure 3N- Advocate Search Report Sy No 177-2.pdf | 8 May 2026 |
| Advocate Search Report Sy No 178File: Annexure 3O- Advocate Search Report Sy No 178.pdf | 8 May 2026 |
| Advocate Search Report Sy No 179-1File: Annexure 3P- Advocate Search Report Sy No 179-1.pdf | 8 May 2026 |
| Advocate Search Report Sy No 179-2File: Annexure 3Q- Advocate Search Report Sy No 179-2.pdf | 8 May 2026 |
| Advocate Search Report Sy No 179-2File: Annexure 3Q- Advocate Search Report Sy No 179-2.pdf | 8 May 2026 |
| Advocate Search Report Sy No 180-1File: Annexure 3R- Advocate Search Report Sy No 180-1.pdf | 8 May 2026 |
| Advocate Search Report Sy No 180-2File: Annexure 3S- Advocate Search Report Sy No 180-2.pdf | 8 May 2026 |
| Advocate Search Report Sy No 180-3File: Annexure 3T- Advocate Search Report Sy No 180-3.pdf | 8 May 2026 |
| Advocate Search Report Sy No 187-1File: Annexure 3U- Advocate Search Report Sy No 187-1.pdf | 8 May 2026 |
| Advocate Search Report Sy No 187-1File: Annexure 3V-Advocate Search Report Sy No 203.pdf | 8 May 2026 |
| Commencement CertificateFile: Annexure 4-Commencement Certificate.pdf | 8 May 2026 |
| Clarification regarding Unit deatails as KSPCB and Sanctioned PlanFile: Annexure 5-Clarification regarding Unit deatails as KSPCB and Sanctioned Plan.pdf | 8 May 2026 |
| Clarifications regarding Area in KSPCB NOCFile: Annexure 6-Clarifications regarding Area in KSPCB NOC.pdf | 8 May 2026 |
| Details of facilities ProvidedFile: Annexure 7-Details of facilities Provided.pdf | 8 May 2026 |
| Clarification regarding Car parkingFile: Annexure 8-Clarification regarding Car parking.pdf | 8 May 2026 |
| Clarification regarding update the amenties and common AreaFile: Annexure 9-Clarification regarding update the amenties and common Area.pdf | 8 May 2026 |
| Amenities DeclarationFile: Annexure 10-Amenities Declaration.pdf | 8 May 2026 |
| Self Attested engineer and Adhar who signed form 3File: Annexure 11-Self Attested engineer and Adhar who signed form 3.pdf | 8 May 2026 |
| BESCOM NOC WITH PAID RECEIPTFile: Annexure 12-BESCOM NOC WITH PAID RECEIPT.pdf | 8 May 2026 |
| Updated ATS with payment planFile: Annexure 13-Updated ATS with payment plan.pdf | 8 May 2026 |
| RTC, survey 5-4 | - |
| Mutation, survey 5-4 | - |
| Encumbrance Certificate, survey 5-4 | - |
| Conversion/Alienation Order, survey 5-4 | - |
| Sale/Title/Gift Deed, survey 5-4 | - |
| JDA, survey 5-4 | - |
| Khatha, survey 5-4 | - |
| RTC, survey 5-5 | - |
| Mutation, survey 5-5 | - |
| Encumbrance Certificate, survey 5-5 | - |
| Conversion/Alienation Order, survey 5-5 | - |
| Sale/Title/Gift Deed, survey 5-5 | - |
| JDA, survey 5-5 | - |
| Khatha, survey 5-5 | - |
| RTC, survey 173-1 | - |
| Mutation, survey 173-1 | - |
| Encumbrance Certificate, survey 173-1 | - |
| Conversion/Alienation Order, survey 173-1 | - |
| Sale/Title/Gift Deed, survey 173-1 | - |
| JDA, survey 173-1 | - |
| Khatha, survey 173-1 | - |
| RTC, survey 173-2 | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Assetz Mizumi Reserve Tower A3 A5 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 20 registered projects within 2 km.
MEMCO SKYLINE - JUTAKU
MEMCO SKYLINE PRIVATE LIMITED
SNN RAJ SERENITY
SNN Builders Private Limited
TVS Emerald Jardin
Emerald Haven Development Limited
CASAGRAND AMOR
CASA GRANDE GARDEN CITY BUILDERS PVT LTD
Assetz Mizumi Reserve Tower A1 A2 A4
APG COMMUNITY DEVELOPMENT PRIVATE LIMITED
Assetz Canvas & Cove 2.0 - Block B & C
APG HABITAT PRIVATE LIMITED
See every Bengaluru Urban project, with the district possession charts
Builder: APG COMMUNITY DEVELOPMENT PRIVATE LIMITED
APG COMMUNITY DEVELOPMENT PRIVATE LIMITED has 2 registrations on RERA Karnataka, including Assetz Mizumi Reserve Tower A3 A5 and Assetz Mizumi Reserve Tower A1 A2 A4. Its filings disclose no earlier RERA Karnataka projects. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Assetz Mizumi Reserve Tower A3 A5 is delayed beyond 31 Mar 2031?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Assetz Mizumi Reserve Tower A3 A5?
The registered promoter entity is APG COMMUNITY DEVELOPMENT PRIVATE LIMITED, a company as per the filing. Its CIN U45203KA2014PTC077653 and GSTIN 29AANCA1479M1ZZ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Assetz Mizumi Reserve Tower A3 A5?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Assetz Mizumi Reserve Tower A3 A5?
The professionals named in the filing: Architect: Sandeep Rajendran; Engineer: B E Pruthviraja; Chartered Accountant: Y S Shetty & Company. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Assetz Mizumi Reserve Tower A3 A5?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback