Home / Browse projects / Gandhinagar, Gujarat / ARJUN 226
ARJUN 226
By SHYAM INFRA
RG-GJ-69594 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MAA04974/A1M/EX2/041024/311223 · Last updated on GujRERA portal: 19 Apr 2025
Source: official GujRERA filing
Red flags
- Completion date moved by 21 months
- 2 extensions taken
Clear
- Nothing verified clear yet
Saved.
ARJUN 226 is a Mixed Development project by SHYAM INFRA in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MAA04974/A1M/EX2/041024/311223 on 5 Mar 2019. Possession is promised by 30 Sep 2024. The completion date has moved by 21 months from the original filing. 225 of the 226 units on this registration are recorded sold or booked, and 36 of 36 construction stages are filed complete.
At a glance
Project
- NameARJUN 226
- TypeMixed Development
- Location
- Arjun 226
- Opp. Diya Green Party Plot
- Vavol Uvarsad Road
- Vavol
- VAVOL
- Gandhinagar
- 382016
- Pincode382016
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MAA04974/A1M/EX2/041024/311223
- ReraGenie IDRG-GJ-69594
Builder
- NameSHYAM INFRA
- Entity typePARTNERSHIP FIRM
- Other registrations1 more →
- Past their filed date1
Key dates
Key facts
Registration and timeline
- StatusValid until 30 Sep 2024
- Registered on5 Mar 2019
- Promised completion30 Sep 2024
- Revised completionRevised to 30 Sep 2024 (originally 30 Dec 2022)
- Buildings4 building records
- Documents filed53 files
Current status
Figures as on 19 Apr 2025, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A+B | - | - | - | 48 | 15 | 63 |
| E+F | - | - | - | 48 | 0 | 48 |
| C+D | - | - | - | 48 | 13 | 61 |
| G+H | - | - | - | 48 | 6 | 54 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building4
As on 19 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
36 of 36 construction stages are filed complete across 4 buildings.
A+B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
E+F100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
C+D100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
G+H100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Progress on shared amenities19
As on 19 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 100% |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 100% |
| Storm water drains | Yes | 100% |
| Landscaping and tree planting | Yes | 100% |
| Street lighting | Yes | 100% |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation, rain water harvesting | Yes | 100% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Fire fighting | Yes | 100% |
| Drinking water facilities | No | Not applicable |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | Yes | 100% |
| Security | Yes | 100% |
| Letter box | Yes | 100% |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A+B | NA | Rs 10.54 cr | Rs 10.54 cr |
| C+D | NA | Rs 6.75 cr | Rs 6.75 cr |
| G+H | NA | Rs 4.91 cr | Rs 4.91 cr |
| E+F | NA | Rs 4.80 cr | Rs 4.80 cr |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Documents filed53
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MAA04974/A1M/EX2/041024/311223 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Accountant's certificate (Form 3) | 19 Apr 2025 |
| Architect's certificate (Form 1) | 16 Apr 2025 |
| Site photograph, A+B | 14 Apr 2025 |
| Site photograph, A+B | 14 Apr 2025 |
| Site photograph, E+F | 14 Apr 2025 |
| Site photograph, E+F | 14 Apr 2025 |
| Site photograph, C+D | 14 Apr 2025 |
| Site photograph, C+D | 14 Apr 2025 |
| Site photograph, G+H | 14 Apr 2025 |
| Site photograph, G+H | 14 Apr 2025 |
| Engineer's certificate (Form 2) | 12 Sep 2024 |
| Engineer's certificate annexure | 12 Sep 2024 |
| RERA registration certificate | 5 Mar 2019 |
| Extension certificate | - |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Drainage affidavit | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Approved building or plotting plan | - |
| NOCs from authorities | - |
| Title clearance certificate | - |
| Title report | - |
| Property card | - |
| Project photograph | - |
| Proforma sale deed | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Gandhinagar
Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.
Keep ARJUN 226 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near VAVOL1,600+ in Gandhinagar
Filed coordinates, straight-line distance. 122 registered projects within 2 km.
Swagat Twincity Highstreet & Swagat Kingsland
SWAGAT DEVELOPERS
EWS - 2
GANDHINAGAR URBAN DEVELOPMENT AUTHORITY
SAMVED GREENVALLEY
SNEHARPAN BUILDCON LLP
Swagat Queen's Land Phase - 1
SWAGAT INFRASTRUCTURE P L TD
PRAMUKH PARISAR
PRAMUKH KRUPA CORPORATION
NEELKANTH HEIGHTS
NEEVA DEVELOPERS
See every Gandhinagar project, with the district possession charts
Builder: SHYAM INFRA
SHYAM INFRA has 2 registrations on GujRERA, including ARJUN 226 and SHYAM ELEGANCE. Read the full track record. See more projects on the Gandhinagar district page.
Frequently asked questions
What are my rights if ARJUN 226 is delayed beyond 30 Sep 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of ARJUN 226?
The registered promoter entity is SHYAM INFRA, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in ARJUN 226?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in ARJUN 226?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.
Report an error Share feedback