Home / Browse projects / Nagpur, Maharashtra / ARMORS ESTATE
ARMORS ESTATE
By ARMORS DEVELOPERS PRIVATE LIMITED
RG-MH-38815 · RERA P50500051030 · Last updated on MahaRERA portal: 12 Aug 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 7 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ARMORS ESTATE is a Plotted project by ARMORS DEVELOPERS PRIVATE LIMITED in Nagpur, Maharashtra, registered with MahaRERA as P50500051030 on 22 May 2023. Possession was promised by 31 Mar 2026 and is now 7 months past that date. 0 of the 119 units on this registration are recorded sold or booked.
At a glance
Project
- NameARMORS ESTATE
- TypePlotted
- Location
- Kh. No. 136-A & 136-B
- MOUZA RANALA
- TAHSIL KAMPTEE
- NAGPUR
- Ranala
- Kamptee
- 441002
- Pincode441002
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50500051030
- ReraGenie IDRG-MH-38815
Builder
- NameARMORS DEVELOPERS PRIVATE LIMITED
- Entity typeCompany
- DirectorSHARDA ANAND KHOBRAGADE
- Managing DirectorANAND NARAYANRAO KHOBRAGADE
- Other registrations1 more →
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on22 May 2023
- Promised completion31 Mar 2026
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed88 files
Current status
Figures as on 12 Aug 2025, this project's latest MahaRERA filing.
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 12 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
NA Plot Without Structure:
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 12 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mr.Kiran Digamber Purohit |
| Engineer | Pankaj Ashokrao Landge |
| Chartered Accountant | CA SANDEEP VIRANI |
| Partner | Role in project |
|---|---|
| ARMORS DEVELOPERS PRIVATE LIMITED | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 13 May 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Apr 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 Apr 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed88
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: FORM 1-Q1.pdf | 12 Aug 2025 |
| Form 2File: FORM-2 ENGINEER CERTIFICATE-Q1-ARMORS ESTATES.pdf | 12 Aug 2025 |
| Form 3File: FORM 3-RERA ARMORS DEVELOPERS-Q1.pdf | 12 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: FORM 3-RERA ARMORS DEVELOPERS-Q1.pdf | 12 Aug 2025 |
| Form 3File: FORM 3-RERA ARMORS DEVELOPERS-Q2.pdf | 12 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: FORM 3-RERA ARMORS DEVELOPERS-Q2.pdf | 12 Aug 2025 |
| Form 2File: FORM-2 ENGINEER CERTIFICATE-Q2-ARMORS ESTATE.pdf | 12 Aug 2025 |
| Form 1File: FORM1-Q2.pdf | 12 Aug 2025 |
| Form 1File: FORM1-Q3.pdf | 12 Aug 2025 |
| Form 2File: FORM-2 ENGINEER CERTIFICATE-Q3-ARMORS ESATE.pdf | 12 Aug 2025 |
| Form 3File: FORM 3-RERA ARMORS DEVELOPERS-Q3.pdf | 12 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: FORM 3-RERA ARMORS DEVELOPERS-Q3.pdf | 12 Aug 2025 |
| Form 3File: FORM 3-RERA ARMORS DEVELOPERS-Q4.pdf | 12 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: FORM 3-RERA ARMORS DEVELOPERS-Q4.pdf | 12 Aug 2025 |
| Form 2File: FORM-2 ENGINEER CERTIFICATE-Q4-ARMORS ESATE.pdf | 12 Aug 2025 |
| Form 1File: FORM1-Q4.pdf | 12 Aug 2025 |
| Form 1File: FORM-1 ARCHITECT'S CERTIFICATE-Q1-Armors Estate.pdf | 12 Aug 2025 |
| Form 2File: FORM-2 ENGINEER CERTIFICATE-Q1-24-25.pdf | 12 Aug 2025 |
| Form 3File: FORM 3-RERA ARMORS DEVELOPERS-Q1.pdf | 12 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: FORM 3-RERA ARMORS DEVELOPERS-Q1.pdf | 12 Aug 2025 |
| Form 1File: Armors Estate-Form-1.pdf | 12 Aug 2025 |
| Form 2File: Armors Estate-Form-2.pdf | 12 Aug 2025 |
| Form 3File: Armors Estate-Form-3_.pdf | 12 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Armors Estate-Form-3.pdf | 12 Aug 2025 |
| Form 1File: Form 1.pdf | 12 Aug 2025 |
| Form 2File: Form 2.pdf | 12 Aug 2025 |
| Form 3File: Form 3.pdf | 12 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Form 3.pdf | 12 Aug 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Armors Estate-Form-1.pdf | 11 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 11 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Armors Estate-Form-3_.pdf | 11 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 11 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Armors Estate-Form-2.pdf | 11 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 11 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 ARCHITECT'S CERTIFICATE-Q1-Armors Estate.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 ENGINEER CERTIFICATE-Q1-24-25.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-RERA ARMORS DEVELOPERS-Q1.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-RERA ARMORS DEVELOPERS-Q4.pdf | 23 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-Q1.pdf | 14 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1-Q2.pdf | 14 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1-Q3.pdf | 14 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1-Q4.pdf | 14 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 ENGINEER CERTIFICATE-Q1-ARMORS ESTATES.pdf | 14 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 ENGINEER CERTIFICATE-Q2-ARMORS ESTATE.pdf | 14 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 ENGINEER CERTIFICATE-Q3-ARMORS ESATE.pdf | 14 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 ENGINEER CERTIFICATE-Q4-ARMORS ESATE.pdf | 14 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-RERA ARMORS DEVELOPERS-Q1.pdf | 14 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-RERA ARMORS DEVELOPERS-Q2.pdf | 14 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-RERA ARMORS DEVELOPERS-Q3.pdf | 14 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form-1 ARCHITECT'S CERTIFICATE-Q1-Armors Estate.pdf | 15 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form-1 ARCHITECT'S CERTIFICATE-Q2-Armors Estate.pdf | 15 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form-1 ARCHITECT'S CERTIFICATE-Q3-Armors Estate.pdf | 15 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 ENGINEER CERTIFICATE-Q1-ARMORS ESTATES.pdf | 15 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 ENGINEER CERTIFICATE-Q2-ARMORS ESTATE.pdf | 15 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 ENGINEER CERTIFICATE-Q3-ARMORS ESATE.pdf | 15 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-RERA ARMORS DEVELOPERS-Q1.pdf | 8 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-RERA ARMORS DEVELOPERS-Q2.pdf | 8 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-RERA ARMORS DEVELOPERS-Q3.pdf | 8 Feb 2024 |
| Copy of the legal title reportFile: Title Verification Report.pdf | 13 May 2023 |
| Copy of the legal title reportFile: Format A.pdf | 13 May 2023 |
| Copy of the legal title reportFile: Annexure to Format A.pdf | 13 May 2023 |
| Other - LegalFile: ANNEXURE A SHARDHA KHOBRAGADE.pdf | 13 May 2023 |
| Proforma of Agreement for saleFile: Model Form of Agreement for Sale.pdf | 5 May 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A SHARDHA KHOBRAGADE.pdf | 4 May 2023 |
| Other - FinanceFile: Reply to Queries.pdf | 4 May 2023 |
| Building plan approval or NA orderFile: NMRDA.pdf | 21 Apr 2023 |
| Layout approvalFile: Sanction Map.pdf | 21 Apr 2023 |
| Layout approvalFile: Crop of Authority Signature for Better Understanding.pdf | 21 Apr 2023 |
| Copy of Layout Approval (in case of layout)File: Sanction Map.pdf | 21 Apr 2023 |
| Copy of Layout Approval (in case of layout)File: Crop of Authority Signature for Better Understanding.pdf | 21 Apr 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: NMRDA.pdf | 21 Apr 2023 |
| CERSAI detailsFile: Undertaking for no security interest 2.pdf | 12 Apr 2023 |
| PAN CardFile: PAN CARD Application to Income Tax.pdf | 10 Apr 2023 |
| Declaration about Commencement CertificateFile: Decleration of Commencement Certificate-Format D.pdf | 10 Apr 2023 |
| Declaration in FORM BFile: FORM B.pdf | 10 Apr 2023 |
| CERSAI detailsFile: CERSAI_Search_Report.pdf | 10 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 10 Apr 2023 |
| Deviation Report with respect to Allotment letterFile: No Deviation-Allotment Letter.pdf | 10 Apr 2023 |
| Deviation Report with respect to model copy of AgreementFile: No Deviation-AFS.pdf | 10 Apr 2023 |
| Building plan approval or NA orderFile: NA ORDER-ORIGINAL SIGN_.pdf | 8 Apr 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 88 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep ARMORS ESTATE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NAGPUR2,800+ in Nagpur
Filed coordinates, straight-line distance. 28 registered projects within 2 km.
KESAR GATEWAY
KESAR GATEWAY PVT LTD
ORANGE CITY HEIGHTS
SANJAY GANPATRAO PATIL
HBA PARK
HBA CONSTRUCTION COMPANY PVT.LTD
JAY AMBE NAGAR
RAMESHWAR SUGHANCHAND BAWANKAR
Green Town
M/s Green Town Developers
SHANKARRAO JIBHKATE NAGAR PHASE 1
VED INFRAA
See every Nagpur project, with the district possession charts
Builder: ARMORS DEVELOPERS PRIVATE LIMITED
ARMORS DEVELOPERS PRIVATE LIMITED has 2 registrations on MahaRERA, including ARMORS NAGAR and ARMORS ESTATE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What does it mean that ARMORS ESTATE shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if ARMORS ESTATE is delayed beyond 31 Mar 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ARMORS ESTATE?
The registered promoter entity is ARMORS DEVELOPERS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ARMORS ESTATE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for ARMORS ESTATE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ARMORS ESTATE?
The professionals named in the filing: Architect: Mr.Kiran Digamber Purohit; Engineer: Pankaj Ashokrao Landge; Chartered Accountant: CA SANDEEP VIRANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ARMORS ESTATE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.