ARCADIA
RG-MH-25095 · RERA P52100013508 · Last updated on MahaRERA portal: 22 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- 2 complaints at MahaRERA
- Completion date moved by 42 months
- 4 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ARCADIA is a Residential / Group Housing project by ACME SAWANT VENTURES in Pune, Maharashtra, registered with MahaRERA as P52100013508 on 9 Oct 2017. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 42 months from the original filing. 70 of the 119 units on this registration are recorded sold or booked, and 10 of 22 construction stages are filed complete. 2 complaints are on record with the regulator.
At a glance
Project
- NameARCADIA
- TypeResidential / Group Housing
- Location
- PUNE SATARA rOAD
- NR BHARAT PETROL PUMP
- Bhilarewadi
- Haveli
- Pune
- 411046
- Pincode411046
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100013508
- ReraGenie IDRG-MH-25095
Builder
- NameACME SAWANT VENTURES
- Entity typePartnership
- PartnersABHAY LAXMIKANT DESAI, RAJIV SADHU SAWANT, VIJAY DEVIDAS MUNDPHANE
- Other registrations2 more →
- Completed2 of 3
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on9 Oct 2017
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 15 Dec 2022)
- Buildings2 building records
- Documents filed313 files
Current status
Figures as on 22 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | NA | 10 | 10 | 107 | 12 | 119 |
| B | NA | 0 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 22 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 95%.
A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 22 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 10% |
| Street Lighting | No | Not applicable |
| Community Buildings | Yes | 60% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 100% |
Parking filed128
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership5
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| BALKRISHNA DAGDOBA BHILARE | Bhilarewadi | Pune |
| SOPAN DAGDOBA BHILARE | Bhilarewadi | Pune |
| SUMAN NAMDEO BHILARE | Pune (CB) | Pune |
| DEVIDAS BHIMRAO MUNDPHANE | Pune (M Corp.) | Pune |
| NIVRUTI DAGDOBA BHILARE | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A | NA | Rs 14.89 cr | Rs 14.59 cr |
| - | NA | Rs 2.62 cr | Rs 2.41 cr |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | NILESH GOVINDLAL BANG |
| Architect | BABASAHEB DHAVALE AND ASSOCITES |
| Engineer | SUBHASH MANGLORI ASSOCIATES |
| Engineer | AJINKYA BHAGAT |
| Engineer | Aditya Desai |
| Engineer | Abhay Desai |
| Chartered Accountant | SPAK & CO. |
| Chartered Accountant | Bogati & Co |
| Partner | Role in project |
|---|---|
| ACME SAWANT VENTURES | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAs part of our building is still remaining to be completed and we know that during Covid there has been Slowdown in the Real estate sector and same has impacted us also. So, please grant us the extension for completion of the same and handover to respective owners within tie.
Reason as filed by the promoterDue to MOD, Completion Certificate is still not received, also Flat No.1 and Common Work is in progress and have not been completed. As a result of poor market condition, covid Lock down and poor funding we are unable to complete the project within the due time.
Reason as filed by the promoterI was planning to expand the project,but there was a delay in receiving the sanction plan from the local authority.This setback has postponed our project timeline as we need the official approval to proceed with the expansion.
Reason as filed by the promoterConstruction of the said project is 97% completed. We are in process to complete the remaining construction of the project. We need extension to complete the remaining construction
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000259014 | MAHENDRA SITARAM GHANEKAR | ABHAY LAXMIKANT BHILARE | 14/06/2023 |
| CC12600160 | Chaitrali Somnath Bhilare | ACME SAWANT VENTURES | 10/01/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 10 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 6 Apr 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 Mar 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 10 Aug 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed313
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 313 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A Rear 25-26.pdf | 22 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 _Acme Jun 26.pdf | 14 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 _Acme jun 26.pdf | 14 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 _Acme Jun 26_compressed.pdf | 14 Jul 2026 |
| Withdrawal Update Form 1File: Form 1_acme _mar 26.pdf | 21 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 31-03-26.pdf | 21 Apr 2026 |
| Withdrawal Update Form 3File: Form-3_ACME Sawant_Arcadia_Mar26_Signed_1.pdf | 21 Apr 2026 |
| Layout approvalFile: LAYOUT.pdf | 6 Apr 2026 |
| Building plan approvalFile: Arcadia compressed-2-5.pdf | 9 Mar 2026 |
| Building plan approvalFile: Sanction plans Arcadia6-10_.pdf | 9 Mar 2026 |
| Building plan approvalFile: Sanction plan Arcadia 10-14.pdf | 9 Mar 2026 |
| Form 5 (FY 2021-2022)File: Arcadia Form 5 FY 2021-22.pdf | 23 Feb 2026 |
| Form 5 (FY 2022-2023)File: Arcadia Form 5 FY 2022-23.pdf | 23 Feb 2026 |
| Form 5 (FY 2017-2018)File: Arcadia Form 5 FY 2017-18.pdf | 21 Feb 2026 |
| Form 5 (FY 2018-2019)File: Arcadia Form 5 FY 2018-19.pdf | 21 Feb 2026 |
| Form 5 (FY 2019-2020)File: Arcadia Form 5 FY 2019-20.pdf | 21 Feb 2026 |
| Form 5 (FY 2020-2021)File: Arcadia Form 5 FY 2020-21.pdf | 21 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 Acme Dec 25.pdf | 20 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Acme dec 2025.pdf | 20 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 Acme Dec 25.pdf | 20 Feb 2026 |
| Form 2A (FY 2023-2024)File: March 2024.pdf | 5 Feb 2026 |
| Form 2A (FY 2024-2025)File: form 2A March 25.pdf | 5 Feb 2026 |
| Form 2A (FY 2019-2020)File: Arcadia Form 2A FY 2019-20.pdf | 5 Feb 2026 |
| Form 2A (FY 2020-2021)File: Arcadia Form 2A FY 2020-21.pdf | 5 Feb 2026 |
| Form 2A (FY 2021-2022)File: Arcadia Form 2A FY 2021-22.pdf | 5 Feb 2026 |
| Form 2A (FY 2022-2023)File: Arcadia Form 2A FY 2022-23.pdf | 5 Feb 2026 |
| Form 1File: Form 1 dec 24 acme.pdf | 28 Jan 2026 |
| Form 2File: Form 2 dec 24 acme.pdf | 28 Jan 2026 |
| Form 3File: Form 3 December 24acme compressed Final.pdf | 28 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold disclosure Dec 24 Acme_compressed.pdf | 28 Jan 2026 |
| Form 2A (FY 2017-2018)File: FORM 2A 2017-18.pdf | 23 Jan 2026 |
| Form 2A (FY 2018-2019)File: FORM 2A 2018-19.pdf | 23 Jan 2026 |
| Form 5 (FY 2023-2024)File: Form 5 fy 23-24.pdf | 22 Jan 2026 |
| Withdrawal Update Form 1File: Form 1-Sep 25.pdf | 3 Nov 2025 |
| Withdrawal Update Form 2File: Form 2-Signed Acme Sep-25_compressed.pdf | 3 Nov 2025 |
| Withdrawal Update Form 3File: acme Acme Sawant Sep 25.pdf | 3 Nov 2025 |
| Form 5 (FY 2024-2025)File: form 5 Acme Sawant Fy 24-25.pdf | 24 Sep 2025 |
| Form 1File: FORM 1 MARCH 18.pdf | 3 Sep 2025 |
| Form 2File: FORM 2 MARCH 18.pdf | 3 Sep 2025 |
| Form 3File: 2 31 March 2018 compressed ok.pdf | 3 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: 2 March 18_compressed.pdf | 3 Sep 2025 |
| Form 1File: FORM 1 JUNE 18.pdf | 3 Sep 2025 |
| Form 2File: FORM 2 JUNE 18.pdf | 3 Sep 2025 |
| Form 3File: 3 31 June 2018 compressed ok.pdf | 3 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: 3 June 18_compressed.pdf | 3 Sep 2025 |
| Form 1File: FORM 1 SEP 18.pdf | 3 Sep 2025 |
| Form 2File: FORM SEPT 18.pdf | 3 Sep 2025 |
| Form 3File: 4 30 Sep 2018 compressed ok.pdf | 3 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: 4 September 18_compressed.pdf | 3 Sep 2025 |
| Form 1File: form 1 dec 2018.pdf | 3 Sep 2025 |
| Form 2File: FORM 2 DEC 18.pdf | 3 Sep 2025 |
| Form 3File: 5 31 Dec 2018 compressed ok.pdf | 3 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: 5 dec 18_compressed.pdf | 3 Sep 2025 |
| Form 1File: Form 1 march 2019.pdf | 3 Sep 2025 |
| Form 2File: FORM 2 MARCH 19.pdf | 3 Sep 2025 |
| Form 3File: 6 31 March 2019 compressed ok.pdf | 3 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: 6 MARCH 2019_compressed.pdf | 3 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: 7 JUNE 2019_compressed.pdf | 3 Sep 2025 |
| Form 2File: Form 2 June 2019.pdf | 3 Sep 2025 |
| Form 3File: 7 30 june 2019 compressed ok.pdf | 3 Sep 2025 |
| Form 1File: form 1 june 2019.pdf | 3 Sep 2025 |
| Form 1File: form 1 sep 2019.pdf | 3 Sep 2025 |
| Form 2File: Form 2 sept 19.pdf | 3 Sep 2025 |
| Form 3File: 8 30 sep 2019 compressed ok.pdf | 3 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: 8 SEPTEMBER 2019_compressed.pdf | 3 Sep 2025 |
| Form 1File: form 1 dec 2019.pdf | 3 Sep 2025 |
| Form 2File: Form 2 Dec 2019.pdf | 3 Sep 2025 |
| Form 3File: 9 31 Dec 2019 compressed ok.pdf | 3 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: 9 December 2019_compressed.pdf | 3 Sep 2025 |
| Form 1File: form 1 march 2020.pdf | 3 Sep 2025 |
| Form 2File: Form 2 March 2020.pdf | 3 Sep 2025 |
| Form 3File: 10 31 March 2020 compressed ok.pdf | 3 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: 10 MARCH 2020_compressed.pdf | 3 Sep 2025 |
| Form 1File: form 1 june 2020.pdf | 3 Sep 2025 |
| Form 2File: form 2 june 2020.pdf | 3 Sep 2025 |
| Form 3File: 11 30 June 2020 compressed ok.pdf | 3 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: 11JUNE 2020_compressed.pdf | 3 Sep 2025 |
| Form 1File: form 1 sep 2020.pdf | 3 Sep 2025 |
| Form 2File: form 2 sep 2020.pdf | 3 Sep 2025 |
| Form 3File: 12 30 Sep 2020 compressed ok.pdf | 3 Sep 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 313 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ARCADIA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NR BHARAT PETROL PUMP13,700+ in Pune
Filed coordinates, straight-line distance. 49 registered projects within 2 km.
Sai Nagari Phase I
Saikedareshwar Developers LLP
SAI NAGARI Phase V
Saikedareshwar Developers LLP
Sai Nagari Phase II
Saikedareshwar Developers LLP
Sai Nagari Phase IV
Saikedareshwar Developers LLP
Sai Nagari Phase III
Saikedareshwar Developers LLP
Bella Casa - Phase 1
Kakkad Infra LLP
Builder: ACME SAWANT VENTURES
ACME SAWANT VENTURES has 3 registrations on MahaRERA, including AZALEA and ARCADIA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that ARCADIA shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if ARCADIA is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ARCADIA?
The registered promoter entity is ACME SAWANT VENTURES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ARCADIA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ARCADIA?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for ARCADIA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ARCADIA?
The professionals named in the filing: Architect: NILESH GOVINDLAL BANG; Architect: BABASAHEB DHAVALE AND ASSOCITES; Engineer: SUBHASH MANGLORI ASSOCIATES; Engineer: AJINKYA BHAGAT; Engineer: Aditya Desai; Engineer: Abhay Desai. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ARCADIA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.