Home / Browse projects / Mumbai Suburban, Maharashtra / ASHOKA CO-OP HSG SOCIETY LIMITED

Registration lapsed No litigation declared Others project

ASHOKA CO-OP HSG SOCIETY LIMITED

By M/S DESIGN BUILDERS PVT LTD

RG-MH-26011 · RERA P51800008451 · Last updated on MahaRERA portal: 22 Jul 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date
  • Completion date moved by 84 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2026Possession promised7 months past this date
2 of 11Construction stages donefurthest along: Excavation, 95%
35 of 47Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 143 documents Report an error

ASHOKA CO-OP HSG SOCIETY LIMITED is a Others project by M/S DESIGN BUILDERS PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800008451 on 19 Aug 2017. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 84 months from the original filing. 12 of the 47 units on this registration are recorded sold or booked, and 2 of 11 construction stages are filed complete.

At a glance

Project

  • NameASHOKA CO-OP HSG SOCIETY LIMITED
  • TypeOthers
  • Location
    • 0
    • Borivali
    • Mumbai Suburban
    • 400068
  • Pincode400068
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800008451
  • ReraGenie IDRG-MH-26011

Builder

  • NameM/S DESIGN BUILDERS PVT LTD
  • Entity typeCompany
  • Managing DirectorSANJAY SURESH MANDAVKAR
  • Declared earlier projects1 →

Key dates

7 months past promisethis monthRegisteredAug 2017First promiseMar 2019Revised toMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on19 Aug 2017
  • Promised completion31 Mar 2026
  • Revised completionRevised to 31 Mar 2026 (originally 31 Mar 2019)
  • Buildings1 building record
  • Documents filed143 files

Current status

26%12 of 47 units booked
23.5%Work done, per cost certificate

Figures as on 22 Jul 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ashoka co-op hsg society limitedNA141040747

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 95%.

ashoka co-op hsg society limited: 41% average across the applicable activities

ActivityProgress
Excavation95%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor35%
Slabs of Super Structure35%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 22 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed24

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots24
Closed/Covered4
Open Space20

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area654 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on4 Sep 2025

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI2020.93
Proposed, not sanctioned804 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMAHAVIR NAGAR KANDIVALI WEST
Estimated costRs 12.44 cr
Cost incurredRs 2.93 cr
Work done23.54%
BuildingWingEstimatedIncurred
ashoka co-op hsg society limitedNARs 6.22 crRs 1.46 cr
-NARs 6.22 crRs 1.46 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAY CONSULTANTS
EngineerVIJAYKUMAR MAURYA
Chartered AccountantNEHALI & CO
PartnerRole in project
M/S DESIGN BUILDERS PVT LTD-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800001592Mar 2019 → Mar 2020

Reason as filed by the promoterDUE TO DELAY IN DCPR 2034 AND IMPLEMENTATION OF DCPR 2034 AND DP ROAD DEMARCATION ISSUE REPRESENTATION GIVEN TO MCGC, WE REQUEST YOU TO PLEASE FURTHER GRANT US EXTENSION FOR ONE YEAR

EXT51800006243Mar 2019 → Sep 2022

Reason as filed by the promoterDUE TO DELAY IN GETTING PERMISSION AS DP 2034 WAS NOT ISSUED AND MCGM HAD WIDENED THE ROAD IN OUR PROJECT AFTER COMPLETION OF THREE FLOORS. WE WOULD LIKE TO EXTEND THE PROJECT AND COMPLETE THE SAME. PLEASE GRANT US THE SAME AT THE EARLIEST.

EXT51800015107Mar 2019 → Mar 2025

Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 30/03/2025

EXT51800027895Mar 2019 → Mar 2026

Reason as filed by the promoterWe would like to request you that the Project ASHOKA CO-OP HSG SOCIETY LIMITED which is located at Tare Compound, Dahisar Check Naka, Dahisar East Mumbai 400 068. having its Registration No P51800008451 was mentioned to be completed on 30-03-2025 However, Due to delay in getting permission as MCGM has proposed to widen existing D.P Road from 13.8 mtr to 18.30 mtr in the D.P Remarks after completion of Three Floors. Further CC of the site is not issued by MCGM because of civil Aviation Authority of India They have restricted the height of the building from earlier MCGM approval of 32m to 18.5m.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Mar 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed143

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 143 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: form 3.pdf22 Jul 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf22 Jul 2025
Disclosure of sold/ booked inventoryFile: inventory.pdf22 Jul 2025
Certificates of CA (Form 3)File: form 3.pdf7 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf7 Apr 2025
Disclosure of sold/ booked inventoryFile: inventory.pdf7 Apr 2025
Certificates of CA (Form 3)File: CA form 3 dec 24 revised.pdf19 Mar 2025
Disclosure of sold/ booked inventoryFile: inventory disclosure final.pdf18 Mar 2025
Declaration in FORM BFile: FORM B-Rs 500 S.pdf17 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Design Builders Pvt Ltd - 2018-2019 (scan).pdf5 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Design Builders Pvt Ltd - 2019-2020 (scan).pdf5 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Design Builders Pvt Ltd - 2020-2021 (scan).pdf5 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Design Builders Pvt Ltd - 2021-2022 (scan).pdf5 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 DEsign Builders Pvt Ltd - 2022-2023 (scan).pdf5 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 DEsign Builders Pvt Ltd - 2023-2024 (scan).pdf5 Feb 2025
Certificates of CA (Form 3)File: form 3 1.pdf20 Jan 2025
Certificates of CA (Form 3)File: form 3.pdf15 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf15 Jan 2025
Certificates of CA (Form 3)File: SIGNED CA Certificate.pdf15 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Form 2.pdf15 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosre of Sold and Booked Inventory.pdf15 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf12 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf12 Jul 2024
Certificates of CA (Form 3)File: form 3.pdf12 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer form 2A.pdf2 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Form 1.pdf10 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER FORM 2.pdf10 Apr 2024
Disclosure of sold/ booked inventoryFile: INVENTORY.pdf10 Apr 2024
Certificates of CA (Form 3)File: CA FORM 3.pdf10 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 oct dec 23.pdf10 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 oct dec 23.pdf10 Jan 2024
Certificates of CA (Form 3)File: Form 3 oct dec 23.pdf10 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf11 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf11 Oct 2023
Disclosure of sold/ booked inventoryFile: disclosure inventory.pdf11 Oct 2023
Certificates of CA (Form 3)File: form 3.pdf11 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Form 1 -NEW (01-Apr-2023 to 30-June-2023).pdf11 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Form 2 -NEW ( 01-Apr-2023 to 30-June-2023).pdf11 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer form 2A-NEW till 30-06-2023).pdf11 Jul 2023
Certificates of CA (Form 3)File: FORM 3 01-04-23 to 30-06-23.pdf11 Jul 2023
Disclosure of sold/ booked inventoryFile: Disclosre of Sold and Booked Inventory-as on dated -31-03-2023(signed).pdf13 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf12 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf12 Apr 2023
Certificates of CA (Form 3)File: form 3.pdf12 Apr 2023
Declaration about Commencement CertificateFile: CC COVERING LETTER.pdf21 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A-31-03-2021.pdf21 Mar 2023
CERSAI detailsFile: CERSAI DECLARATION.pdf21 Mar 2023
Disclosure of sold/ booked inventoryFile: Disclosre Inventory.pdf21 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CFT 10 01 2023.pdf11 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: No Progress Letter Dated-.pdf7 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Form 2 -NEW.pdf7 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer form 2A-NEW.pdf7 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosre of Sold AND Booked Inventory.pdf7 Jan 2023
Certificates of CA (Form 3)File: CA CERTIFICATE.pdf7 Jan 2023
OtherFile: Cancellation letter with srk.pdf4 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Form 1.pdf12 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Form 2.pdf12 Oct 2022
Disclosure of sold/ booked inventoryFile: Disclosre of Sold and Booked Inventory.pdf12 Oct 2022
Certificates of CA (Form 3)File: CA Form 3.pdf12 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect form 1.pdf15 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf7 Jul 2022
Form 2AFile: FORM 2A.pdf7 Jul 2022
Disclosure of sold/ booked inventoryFile: DISCOSER OF INVENTORY.pdf7 Jul 2022
Certificates of CA (Form 3)File: FORM 3 (1).pdf7 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 (3).pdf5 Apr 2022
Certificates of CA (Form 3)File: FORM 3.pdf5 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER FORM 2.pdf7 Jan 2022
Certificates of CA (Form 3)File: CA FORM 3.pdf7 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: No Progress Letter.pdf5 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Cirtificate form 2.pdf5 Oct 2021
Form 2AFile: FORM 2A- Site Supervisor Certificate.pdf5 Oct 2021
Certificates of CA (Form 3)File: SIGNED CA CERTIFICATE form 3.pdf5 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: No Progress Letter Dated.pdf3 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: no progess letter.pdf3 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Cirtificate form 2.pdf3 Aug 2021
Form 2AFile: FORM 2A.pdf3 Aug 2021
Disclosure of sold/ booked inventoryFile: dislosure invntory.pdf3 Aug 2021
Certificates of CA (Form 3)File: ca form 3.pdf3 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Cirtificate FORM 2.pdf15 May 2021
Form 2AFile: FORM 2A Site Supervisor Certificate.pdf15 May 2021

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
CRYSTAL ROSE CHS1 CRYSTAL ROSE DUTTA MANDIR ROAD MAHAVIR NAGAR KANDIVALI WEST21CompletedJun 2016Late, Jul 2016

How this compares with Mumbai Suburban

26%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 84 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ASHOKA CO-OP HSG SOCIETY LIMITED on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Borivali6,700+ in Mumbai Suburban

2 kmASHOKA CO-OP HSG SOCIETYCompleted 119Lapsed / revoked 66Other 169Dot size: filed unitsN

Filed coordinates, straight-line distance. 354 registered projects within 2 km.

Builder: M/S DESIGN BUILDERS PVT LTD

M/S DESIGN BUILDERS PVT LTD has 1 registration on MahaRERA, including ASHOKA CO-OP HSG SOCIETY LIMITED. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that ASHOKA CO-OP HSG SOCIETY LIMITED shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ASHOKA CO-OP HSG SOCIETY LIMITED is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ASHOKA CO-OP HSG SOCIETY LIMITED?

The registered promoter entity is M/S DESIGN BUILDERS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ASHOKA CO-OP HSG SOCIETY LIMITED?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ASHOKA CO-OP HSG SOCIETY LIMITED?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ASHOKA CO-OP HSG SOCIETY LIMITED?

The professionals named in the filing: Architect: RAY CONSULTANTS; Engineer: VIJAYKUMAR MAURYA; Chartered Accountant: NEHALI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ASHOKA CO-OP HSG SOCIETY LIMITED?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ASHOKA CO-OP HSG SOCIETY LIMITED. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ASHOKA CO-OP HSG SOCIETY LIMITED to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.