Registration lapsed No litigation declared Residential / Group Housing project

Anuradha Shrushti

RG-MH-12259 · RERA P53100005075 · Last updated on MahaRERA portal: Not stated

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 104 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.
Feb 2018Possession promised104 months past this date
0Complaints at MahaRERAon this registration
Jump to the 0 documents Report an error

Anuradha Shrushti is a Residential / Group Housing project by Promoter name not stated in filing in Sangli, Maharashtra, registered with MahaRERA as P53100005075 on 9 Aug 2017. Possession was promised by 28 Feb 2018 and is now 104 months past that date.

At a glance

Project

  • NameAnuradha Shrushti
  • TypeResidential / Group Housing
  • Location
    • Sangli Miraj Kupwad (M Corp.)
    • Miraj
    • Sangli
    • 416415
  • Pincode416415
  • RERA no.P53100005075
  • ReraGenie IDRG-MH-12259

Builder

  • NamePromoter name not stated in filing

Key dates

104 months past promisethis monthRegisteredAug 2017PromisedFeb 2018

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Aug 2017
  • Promised completion28 Feb 2018
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed0 files

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area363 sq m
Land owned byThe promoter
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
Vidhi Builders & Associates-

Complaints filed with MahaRERA

No complaints on record against this registration.

How this compares with Sangli

11%of Sangli projects moved their completion datethis one has not
29%of Sangli registrations have lapsed or been cancelledthis one is among them

Computed across the 790+ Sangli projects on ReraGenie, from their own filings.

Keep Anuradha Shrushti on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Sangli Miraj Kupwad (M Corp.)790+ in Sangli

Builder: Promoter name not stated in filing

The filing does not name a promoter organisation for this registration. See more projects on the Sangli district page.

Frequently asked questions

What does it mean that Anuradha Shrushti shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Anuradha Shrushti is delayed beyond 28 Feb 2018?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Anuradha Shrushti?

The registered promoter entity is Promoter name not stated in filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Anuradha Shrushti?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in Anuradha Shrushti?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Anuradha Shrushti. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Anuradha Shrushti to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.