Home / Browse projects / Nagpur, Maharashtra / ANJANEYA NAGAR V
ANJANEYA NAGAR V
By Shri Anjaneya Developers Pvt. Ltd.
RG-MH-22942 · RERA P50500048384 · Last updated on MahaRERA portal: 29 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 3 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ANJANEYA NAGAR V is a Plotted project by Shri Anjaneya Developers Pvt. Ltd. in Nagpur, Maharashtra, registered with MahaRERA as P50500048384 on 3 Jan 2023. Possession is promised by 31 Dec 2027. 43 of the 596 units on this registration are recorded sold or booked.
At a glance
Project
- NameANJANEYA NAGAR V
- TypePlotted
- Location
- MOUZA WARANGA PATWARI HALKA NO 41
- MOUZA WARANGA
- Waranga
- Nagpur (Rural)
- Nagpur
- 441202
- Pincode441202
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50500048384
- ReraGenie IDRG-MH-22942
Builder
- NameShri Anjaneya Developers Pvt. Ltd.
- Entity typeCompany
- Managing DirectorAnil Shyamraoji Ashtankar
- DirectorArchana Anil Ashtankar
- Other registrations3 more →
- Completed1 of 4
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on3 Jan 2023
- Promised completion31 Dec 2027
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed98 files
Current status
Figures as on 29 Apr 2026, this project's latest MahaRERA filing.
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 29 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
NA Plot Without Structure:
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 29 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 14.00 cr | Rs 7.25 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | UMESH LAMGE |
| Engineer | MAHESH BOOB |
| Engineer | ANIKET LILADHAR GHODE |
| Chartered Accountant | SUMIT R CHANDWANI |
| Chartered Accountant | ASHISH LAXMINARAYAN AGARWAL |
| Partner | Role in project |
|---|---|
| Shri Anjaneya Developers Pvt. Ltd. | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 Sep 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 10 Sep 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 10 Sep 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Sep 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed98
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 98 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Architect Certificate March 2026.pdf | 29 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate March 2026.pdf | 29 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate March 2026.pdf | 29 Apr 2026 |
| Withdrawal Update Form 1File: Architect Certificate Dec-25.pdf | 24 Jan 2026 |
| Withdrawal Update Form 2File: Engineer Certificate Dec 25.pdf | 24 Jan 2026 |
| Withdrawal Update Form 3File: CA Certificate Dec 2025.pdf | 24 Jan 2026 |
| Withdrawal Update Form 1File: Form 1 Architect certificate sept 25.pdf | 23 Oct 2025 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate Sept 25.pdf | 23 Oct 2025 |
| Withdrawal Update Form 3File: CA Certificate Anjaneya 5 Sept 25.pdf | 23 Oct 2025 |
| Form 5 (FY 2024-2025)File: Anjaneya 5 FORM 5- FY 24-25.pdf | 29 Sep 2025 |
| Form 2A (FY 2024-2025)File: Form 2A FY 24-25.pdf | 27 Sep 2025 |
| Withdrawal Update Form 1File: Architect Certificate.pdf | 24 Jul 2025 |
| Withdrawal Update Form 2File: Engineer Certificate.pdf | 24 Jul 2025 |
| Withdrawal Update Form 3File: FINAL CA CERTIFICATE JUNE 2025.pdf | 24 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Anjaneya 5 Mar25.pdf | 23 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf | 23 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 18 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold book.pdf | 18 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: final 75 Form 3 Dec24 Anjaneya Nagar V.pdf | 28 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG DEC-24 final.pdf | 25 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD DEC-24 (1)_compressed.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate Dec 24.pdf | 11 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: NEW Engineer Certificate Sept24.pdf | 24 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: NEW CA CERTIFICATE ANJANEYA 5 SEPT24.pdf | 23 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: NEW Sold-Unsold Sept24_compressed.pdf | 23 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERTIFICATE LAMGE SEPT 2024.pdf | 18 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QAC 2023.pdf | 11 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QAC 2024.pdf | 11 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 ANJANEYA 5.pdf | 7 Oct 2024 |
| Form 5 (FY 2022-2023)File: FORM 5 22-23.pdf | 30 Sep 2024 |
| Form 5 (FY 2023-2024)File: Form 5 ANJANEYA 5.pdf | 30 Sep 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate june_24 edited.pdf | 12 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 148 Final CA CERTIFICATE June24 Anjaneya Nagar V.pdf | 12 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERT JUNE 24.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory June-2024_organized (1)_organized_compressed.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ANJANEYA NAGAR-V CA CERT (MAR 24).pdf | 20 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer Certificate (MARCH 2024)_compressed.pdf | 13 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD BOOKED INVENTORY(MARCH 2024)_compressed.pdf | 13 Apr 2024 |
| Declaration about Commencement CertificateFile: FORM D(MARCH 2024).pdf | 3 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate (MARCH 2024).pdf | 3 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engr Certificate Dec 2023.pdf | 10 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Anjaneya Nagar V Nagpur Dec 23.pdf | 10 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FInal Form no1 Arch Dec23.pdf | 7 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FInal FOrm2 June23.pdf | 7 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Final FOrm 2 Sep23.pdf | 7 Feb 2024 |
| Declaration about Commencement CertificateFile: Declaration Dec23.pdf | 24 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form no1 Arch Dec23.pdf | 24 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 june-23.pdf | 24 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 sept-23.pdf | 24 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Dec-23_compressed.pdf | 24 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Signed Form5 AnjaneyaV Mar23.pdf | 2 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer certificate sept 23.pdf | 23 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Sept 2023.pdf | 23 Nov 2023 |
| Declaration about Commencement CertificateFile: form D sept-23.pdf | 20 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERT SEPT-23.pdf | 20 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: sold unsold details sept-23.pdf | 20 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 march.pdf | 27 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 june.pdf | 27 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - March.pdf | 27 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - June.pdf | 27 Sep 2023 |
| Declaration about Commencement CertificateFile: 4 Form D - Anjaneya Nagar V - March 23.pdf | 26 Sep 2023 |
| Declaration about Commencement CertificateFile: 4 Form D - Anjaneya Nagar V - June 23.pdf | 26 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 March 23 - Anjaneya Nagar V.pdf | 26 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 June 23 - Anjaneya Nagar V.pdf | 26 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: sold booked mar.pdf | 26 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: sold booked jun.pdf | 26 Sep 2023 |
| Other - LegalFile: WARANGA TITLE REPORT_compressed_compressed (2)_compressed.pdf | 21 Dec 2022 |
| Other - LegalFile: SALE DEED 127-1(1).pdf | 23 Nov 2022 |
| Other - LegalFile: SALE DEED 127-1(2).pdf | 23 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE 1.pdf | 17 Sep 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE 2.pdf | 17 Sep 2022 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf | 17 Sep 2022 |
| Proforma of Agreement for saleFile: ALLOTMENT LETTER.pdf | 17 Sep 2022 |
| Deviation Report with respect to Allotment letterFile: DEVIATION ALLOTMENT LETTER.pdf | 17 Sep 2022 |
| Deviation Report with respect to model copy of AgreementFile: DEVIATION AFS.pdf | 17 Sep 2022 |
| Proforma of Agreement for saleFile: AGREEMENT TO SELL.pdf | 16 Sep 2022 |
| Proforma of Allotment letterFile: AGREEMENT TO SELL.pdf | 16 Sep 2022 |
| Other - LegalFile: SALE DEED 118 AND 135(1).pdf | 14 Sep 2022 |
| Other - LegalFile: SALE DEED 118 AND 135(2).pdf | 14 Sep 2022 |
| Copy of the legal title reportFile: title report.pdf | 12 Sep 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 98 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ANJANEYA NAGAR V on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MOUZA WARANGA2,800+ in Nagpur
Filed coordinates, straight-line distance. 4 registered projects within 2 km.
UNIQUEVISHWA WARANGA
GANPATI BUILDERS AND DEVELOPERS
BAMBOO FARM VILLA
S R INFRA
KRUSHNA BUILDCOM
AJIT KRUSHNAJI UGALE
Shree Krishna nagri 01
Sarita Ravindra Ghodeswar
NAVKAR INDUSTRIAL AND LOGISTIC PARK - II
SHRI RAMESH BHAGIRATH RANDER AND OTHERS
Shree Sai Nagari 03
Sarita Ravindra Ghodeswar
See every Nagpur project, with the district possession charts
Builder: Shri Anjaneya Developers Pvt. Ltd.
Shri Anjaneya Developers Pvt. Ltd. has 4 registrations on MahaRERA, including Anjaneya Vatika and ANJANEYA NAGAR. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What are my rights if ANJANEYA NAGAR V is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ANJANEYA NAGAR V?
The registered promoter entity is Shri Anjaneya Developers Pvt. Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ANJANEYA NAGAR V?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for ANJANEYA NAGAR V?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ANJANEYA NAGAR V?
The professionals named in the filing: Architect: UMESH LAMGE; Engineer: MAHESH BOOB; Engineer: ANIKET LILADHAR GHODE; Chartered Accountant: SUMIT R CHANDWANI; Chartered Accountant: ASHISH LAXMINARAYAN AGARWAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ANJANEYA NAGAR V?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback