Home / Browse projects / ANSHULKOSMAS C AND D BUILDING

Registration lapsed No litigation declared Others project

ANSHULKOSMAS C AND D BUILDING

By M/S ANSHULBHOSALE REALTY

RG-MH-09276 · RERA P52100000851 · Last updated on MahaRERA portal: 31 Mar 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 67 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 23 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Mar 2021Possession promised67 months past this date
14 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 95%
1Complaints at MahaRERAon this registration
Jump to the 50 documents Report an error

ANSHULKOSMAS C AND D BUILDING is a Others project by M/S ANSHULBHOSALE REALTY in Anant Nagar, 412105, registered with MahaRERA as P52100000851 on 23 Jul 2017. Possession was promised by 31 Mar 2021 and is now 67 months past that date. The completion date has moved by 23 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameANSHULKOSMAS C AND D BUILDING
  • TypeOthers
  • Location
    • Old Dehu Road
    • Anant Nagar
    • 412105
  • Pincode412105
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100000851
  • ReraGenie IDRG-MH-09276

Builder

  • NameM/S ANSHULBHOSALE REALTY
  • Entity typePartnership
  • PartnerDeepak Vilasrao Jagtap

Key dates

67 months past promisethis monthRegisteredJul 2017First promiseApr 2019Revised toMar 2021

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on23 Jul 2017
  • Promised completion31 Mar 2021
  • Revised completionRevised to 31 Mar 2021 (originally 30 Apr 2019)
  • Buildings2 building records
  • Documents filed50 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C BULDINGNA160000
D BUILDINGNA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 31 Mar 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 95%.

C BULDING90%
ActivityProgress
Excavation100%
Basement (if any)95%
Podiums (if any)0%
Plinth95%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
D BUILDING90%
ActivityProgress
Excavation100%
Basement (if any)95%
Podiums (if any)0%
Plinth95%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 31 Mar 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes70%
Street LightingYes100%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
C BULDING11
D BUILDING11

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,446 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
BALU ANANTA SASTEDehu Road (CB)Pune
CHANDRAKANT ANANT SASTEDehu Road (CB)Pune
SANDEEP ANANT SASTEDehu Road (CB)Pune

Approvals and building plan

Permissible FSI15993.44
Proposed, not sanctioned14,323 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBHANDARKAR ROAD PUNE

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNITIN WAGHMARE
EngineerG A BHILARE
PartnerRole in project
M/S ANSHULBHOSALE REALTY-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100003676Apr 2019 → Apr 2020

Reason as filed by the promoterTo, Maharashtra Real Estate Regulatory Authority Dear Sir/Madam, We promoter/builder of Anshul Kosmas project having RERA No. P52100000851, our project expiry date is 30/04/2019. However the said project is completed on dated 16/05/2018 and our project Architect Mr. Nitin M. Waghmare has applied for Occupancy Certificate on 17/05/2018 before Executive Engineer of Pimpri Chinchwad Municipal Corporation, Building permission department and the copy of which is uploaded and updated in other document on the said website. However the same is pending before PCMC Authority for receiving Occupancy/comp

EXT52100008446Apr 2019 → Mar 2021

Reason as filed by the promoterWE HAVE COMPLITED OUR PROJECT BUT DUE TO COVID 19 CORPORATION PEPOLE ARE WORKING WITH 50% STRENTH HENCE WE ARE NOT ABLE TO GET THE OCCUPENCY CERTIFICATE HENCE WE REQUEST YOU TO GIVE US EXTENSION OF LAST SIX MONTHS. THANK YOU

Litigation declared2

CaseCourtStatus
1568/2012CIVIL JUDGE SENIOR DIVISIONFOR HEARING
1096/2016SUB DIVISIONAL OFFICER HAVELIOrder Passed

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000010460Zeeshan ShaikhAnshul Bhosale Realty (Deepak Jagtap & Vikram Bhosale)08/11/2017

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Dec 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 24 Mar 2022

Documents filed50

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AC_KosmasCD_Dec21.pdf31 Mar 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EC_KosmasCD_Dec2021.pdf24 Mar 2022
Certificates of CA (Form 3)File: CA_KosmasCD_Dec2021.pdf24 Mar 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Architect_Cert.pdf24 Mar 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EC_KosmasCD_Dec21.pdf3 Mar 2022
Certificates of CA (Form 3)File: CA_KosmasCD_Sept21.pdf4 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EC_KosmasCD_Sept21.pdf17 Nov 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AC_KosmasCD_Sept21.pdf15 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: EA_Kosmas_QualityAssu_2019-20.pdf20 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: EA_Kosmas_QualityAssu_2020-21.pdf20 Aug 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Kosmas part completion.pdf31 Jul 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EC_KosmasCD_June21.pdf22 Jul 2021
Certificates of CA (Form 3)File: CA_KosmasCD_June21.pdf20 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AC_KosmasCD_June21.pdf15 Jul 2021
Certificates of CA (Form 3)File: CA_KosmasCD_March21_compressed.pdf17 Apr 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AC_KosmasCD_March21.pdf14 Apr 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EC_KosmasCD_March21.pdf14 Apr 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AC_KosmasCDSept20.pdf15 Feb 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AC_KosmasCDDec20.pdf15 Feb 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EC_KosmasCDDec20.pdf15 Feb 2021
Certificates of CA (Form 3)File: CA_KosmasSept20.pdf31 Jan 2021
Certificates of CA (Form 3)File: CA_KosmasDec20.pdf31 Jan 2021
Certificates of CA (Form 3)File: CA_Kosmas.pdf28 Jun 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EC_KosmasCD.pdf29 May 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AC_KosmasCD.pdf13 Feb 2019
Certificates of CA (Form 3)File: CA_KosmasCD.pdf13 Feb 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EC_Kosmas.pdf24 Jan 2019
Certificates of CA (Form 3)File: CA_Kosmas.pdf25 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AC_Kosmas.pdf2 Nov 2018
Certificates of CA (Form 5)File: Form5_Kosmas.pdf15 Oct 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EC_KosmasCD.pdf6 Aug 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AC_KosmasCD.pdf1 Aug 2018
Certificates of CA (Form 3)File: CA_KosmasCD.pdf1 Aug 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AC_Kosmas.pdf2 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EC_Kosmas.pdf21 Apr 2018
Certificates of CA (Form 3)File: CA Kosmos.pdf17 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: kosmas Commencement.pdf23 Dec 2017
Building plan approvalFile: Kosmas IOD-ilovepdf-compressed.pdf20 Jul 2017
Layout approvalFile: Copy of Layout Approval.pdf20 Jul 2017
Copy of Layout Approval (in case of layout)File: Copy of Layout Approval.pdf20 Jul 2017
Building Plan Approval (IOD)File: Kosmas IOD-ilovepdf-compressed.pdf20 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate Kosmas.pdf20 Jul 2017
Proforma of Allotment letterFile: kosmas agreement.pdf20 Jul 2017
OtherFile: Addl Affidavit.pdf20 Jul 2017
Declaration in FORM BFile: Declaration Promoter Kosmas.pdf19 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf19 Jul 2017
Certificates of CA (Form 3)File: CA Certificate - Anshul Kosmas.pdf19 Jul 2017
Details of encumbrancesFile: Mortgage Deed Reliance - Index II.pdf12 Jul 2017
PAN CardFile: ABR PAN CARD.pdf11 Jul 2017
Copy of the legal title reportFile: Search Title.pdf11 Jul 2017

Keep ANSHULKOSMAS C AND D BUILDING on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Anant Nagar

Builder: M/S ANSHULBHOSALE REALTY

M/S ANSHULBHOSALE REALTY has 1 registration on MahaRERA, including ANSHULKOSMAS C AND D BUILDING. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What does it mean that ANSHULKOSMAS C AND D BUILDING shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ANSHULKOSMAS C AND D BUILDING is delayed beyond 31 Mar 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ANSHULKOSMAS C AND D BUILDING?

The registered promoter entity is M/S ANSHULBHOSALE REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ANSHULKOSMAS C AND D BUILDING?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ANSHULKOSMAS C AND D BUILDING?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ANSHULKOSMAS C AND D BUILDING?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ANSHULKOSMAS C AND D BUILDING?

The professionals named in the filing: Architect: NITIN WAGHMARE; Engineer: G A BHILARE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ANSHULKOSMAS C AND D BUILDING?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ANSHULKOSMAS C AND D BUILDING. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ANSHULKOSMAS C AND D BUILDING to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.