ARIHANT ALOKI PHASE V
By ARIHANT AASHIYANA PRIVATE LIMITED
RG-MH-28067 · RERA P52000025052 · Last updated on MahaRERA portal: 16 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 2 cases
- 1 complaint at MahaRERA
- Completion date moved by 60 months
- 1 extension taken
Clear
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ARIHANT ALOKI PHASE V is a Residential / Group Housing project by ARIHANT AASHIYANA PRIVATE LIMITED in Raigarh, Maharashtra, registered with MahaRERA as P52000025052 on 18 Mar 2020. Possession is promised by 31 Dec 2031. The completion date has moved by 60 months from the original filing. 0 of the 142 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameARIHANT ALOKI PHASE V
- TypeResidential / Group Housing
- Location
- Bhisegaon
- karjat
- Raigarh
- 410201
- Pincode410201
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000025052
- ReraGenie IDRG-MH-28067
Builder
- NameARIHANT AASHIYANA PRIVATE LIMITED
- Entity typeCompany
- DirectorsASHOKKUMAR BHANWARLAL CHHAJER, PARTH ASHOKKUMAR CHHAJER
- Other registrations11 more →
- Completed7 of 12
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on18 Mar 2020
- Promised completion31 Dec 2031
- Revised completionRevised to 31 Dec 2031 (originally 30 Dec 2026)
- Buildings1 building record
- Documents filed127 files
Current status
Figures as on 16 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| C1 | NA | 17 | 17 | 142 | 0 | 142 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 16 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.
C1: 0% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 16 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| USHASHRIKRISHNA DHARAP | Mumbai City | Mumbai City |
| RAMCHANDRABARSHA GHARAT | Navi Mumbai (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| C1 | NA | Rs 19.78 cr | - |
| - | NA | Rs 99.76 lakh | - |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | YOGITA BHANDARKAR |
| Engineer | SATISH MHATRE |
| Engineer | KALEEM SAYYAD |
| Engineer | ER. Kaleem Sayyad |
| Chartered Accountant | Ummed Jain & Co. |
| Chartered Accountant | ANJANI KUMAR GOYAL |
| Chartered Accountant | Kailash Chand Jain & Co |
| Chartered Accountant | Anjani Goyal & Co. |
| Partner | Role in project |
|---|---|
| ARIHANT AASHIYANA PRIVATE LIMITED | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.
Litigation declared2
| Case | Court | Status |
|---|---|---|
| RCS No 120/2018/2018 | Court of Civil Judge Karjat | Pending for hearing on application for dismissal of suit |
| 120/2018/2018 | Civil Judge Junior Division | Ongoing |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| SM12600110 | Bhakti Achrekar | ARIHANT AASHIYANA PRIVATE LIMITED | 05/02/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 19 Feb 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Aug 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 12 Aug 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Aug 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2031
Documents filed127
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 127 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: 10 Form 1_ALOKI PH V_310326.pdf | 16 Apr 2026 |
| Withdrawal Update Form 2File: Form 2_Aloki Ph V_250326.pdf | 16 Apr 2026 |
| Withdrawal Update Form 3File: 10 Form 3_Aloki Ph V_250326.pdf | 16 Apr 2026 |
| Withdrawal Update Form 1File: Form 1_Aloki Phase V_31122025.pdf | 20 Jan 2026 |
| Withdrawal Update Form 2File: Form 2_Aloki Ph V_31122025.pdf | 20 Jan 2026 |
| Withdrawal Update Form 3File: Form 3_Aloki Phase V_31122025.pdf | 20 Jan 2026 |
| Withdrawal Update Form 1File: Form 1_ALOKI PHASE V_30092025.pdf | 17 Oct 2025 |
| Withdrawal Update Form 2File: Form 2_Aloki Ph V_30092025.pdf | 17 Oct 2025 |
| Withdrawal Update Form 3File: Form 3_Aloki Ph V_30092025.pdf | 17 Oct 2025 |
| Form 5 (FY 2024-2025)File: Aloki Phase V.pdf | 17 Oct 2025 |
| Form 2A (FY 2024-2025)File: Aloki Phase V.pdf | 4 Oct 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Aloki Ph V_310325.pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Aloki Ph-V_310325.pdf | 18 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Aloki Ph-V_310325_SIGNED.pdf | 18 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE SIGNED.pdf | 18 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Aloki Phase V.pdf | 19 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Aloki Phase V.pdf | 19 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Aloki Phase V.pdf | 19 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLSOURE SIGNED.pdf | 19 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Aloki Phase V_signed.pdf | 12 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Aloki Ph V.pdf | 21 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE_SIGNED.pdf | 21 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM I - ALOKI PHASE V_SIGNED.pdf | 19 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aloki 5 SIGNED.pdf | 19 Oct 2024 |
| Declaration about Commencement CertificateFile: Aloki V - Format D SIGN.pdf | 13 Aug 2024 |
| Layout approvalFile: 1.pdf | 12 Aug 2024 |
| Building plan approvalFile: 2.pdf | 12 Aug 2024 |
| Building plan approvalFile: 3.pdf | 12 Aug 2024 |
| Building plan approvalFile: 4.pdf | 12 Aug 2024 |
| Building plan approvalFile: 5.pdf | 12 Aug 2024 |
| Building plan approvalFile: 6.pdf | 12 Aug 2024 |
| Building plan approvalFile: 7.pdf | 12 Aug 2024 |
| Copy of Layout Approval (in case of layout)File: 1.pdf | 12 Aug 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 2.pdf | 12 Aug 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 3.pdf | 12 Aug 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 4.pdf | 12 Aug 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 5.pdf | 12 Aug 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 6.pdf | 12 Aug 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 7.pdf | 12 Aug 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: ARIHANT ALOKI C1-C2 CC 04-02-2022.pdf | 12 Aug 2024 |
| Details of encumbrances concerned to FinanceFile: Aloki V - Encumbrance Letter Legal SIGN.pdf | 10 Aug 2024 |
| Details of encumbrances concerned to LegalFile: Aloki V - Encumbrance Letter Legal SIGN.pdf | 10 Aug 2024 |
| Declaration about Commencement CertificateFile: Aloki V - Format D.pdf | 10 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aloki V - Form 1 30062024.pdf | 10 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aloki V - Form 2 30062024.pdf | 10 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Aloki V 19-20 SIGN.pdf | 10 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Aloki V 20-21 SIGN.pdf | 10 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Aloki V 21-22 SIGN.pdf | 10 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Aloki V 22-23 SIGN.pdf | 10 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Aloki V 23-24 SIGN.pdf | 10 Aug 2024 |
| CERSAI detailsFile: Aloki V - Cersai Declaration.pdf | 10 Aug 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf | 10 Aug 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Aloki V - Form 5 FY 21-22.pdf | 10 Aug 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Aloki V - Form 5 FY 22-23.pdf | 10 Aug 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Aloki V - Format A.pdf | 10 Aug 2024 |
| Declaration in FORM BFile: Aloki V - Form B.pdf | 9 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aloki V - Form 3 30062024_11zon.pdf | 9 Aug 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_Aloki Phase 5_FY 22-23.pdf | 5 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Aaloki V.pdf | 22 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ALOKI PHASE V.PDF | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure SIGNED.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 30062024 Aloki Phase V SIGNED.pdf | 20 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_Aloki Phase 5_FY 22-23.pdf | 7 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Aloki V - Dec 23 SIGNED.pdf | 28 May 2024 |
| Disclosure of sold/ booked inventoryFile: Aloki V - Mar 24 SIGNED.pdf | 28 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Aloki Phase V 31032024.PDF | 4 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Aloki Phase V 31122023.pdf | 4 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Aloki Phase V 31032024.pdf | 4 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 31032024 Aloki Phase V SIGN.pdf | 23 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aloki Phase 5.pdf | 7 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE - ARIHANT ALOKI PHASE V 30TH DECEMBER 2023.PDF | 22 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE - ARIHANT ALOKI PHASE V 30TH DECEMBER 2023.PDF | 22 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM I -ARIHANT ALOKI PHASE V 30 SEPTEMBER 2023.PDF | 19 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 RERA Aloki Ph V Sept 2023.pdf | 19 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Arihant Aloki Phase 5-Aashiyana.pdf | 19 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aloki Phase-V.pdf | 19 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 RERA Aloki 5 June 2023.pdf | 19 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARIHANT ALOKI PHASE V - FORM 1 - ARCHITECT CERTIFICATE 30 JUNE 2023.PDF | 17 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AlokiPhaseV.pdf | 17 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 RERA ALOKI 5 MARCH 2023.pdf | 19 Apr 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 11 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 127 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ARIHANT ALOKI PHASE V on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near karjat5,900+ in Raigarh
Filed coordinates, straight-line distance. 103 registered projects within 2 km.
Bellezza Woods
DOTOM BUILD SQUARE
Winds of Calm
Eiffel Lifespaces Pvt Ltd
PURANIK CITY SECTOR 2
Puranik Builders Limited
Foothills of Matheran P - 2
HOABL Impactum Land Private Limited
FLORENCE TOWN
BRIGHT DEVELOPERS
The Destination
DOVE BUILDMART PRIVATE LIMITED
See every Raigarh project, with the district possession charts
Builder: ARIHANT AASHIYANA PRIVATE LIMITED
ARIHANT AASHIYANA PRIVATE LIMITED has 12 registrations on MahaRERA, including ARIHANT ANSHULA and ARIHANT AMISHA PHASE I. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if ARIHANT ALOKI PHASE V is delayed beyond 31 Dec 2031?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ARIHANT ALOKI PHASE V?
The registered promoter entity is ARIHANT AASHIYANA PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ARIHANT ALOKI PHASE V?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ARIHANT ALOKI PHASE V?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for ARIHANT ALOKI PHASE V?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ARIHANT ALOKI PHASE V?
The professionals named in the filing: Architect: YOGITA BHANDARKAR; Engineer: SATISH MHATRE; Engineer: KALEEM SAYYAD; Engineer: ER. Kaleem Sayyad; Chartered Accountant: Ummed Jain & Co.; Chartered Accountant: ANJANI KUMAR GOYAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ARIHANT ALOKI PHASE V?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback