Home / Browse projects / Nagpur, Maharashtra / ARUN DEONAGARI II

Registered No litigation declared Plotted project

ARUN DEONAGARI II

By HUSUKALE JAIN & OTHERS

RG-MH-14795 · RERA P50500048739 · Last updated on MahaRERA portal: 1 May 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 36 months from the original
15 of 33Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 69 documents Report an error

ARUN DEONAGARI II is a Plotted project by HUSUKALE JAIN & OTHERS in Nagpur, Maharashtra, registered with MahaRERA as P50500048739 on 17 Jan 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 36 months from the original filing. 18 of the 33 units on this registration are recorded sold or booked.

At a glance

Project

  • NameARUN DEONAGARI II
  • TypePlotted
  • Location
    • KH NO 558
    • OCCUPANCY CLASS-1 RIGHTS OF MOUZA UMRED P.S.K.-46 KHATE NO 133
    • MOUZA UMRED
    • Umred (M Cl)
    • Umred
    • Nagpur
    • 441203
  • Pincode441203
  • RERA no.P50500048739
  • ReraGenie IDRG-MH-14795

Builder

  • NameHUSUKALE JAIN & OTHERS
  • Entity typeOthers
  • Named personsVIVEK BABANRAO HUSUKALE, PRAVIN RATANLALJI JAIN, PRAJAKTA PAWAN KALBANDE, TEJASWINI SHRIKANT KAWALE, UTKARSHA RAJESH ITANKAR
  • Other registrations2 more →

Key dates

this monthRegisteredJan 2023First promiseDec 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Jan 2023
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2023)
  • BuildingsNot stated in filing
  • Documents filed69 files

Current status

55%18 of 33 units booked

Figures as on 1 May 2025, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 1 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes90%
Street LightingYes90%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,233 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
PRATIBHA PRAKASH DESHMUKHNagpur (M Corp.)Nagpur
TEJASWINI SHRIKANT KAWALENagpur (M Corp.)Nagpur
UTKARSHA RAJESH ITANKARNagpur (M Corp.)Nagpur
PRAJAKTA PAWAN KALBANDENagpur (M Corp.)Nagpur

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPRATAP NAGAR NAGPUR

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
HUSUKALE JAIN & OTHERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50500018484Dec 2023 → Dec 2024

Reason as filed by the promoterDue to Covid-19 our work got delayed and labor and material price hike.

EXT50500026034Dec 2023 → Dec 2026

Reason as filed by the promoterDue to unforeseen circumstances beyond our control, like few departmental clearances for the execution of project, administrative procedures, Labour issues like labour shortage and Migration of labour due to govt. policy.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Jul 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Jul 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed69

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engn Certf Deonagari II.pdf1 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE Arun Deonagari 2 Mar 25.pdf25 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certf Deonagari II March Qtr.pdf21 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DEONAGRI 2.pdf15 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engn Certf Deonagari II.pdf15 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Booked Deonagri 2 Inventory Disclosure.pdf13 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certf Deonagari II organized.pdf19 Feb 2025
Disclosure of sold/ booked inventoryFile: New Sold Booked Deonagri-2 Inventory Disclosure - DEC-2024.pdf19 Feb 2025
Declaration in FORM BFile: FORM B-Deonagari II_organized.pdf1 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE Arun Deonagari 2 sept 24.pdf3 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 CA Certf 2023-24 Deonagari II.pdf20 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 CA Certf 2023-24 Deonagari II.pdf20 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGI DEONAGARI 2.pdf21 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certf sept2024 Deonagari II.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: sold book deo 2.pdf19 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A DEONAGARI 2 22-23.pdf14 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A DEONAGARI 2 23-24.pdf14 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE Arun Deonagari 2 June 24.pdf19 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Deonagari 2 engi june 24.pdf18 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certf June2024 new.pdf12 Aug 2024
Disclosure of sold/ booked inventoryFile: DEONAGRI -2 SOLD BOOKED INVENTORY.pdf6 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ARUN DEONAGRI 2rotated.pdf5 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engn Certf March 2024 II rotated.pdf29 May 2024
Disclosure of sold/ booked inventoryFile: Deonagari II sold booked inventory (MAR 24)_rotated.pdf20 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certf Deonagri II.pdf19 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form 2 Deonagari 2 - Dec 23.pdf17 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Form 3 Deo Nagari 2 - Dec 23.pdf17 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: deonagari 2 jan to mar.pdf29 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 deonagari 2 .pdf20 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold booked inventoryDeonagari-2.pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf29 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23).pdf29 Dec 2023
Declaration in FORM BFile: Deonagari 2 FormB.pdf25 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: ARUN DEO NAGARI 2.pdf18 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: deonagari 2 final sep 23 ca cert.pdf25 Nov 2023
Declaration about Commencement CertificateFile: From D July Sept 2023.pdf23 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engg cert 1.pdf23 Nov 2023
Disclosure of sold/ booked inventoryFile: Sold Booked Inventory July-Sept 2023.pdf23 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 arun deonagari 2 sept.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: deonagari 2 jun 23.pdf13 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC AD2 MARCH 2023.pdf13 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: deonagri 2 mar 23.pdf12 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Deonagri 2 jun 23.pdf12 Oct 2023
Declaration about Commencement CertificateFile: 4 Form D - March 2023.pdf26 Sep 2023
Declaration about Commencement CertificateFile: 4 From D - June 2023.pdf26 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 Arun Deo Nagari 2 - March 23.pdf22 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 Arun Deo Nagari 2 - june 23.pdf22 Sep 2023
Disclosure of sold/ booked inventoryFile: 5 Sold Booked Inventory - Deonagari 2 March 2023.pdf22 Sep 2023
Disclosure of sold/ booked inventoryFile: 5 Sold Booked Inventory - Deonagari 2 June 2023.pdf22 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE ARUN DEONAGARI II.pdf5 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A DECLRTN ABOUT INTEREST IN OTHER REAL ESTATE PROJECTS.pdf5 Jan 2023
CERSAI detailsFile: KH NO 558 CERSAI.pdf7 Sep 2022
Proforma of Allotment letterFile: AGREEMENT TO SALE-KH-558.pdf25 Aug 2022
Proforma of Agreement for saleFile: deonagari 2 agreement to sale.pdf25 Aug 2022
Deviation Report with respect to Allotment letterFile: Declaration_Allotment_Letter.pdf24 Aug 2022
Deviation Report with respect to model copy of AgreementFile: deonagari 2 declr abt dev in agreement to sale.pdf24 Aug 2022
Copy of the legal title reportFile: TITLE REPORT 558.pdf16 Aug 2022
Details of encumbrances concerned to FinanceFile: Encumbrance.pdf16 Aug 2022
Details of encumbrances concerned to LegalFile: Encumbrance.pdf16 Aug 2022
Declaration about Commencement CertificateFile: Form D.pdf16 Aug 2022
Declaration in FORM BFile: Form B_compressed_558.pdf16 Aug 2022
Proforma of Allotment letterFile: Allotment Letter_compressed_558.pdf16 Aug 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Ac_Declaration.pdf16 Aug 2022
Layout approvalFile: SANCTION MAP 558.pdf14 Jul 2022
Building plan approval or NA orderFile: SANCTION MAP 558.pdf14 Jul 2022
Copy of Layout Approval (in case of layout)File: SANCTION MAP 558.pdf14 Jul 2022
Building Plan Approval / NA Order for plotted developmentFile: SANCTION MAP 558.pdf14 Jul 2022
PAN CardFile: 1 PAN Card.pdf13 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: NMRDA Letter-558.pdf13 Jul 2022

How this compares with Nagpur

55%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one moved by 36 months
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ARUN DEONAGARI II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MOUZA UMRED2,800+ in Nagpur

Builder: HUSUKALE JAIN & OTHERS

HUSUKALE JAIN & OTHERS has 3 registrations on MahaRERA, including ARUN DEONAGARI I and ARUN DEONAGARI II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if ARUN DEONAGARI II is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ARUN DEONAGARI II?

The registered promoter entity is HUSUKALE JAIN & OTHERS, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ARUN DEONAGARI II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ARUN DEONAGARI II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in ARUN DEONAGARI II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ARUN DEONAGARI II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ARUN DEONAGARI II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.