Home / Browse projects / Mumbai Suburban, Maharashtra / APEX GREEN WOOD
APEX GREEN WOOD
RG-MH-48377 · RERA P51800047381 · Last updated on MahaRERA portal: 30 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
APEX GREEN WOOD is a Residential / Group Housing project by APEX INFRATEC in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800047381 on 27 Oct 2022. Possession was promised by 30 Jun 2026 and is now 4 months past that date. 149 of the 250 units on this registration are recorded sold or booked, and 24 of 33 construction stages are filed complete.
At a glance
Project
- NameAPEX GREEN WOOD
- TypeResidential / Group Housing
- Location
- MAUJE MAGATHANE VILLAGE
- RAJENDRA NAGAR
- DATTAPADA ROAD
- BORIVALI EAST
- MUMBAI
- Borivali
- Mumbai Suburban
- 400066
- Pincode400066
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800047381
- ReraGenie IDRG-MH-48377
Builder
- NameAPEX INFRATEC
- Entity typePartnership
- PartnersDEVSHANKAR SUSHIL CHOUDHARY, PARAG BIPINBHAI SHAH, VIRAG PRAVINCHANDRA KOTHARI
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on27 Oct 2022
- Promised completion30 Jun 2026
- Revised completionNone
- Buildings3 building records
- Documents filed87 files
Current status
Figures as on 30 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BLDG NO 1 | NA | 25 | 23 | 57 | 0 | 57 |
| BLDG NO 2 A WING | NA | 25 | 23 | 86 | 0 | 86 |
| BLDG NO 2 B WING | NA | 25 | 23 | 107 | 0 | 107 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 30 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
24 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Basement (if any), at 0%.
BLDG NO 173%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BLDG NO 2 A WING73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BLDG NO 2 B WING73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 30 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed167
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| BLDG NO 1 | 32 | 32 |
| BLDG NO 2 A WING | 135 | 135 |
Land and ownership2
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| APEX INFRATEC | Borivali | Mumbai Suburban |
| RAJENDRA NAGAR CO-OP HOUSING SOCIETY LIMITED | Borivali | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| BLDG NO 2 B WING | NA | Rs 27.51 cr | Rs 25.51 cr |
| BLDG NO 2 A WING | NA | Rs 15.60 cr | Rs 14.47 cr |
| BLDG NO 1 | NA | Rs 15.27 cr | Rs 14.16 cr |
| - | NA | Rs 6.15 cr | - |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | 3 Dimensional Consultants LLP |
| Engineer | Hiren Mohanlal Tanna |
| Engineer | ANKIT SATISH SHAH |
| Chartered Accountant | BOHRA OM & COMPANY |
| Partner | Role in project |
|---|---|
| APEX INFRATEC | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Oct 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 20 Oct 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 20 Oct 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 14 Oct 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed87
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 87 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1 RERA Architect certificate BLDG NO 02 23012026 Wing A.pdf | 30 Jun 2026 |
| Withdrawal Update Form 1File: FORM 1 RERA Architect certificate BLDG NO 02 23012026 Wing A.pdf | 30 Jun 2026 |
| Withdrawal Update Form 1File: FORM 1 RERA Architect certificate BLDG NO 01 31032026.Pdf | 30 Jun 2026 |
| Withdrawal Update Form 2File: Q13 Apex Engineers Certificate 17012026 .pdf | 30 Jun 2026 |
| Withdrawal Update Form 2File: Q13 Apex Engineers Certificate 17012026 .pdf | 30 Jun 2026 |
| Withdrawal Update Form 2File: Q14_SHRADDHA_FORM 2_20042026.pdf | 30 Jun 2026 |
| Withdrawal Update Form 3File: FORM 3 ANNEXURE D Apex Infratec 07102025.pdf | 30 Jun 2026 |
| Withdrawal Update Form 3File: FORM 3 ANNEXURE D Apex Infratec 07102025.pdf | 30 Jun 2026 |
| Withdrawal Update Form 3File: FORM 3 ANNEXURE D Apex Infratec 07102025.pdf | 30 Jun 2026 |
| Form 1File: FORM 1 RERA Architect certificate BLDG NO 01 & 02 30062025 merged.pdf | 31 Jul 2025 |
| Form 2File: Form 2 Engineer's Certificate Q11Apex.pdf | 31 Jul 2025 |
| Form 3File: Form 3 CA Certificate Apex Infratec Apr to Jun 25.pdf | 31 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD OR BOOKED INVENTORY.pdf | 31 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 ANNEXURE D Apex Infratec 07042025.pdf | 30 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Signed FORM 1 RERA Architect certificate BLDG NO01 31032025.pdf | 20 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: signed FORM 1 RERA Architect certificate(BLDG NO 02) 31032025 (Wing A).pdf | 20 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: signed FORM 1 RERA Architect certificate(BLDG NO 02) 31032025 (Wing B).pdf | 20 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate Q10 Apex.pdf | 20 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 ANNEXURE D Apex Infratec 07012025.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Apex Infratec 012025.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - RERA Architect certificate merged.pdf | 18 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 ANNEXURE D Apex Infratec 07102024.pdf | 20 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 RERA Architect certificate BLDG NO 01 10102024 1.pdf | 15 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 RERA Architect certificate BLDG NO02 10102024.pdf | 15 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate Q8.pdf | 15 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 Apex Rera.pdf | 6 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 ANNEXURE D Apex Infratec 07042024 Final.pdf | 6 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate Q7.pdf | 15 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Q6 Final 31032024.pdf | 25 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 RERA CERTIFICATE FINAL.pdf | 25 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - RERA Architect certificate BLDG NO 01 06042024.PDF | 14 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1- RERA ARCHITECT CERTIFICATE BLDG NO 02 060424.pdf | 14 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer's Certificate Apex Infratec 240124.pdf | 31 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 RERA APEX INFRATEC.pdf | 31 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect certificate Bldg No 01 060124.pdf | 8 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect certificate Bldg No 02 060124.pdf | 8 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate 12102023.pdf | 12 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer's Certificate 12102023.pdf | 12 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Apex Infratec 07102023.pdf | 12 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1FORM 1 Architect certificate New 06102023.pdf | 9 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect certificate Bldg No 01 06102023.pdf | 9 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 RERA APEX SHRADDHA.pdf | 30 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 ANNEXURE D Apex Infratec 07072023.pdf | 8 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Architect certificate BLDG NO 01 04072023.pdf | 7 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA ARCHITECT CERTIFICATE BLDG NO 02 05072023.pdf | 7 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Apex Infratec 07072023.pdf | 7 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate Apex Infratec 08042023.pdf | 12 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: final rera form 3 signed.pdf | 12 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Architect certificate BLDGNO01 06042023.pdf | 7 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RARA ARCHITECT CERTIFICATE BLDG NO 02 060423.pdf | 7 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect certificate 060123.pdf | 7 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer's Certificate 06012023.pdf | 7 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: apex final 07012023.pdf | 7 Jan 2023 |
| Other - LegalFile: Agreement for Sale Apex Green Wood.pdf | 21 Oct 2022 |
| Layout approvalFile: BUILDING NO 1 PART 1.pdf | 20 Oct 2022 |
| Layout approvalFile: Layout Plan_Bldg 2 A wing and B wing.pdf | 20 Oct 2022 |
| Building plan approvalFile: BUILDING NO 2 PART 2.pdf | 20 Oct 2022 |
| Building plan approvalFile: Building Plan Approved _Bldg 2 Part 3.pdf | 20 Oct 2022 |
| Building plan approvalFile: Building Plan Approved _Bldg 2 Part 3.pdf | 20 Oct 2022 |
| Building plan approvalFile: Building Plan Approved _Bldg 2 Part 4.pdf | 20 Oct 2022 |
| Building plan approvalFile: BUILDING NO 2 PART 2.pdf | 20 Oct 2022 |
| Copy of Layout Approval (in case of layout)File: BUILDING NO 1 PART 1.pdf | 20 Oct 2022 |
| Copy of Layout Approval (in case of layout)File: Layout Plan_Bldg 2 A wing and B wing.pdf | 20 Oct 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING NO 2 PART 2.pdf | 20 Oct 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan Approved _Bldg 2 Part 3.pdf | 20 Oct 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan Approved _Bldg 2 Part 3.pdf | 20 Oct 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan Approved _Bldg 2 Part 4.pdf | 20 Oct 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING NO 2 PART 2.pdf | 20 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: APEX FINAL RERA FORM 3 20102022.pdf | 20 Oct 2022 |
| Deviation Report with respect to model copy of AgreementFile: DEVIATION WITH RESPECT TO MODEL COPY OF AGREEMENT.pdf | 20 Oct 2022 |
| Copy of the legal title reportFile: Title Report Apex Green Wood.pdf | 14 Oct 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Plinth CC bldg no 2.pdf | 14 Oct 2022 |
| Declaration about Commencement CertificateFile: Form D Declaration for commencement certificate.pdf | 14 Oct 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Form A Delcaration for Bank Account.pdf | 14 Oct 2022 |
| Deviation Report with respect to Allotment letterFile: APEX DEVIATION SHEET FOR ALLOTMENT.pdf | 14 Oct 2022 |
| Proforma of Agreement for saleFile: Allotment Letter Apex Infratec.pdf | 7 Oct 2022 |
| Proforma of Allotment letterFile: Allotment Letter Apex Infratec.pdf | 7 Oct 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Title As per RERA (Rajendra Nagar Shradha CHSL) Part 1.pdf | 7 Oct 2022 |
| Status of ConveyanceFile: 712 Property Card Apex Infrastructure.pdf | 7 Oct 2022 |
| Details of encumbrances concerned to FinanceFile: Self Declaration non encumbrance.pdf | 26 Sep 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 87 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep APEX GREEN WOOD on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MUMBAI6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 110 registered projects within 2 km.
Shraddha Park City
Shraddha Prime Projects Limited
GREENAIRY
SAROJ LANDMARK REALTY LLP
Sky City Tower H
Incline Realty Private Limited
Sky City Tower G
Incline Realty Private Limited
SHEETAL REGALIA
D G S TOWNSHIP PRIVATE LIMITED
JANGID ELYSIUM
IMPRINT CONSTRUCTION PRIVATE LIMITED
See every Mumbai Suburban project, with the district possession charts
Builder: APEX INFRATEC
APEX INFRATEC has 1 registration on MahaRERA, including APEX GREEN WOOD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that APEX GREEN WOOD shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if APEX GREEN WOOD is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of APEX GREEN WOOD?
The registered promoter entity is APEX INFRATEC, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in APEX GREEN WOOD?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for APEX GREEN WOOD?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at APEX GREEN WOOD?
The professionals named in the filing: Architect: 3 Dimensional Consultants LLP; Engineer: Hiren Mohanlal Tanna; Engineer: ANKIT SATISH SHAH; Chartered Accountant: BOHRA OM & COMPANY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in APEX GREEN WOOD?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback