Ashanand residency Building D and E
RG-MH-16541 · RERA P52100026295 · Last updated on MahaRERA portal: 10 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 28 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 2 earlier projects delivered on promise
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Ashanand residency Building D and E is a Residential / Group Housing project by Anand Deoram Tambe in Pune, Maharashtra, registered with MahaRERA as P52100026295 on 7 Sep 2020. Possession is promised by 30 Oct 2028. The completion date has moved by 28 months from the original filing. 48 of the 126 units on this registration are recorded sold or booked, and 14 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameAshanand residency Building D and E
- TypeResidential / Group Housing
- Location
- Survey No 276/1/A
- Rakshewadi
- Rajgurunagar
- Khed
- Rajgurunagar (CT)
- Pune
- 410505
- Pincode410505
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100026295
- ReraGenie IDRG-MH-16541
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on7 Sep 2020
- Promised completion30 Oct 2028
- Revised completionRevised to 30 Oct 2028 (originally 30 Jun 2026)
- Buildings2 building records
- Documents filed161 files
Current status
Figures as on 10 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Ashanand Residency Building D | NA | 8 | 8 | 49 | 0 | 49 |
| Ashanand Residency Building E | NA | 11 | 11 | 77 | 0 | 77 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 10 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 75%.
Ashanand Residency Building D82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Ashanand Residency Building E68%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 40% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 10 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 70% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 92% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 75% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 70% |
| Aggregate area of recreational Open Space | Yes | 70% |
| Open Parking | No | Not applicable |
Parking filed202
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Ashanand Residency Building D | 77 | 77 | 154 |
| Ashanand Residency Building E | 48 | 0 | 48 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Ashanand Residency Building E | NA | Rs 7.97 cr | Rs 2.22 cr |
| Ashanand Residency Building D | NA | Rs 7.43 cr | Rs 7.43 cr |
| - | NA | Rs 29.09 lakh | Rs 23.31 lakh |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mr. Deepak Honkan |
| Engineer | Mr.Anil Kisanrao Gavhane |
| Engineer | Pratik Sanjaysing Pardeshi |
| Engineer | PRATHAMESH BABAN MANJARE |
| Chartered Accountant | Narayan Sarda |
| Chartered Accountant | Jatin Sethi & Co |
| Partner | Role in project |
|---|---|
| Anand Deoram Tambe | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe completion of the project has been delayed due to unforeseen circumstances beyond the promoter’s control, including delays in approvals, shortage of manpower, and disruption in material supply, which affected the project progress despite best efforts. The promoter remains committed to completing the project with maintained quality standards and therefore requests an extension of the project registration up to 30/06/2027 to complete the remaining work and statutory compliances under the Real Estate (Regulation and Development) Act, 2016.
Reason as filed by the promoterNA
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12500415 | Shafi Sayyed | Anand Deoram Tambe | 08/02/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Aug 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Jun 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 Aug 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 16 Dec 2023
Documents filed161
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 161 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Ashanand - Q1 - Form 1.pdf | 10 Sep 2026 |
| Withdrawal Update Form 2File: Ashanand - Q1 - Form 2.pdf | 10 Sep 2026 |
| Withdrawal Update Form 3File: Ashanand - Q1 - Form 3.pdf | 10 Sep 2026 |
| Form 2A (FY 2025-2026)File: Form 2A March 2025.pdf | 9 Jun 2026 |
| Form 5 (FY 2025-2026)File: Form 5 March 2025.pdf | 9 Jun 2026 |
| Withdrawal Update Form 1File: ASHANAND - Q4 - FORM 1.pdf | 29 May 2026 |
| Withdrawal Update Form 1File: ASHANAND - Q4 - FORM 1.pdf | 29 May 2026 |
| Withdrawal Update Form 1File: ASHANAND - Q4 - FORM 1.pdf | 29 May 2026 |
| Withdrawal Update Form 1File: ASHANAND - Q4 - FORM 1.pdf | 29 May 2026 |
| Withdrawal Update Form 1File: ASHANAND - Q4 - FORM 1.pdf | 29 May 2026 |
| Withdrawal Update Form 1File: ASHANAND - Q4 - FORM 1.pdf | 29 May 2026 |
| Withdrawal Update Form 2File: ASHANAND - Q4 - FORM 2.pdf | 29 May 2026 |
| Withdrawal Update Form 2File: ASHANAND - Q4 - FORM 2.pdf | 29 May 2026 |
| Withdrawal Update Form 2File: ASHANAND - Q4 - FORM 2.pdf | 29 May 2026 |
| Withdrawal Update Form 2File: ASHANAND - Q4 - FORM 2.pdf | 29 May 2026 |
| Withdrawal Update Form 2File: ASHANAND - Q4 - FORM 2.pdf | 29 May 2026 |
| Withdrawal Update Form 2File: ASHANAND - Q4 - FORM 2.pdf | 29 May 2026 |
| Withdrawal Update Form 3File: ASHANAND - Q4 - FORM 3.pdf | 29 May 2026 |
| Withdrawal Update Form 3File: ASHANAND - Q4 - FORM 3.pdf | 29 May 2026 |
| Withdrawal Update Form 3File: ASHANAND - Q4 - FORM 3.pdf | 29 May 2026 |
| Withdrawal Update Form 3File: ASHANAND - Q4 - FORM 3.pdf | 29 May 2026 |
| Withdrawal Update Form 3File: ASHANAND - Q4 - FORM 3.pdf | 29 May 2026 |
| Withdrawal Update Form 3File: ASHANAND - Q4 - FORM 3.pdf | 29 May 2026 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate of Completion of Work (Form 1).pdf | 22 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Certificates of CA (Form 3).pdf | 22 Jul 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate Form 2.pdf | 22 Jul 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer's Quality Certificate-Form 2A.pdf | 22 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Certificates of CA (Form 3).pdf | 18 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate of Completion of Work (Form 1).pdf | 5 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Certificates of CA (Form 3).pdf | 5 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate Form 2.pdf | 5 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer's Quality Certificate-Form 2A.pdf | 5 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate of Completion of Work (Form 1).pdf | 9 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate -Form 2.pdf | 9 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer's Quality Certificate-Form 2A.pdf | 9 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer's Quality Certificate-Form 2A.pdf | 9 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate of Completion of Work (Form 1).pdf | 9 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate -Form 2.pdf | 9 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Annual Audit Report of Statutory CA (Form 5) (FY 2023-24).pdf | 9 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate of Completion of Work (Form 1).pdf | 9 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate -Form 2.pdf | 9 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer's Quality Certificate-Form 2A.pdf | 9 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Annual Audit Report of Statutory CA (Form 5) (FY 2023-24).pdf | 9 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Certificates of CA (Form 3).pdf | 26 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate of Completion of Work (Form 1).pdf | 11 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate -Form 2.pdf | 11 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer's Quality Certificate-Form 2A.pdf | 11 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory.pdf | 4 May 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory.pdf | 4 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Certificates of CA (Form 3).pdf | 30 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Certificates of CA (Form 3).pdf | 30 Apr 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Formation of Legal Entity -SocietyCo Op.pdf | 26 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate.pdf | 20 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate of Completion of Work (Form 1).pdf | 20 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate -Form 2.pdf | 20 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate -Form 2.pdf | 20 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer's Quality Certificate-Form 2A.pdf | 20 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer's Quality Certificate-Form 2A.pdf | 20 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate of Completion of Work (Form 1) (2).pdf | 16 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate of Completion of Work (Form 1).pdf | 16 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate -Form 2.pdf | 16 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate -Form 2.pdf | 16 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer's Quality Certificate-Form 2A.pdf | 16 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer's Quality Certificate-Form 2A.pdf | 16 Dec 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PART OCCUPANCY CERTIFICATE-1.pdf | 16 Dec 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PART OCCUPANCY CERTIFICATE-2.pdf | 16 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Certificates of CA (Form 3).pdf | 8 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Certificates of CA (Form 3).pdf | 19 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Certificates of CA (Form 3).pdf | 19 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Certificates of CA (Form 3).pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annual Audit Report of Statutory CA (Form 5) (FY 2022-23).pdf | 19 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate of Completion of Work (Form 1).pdf | 17 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate of Completion of Work (Form 1).pdf | 17 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate -Form 2.pdf | 17 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate -Form 2.pdf | 17 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer's Quality Certificate-Form 2A.pdf | 17 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer's Quality Certificate-Form 2A.pdf | 17 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer's Quality Certificate-Form 2A.pdf | 16 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate of Completion of Work (Form 1).pdf | 15 Jul 2023 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Ashanand Residency - Building B | Survey No 276 1 A Rajgurunagar Khed Pune 410505 | 56 | Completed | May 2017 | May 2017 |
| Ashananda Residency - Building A | S No 276 1 A At Rajgurunagar Tal Khed Dist Pune | 56 | Completed | Apr 2017 | Apr 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 161 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Ashanand residency Building D and E on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Khed13,700+ in Pune
Filed coordinates, straight-line distance. 268 registered projects within 2 km.
First City
Xrbia Developers Ltd
SURAJ EKYUM
SURAJ INFRA
Shankeshwar World
Nitin Chhaganlal Jain
Escape City Ph 1
Gajendra Patil , Pramod Patil , Vinod Pati
YESAI PARK
SIDDHIVINAYAK DEVELOPERS
Escape City Ph 2
Gajendra Patil , Pramod Patil , Vinod Pati
Builder: Anand Deoram Tambe
Anand Deoram Tambe has 4 registrations on MahaRERA, including Ashanand Residency C building and Ashanand Residency F Buidling. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Ashanand residency Building D and E is delayed beyond 30 Oct 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Ashanand residency Building D and E?
The registered promoter entity is Anand Deoram Tambe, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Ashanand residency Building D and E?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Ashanand residency Building D and E?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Ashanand residency Building D and E?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Ashanand residency Building D and E?
The professionals named in the filing: Architect: Mr. Deepak Honkan; Engineer: Mr.Anil Kisanrao Gavhane; Engineer: Pratik Sanjaysing Pardeshi; Engineer: PRATHAMESH BABAN MANJARE; Chartered Accountant: Narayan Sarda; Chartered Accountant: Jatin Sethi & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Ashanand residency Building D and E?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.