Home / Browse projects / Bengaluru Urban, Karnataka / ASSETZ KVN NIWA & NEO

Registration approved No litigation declared Residential/Group Housing project

ASSETZ KVN NIWA & NEO

By Elite Projects

RG-KA-28527 · RERA PRM/KA/RERA/1251/472/PR/220726/008831 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Sep 2031Possession promisedno revision filed
0 of 18Construction stages donefurthest along: Earth work and other leveling..., 70%
845 of 845Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 83 documents Report an error

ASSETZ KVN NIWA & NEO is a Residential/Group Housing project by Elite Projects in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/472/PR/220726/008831 on 22 Jul 2026. Possession is promised by 30 Sep 2031. 0 of the 845 units on this registration are recorded sold or booked, and 0 of 18 construction stages are filed complete.

At a glance

Project

  • NameASSETZ KVN NIWA & NEO
  • TypeResidential/Group Housing
  • Location
    • Yelahanka
    • Bengaluru Urban
    • 562149
  • Pincode562149
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/472/PR/220726/008831
  • ReraGenie IDRG-KA-28527

Builder

  • NameElite Projects
  • Entity typePartnership Firm
  • GSTIN29AALFE6056H1Z3
  • Authorized SignatorySaurav Guha
  • Other registrations1 more →

Key dates

this monthRegisteredJul 2026PromisedSep 2031

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on22 Jul 2026
  • Promised completion30 Sep 2031
  • Revised completionNone
  • Buildings3 building records
  • Documents filed83 files

Current status

0%0 of 845 units booked
0.5%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER A---2200220
TOWER B---3120312
TOWER C---3130313

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 18 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 70%.

Building: 4% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work70%
Foundation footing work0%
Upto Plinth Level0%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)0%
RCC or MS Framed structure0%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area22,946 sq m
Named landowners1
LandownerVillageDistrict
Elite Projects--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 682.31 cr
Cost incurredRs 3.53 cr
Spent of the estimate0.52%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 436.37 crRs 1.35 cr
On-site expenditure-Salaries of workersRs 154.07 cr-
Principal sum and interest payable to financial institutions-Scheduled BanksRs 82.53 cr-
On-site expenditure-Consultants FeesRs 9.34 crRs 2.18 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectLolita Almeida Thota
EngineerH.G.Naikar
Chartered AccountantShyam Prasad Shetty

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed83

As listed on the registration, under the names the promoter filed them with; the newest 80 of 83 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/472/PR/220726/008831 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Chartered ASSETZ KVN NIWA & NEO.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect ASSETZ KVN NIWA & NEO - RA Sign.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6 Engineer ASSETZ KVN NIWA & NEO.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Elite Projects Financials - 2025-2026File: 1 Elite Projects Financials - 2025-2026.pdf21 Jul 2026
Elite Projects AR - 2025-2026File: 1 Elite Projects AR - 2025-2026.pdf21 Jul 2026
Elite Projects Financials - 2024-2025File: 2 Elite Projects Financials - 2024-2025.pdf21 Jul 2026
Elite Projects AR - 2024-2025File: 2 Elite Projects AR - 2024-2025.pdf21 Jul 2026
Elite Projects Financials - 2023-2024File: 3 Elite Projects Financials - 2023-2024.pdf21 Jul 2026
Elite Projects AR - 2023-2024File: 3 Elite Projects AR - 2023-2024.pdf21 Jul 2026
FY 2022-23 Financials DeclarationFile: 4 FY 2022-23 Financials Declaration.pdf21 Jul 2026
CA Self-attested Membership and KYCFile: 5 CA Self-attested Membership and KYC.pdf21 Jul 2026
Clarification on QueriesFile: 1 Clarification on Queries.pdf21 Jul 2026
Proforma Agreement to SellFile: 2 Proforma Agreement to Sell.pdf21 Jul 2026
Allotment Letter - Assetz Niwa & NeoFile: 3 Allotment Letter - Assetz Niwa & Neo.pdf21 Jul 2026
Declaration Affidavit - Water SupplyFile: 4 Declaration Affidavit - Water Supply.pdf21 Jul 2026
Registration CertificateFile: Registration Certificate.pdf-
GST CertificateFile: GST Certificate.pdf-
Partnership DeedFile: Partnership reconstitution Deed-Elite.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form 1 CA Certificate.pdf-
Certificate issued by Architect Form 2File: Form 2 Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Form 3 Engineer certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non Litigation Affidavit.pdf-
Balance Sheet 2024 - 2025File: Balance sheet 2025-26.pdf-
Balance Sheet 2023 - 2024File: Balance sheet 2023-24.pdf-
Audited Profit and Loss Statement 2024 - 2025File: Profit & Loss 2024-25.pdf-
Audited Profit and Loss Statement 2023 - 2024File: Profit & Loss 2023-24.pdf-
Income Tax Return Acknowledgement 2024 - 2025File: ITR 2024-25.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: ITR 2023-24.pdf-
Buidling Permit - KIADB-
1 Site Plan-
15 Section 1-
STRUCTURAL STABILITY CERTIFICATE 2-
Project Specifications-
Form B Affidavit-
Sec 3-1 Violation Affidavit-
Advocate Search Report Title report-
NOC BESCOM-
NOC WATER-
NOC KSPCB-
NOC SEIAA-
NOC FIRE-
NOC AIRPORT-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Amenities Declaration-
CDP Master Extract-
2 Basement 2 Floor Plan-
3 Basement 1 Floor Plan-
4 Ground Floor Plan-
5 First Floor Plan Tower A B C-
6 Second Floor Tower A B C-
7 3rd Floor Plan Tower A B C-
8 Typical Floor Tower A B C-
9 19th Floor Plan Tower A B C-
10 23rd Floor Plan Tower A B C-
11 24-28th Floor Plan Tower A B C-
12 29th Floor Tower B C Terrace Floor Tower A-
13 Terrace Floor Tower B C-
14 Elevation Tower A-
15 Section 1-
16 Section 2-
Land Cost calculation Sheet-
No Sales Declaration-
Construction cost estimate by Engineer 2-

How this compares with Bengaluru Urban

0%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep ASSETZ KVN NIWA & NEO on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmASSETZ KVN NIWA & NEOOther 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 25 registered projects within 2 km.

Builder: Elite Projects

ELITE PROJECTS has 2 registrations on RERA Karnataka, including BREEZE and ASSETZ KVN NIWA & NEO. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if ASSETZ KVN NIWA & NEO is delayed beyond 30 Sep 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ASSETZ KVN NIWA & NEO?

The registered promoter entity is Elite Projects, a partnership firm as per the filing. Its GSTIN 29AALFE6056H1Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ASSETZ KVN NIWA & NEO?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ASSETZ KVN NIWA & NEO?

The professionals named in the filing: Architect: Lolita Almeida Thota; Engineer: H.G.Naikar; Chartered Accountant: Shyam Prasad Shetty. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ASSETZ KVN NIWA & NEO?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ASSETZ KVN NIWA & NEO. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ASSETZ KVN NIWA & NEO to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.