Home / Browse projects / Pune, Maharashtra / Amrutdhara A building

Completed No litigation declared Others project

Amrutdhara A building

By Lunkad Gruh Nirman Company

RG-MH-12858 · RERA P52100021533 · Last updated on MahaRERA portal: 1 Aug 2024

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 4 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2022Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Stilt Floor, 0%
0Complaints at MahaRERAon this registration
Jump to the 44 documents Report an error

Amrutdhara A building is a Others project by Lunkad Gruh Nirman Company in Pune, Maharashtra, registered with MahaRERA as P52100021533 on 8 Jul 2019. The registration is recorded completed; possession was promised by 30 Dec 2022.

At a glance

Project

  • NameAmrutdhara A building
  • TypeOthers
  • Location
    • Alandi Road
    • Sai Mandir Wadmukhwadi
    • CHARHOLI
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100021533
  • ReraGenie IDRG-MH-12858

Builder

  • NameLunkad Gruh Nirman Company
  • Entity typePartnership
  • PartnersSANJAY DHANRAJ GATAGAT, NAVIN RAMESH KHIVANSARA
  • Other registrations4 more →
  • Completed5 of 5
  • Declared earlier projects1 →

Key dates

this monthRegisteredJul 2019PromisedDec 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on8 Jul 2019
  • Promised completion30 Dec 2022
  • Revised completionNone
  • Buildings1 building record
  • Documents filed44 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Amrutdhara A buildingNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 Aug 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 0%.

Amrutdhara A building: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 1 Aug 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed62

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots62
Closed/Covered44
Open Space18

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,004 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI5564.34
Proposed, not sanctioned4,764 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDANGE CHOWK,THERGOAN PUNE 411033

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRajendra Khire
PartnerRole in project
Lunkad Gruh Nirman Company-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Jun 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Jun 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Jun 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Jun 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 15 Mar 2022

Documents filed44

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Home Buyer /Allottee Grievance Redressal CellFile: 123.pdf1 Aug 2024
Other - TechnicalFile: A wing 123 commercial parking.pdf12 Sep 2023
Certificates of CA (Form 3)File: Amrutdhara A bldg (1).pdf27 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 A Anrutdhara A wing march 22.pdf3 Apr 2023
Status of ConveyanceFile: Amrutdhara Conveyance.pdf18 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Amrutdhara (1).pdf12 Oct 2022
Architect’s Certificate on Completion of Project (Form 4)File: Amrutdhara form 4.pdf29 Jul 2022
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf2 May 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: AMRUTDHARA FINAL COMPLETION.pdf15 Mar 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: SOCIETY 123.pdf20 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 dEC 21.pdf7 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ( 2 ) A dEC 21.pdf7 Jan 2022
Certificates of CA (Form 3)File: fORM 3 Dec 21 Amrutdhara A Building.pdf7 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form - 5 - A Build 21.pdf12 Oct 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: AMRUTDHARA COMPLETION A.PDF8 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2 A (sEP 21) - Copy.pdf25 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 AUG 21.pdf26 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ( 2 ) A Aug 21.pdf26 Aug 2021
Certificates of CA (Form 3)File: Form 3 - A Aug 21.PDF26 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - A Bld-1920.pdf12 Aug 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: 123 SOCIETY.pdf22 Jun 2021
Disclosure of sold/ booked inventoryFile: Amrutdhara_ DISCLOSURE OF SOLD BOOKED INVENTORY.pdf1 Jun 2021
Form 2AFile: form 2 A (june 21).pdf22 May 2021
Form 2AFile: QAC FORM 2A March 2021.pdf23 Mar 2021
Form 2AFile: QAC dEC 2020FORM 2A RERA FORMATE for A 123.pdf30 Dec 2020
Form 2AFile: form 2 A (sep 20 ).pdf22 Sep 2020
Proforma of Allotment letterFile: New Draft Agreement AMRUTDHARA.pdf8 Sep 2020
Form 2AFile: March QAC FORM 2A RERA FORMATE for A 123 Mar 2020.pdf1 Jul 2020
Form 2AFile: FORM 2 A 123 A WING DEC 2019.pdf24 Feb 2020
Form 2AFile: QAC FORM 2A RERA FORMATE for A 123 dec 2019.pdf20 Jan 2020
Certificates of CA (Form 3)File: LGNC Form 3 A Building - 010519 (2 files merged).pdf2 Jul 2019
Copy of the legal title reportFile: title Certificate.PDF21 Jun 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect Cerififcate 123 (1).pdf19 Jun 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ( 1 )A.pdf19 Jun 2019
Form 2AFile: QAC FORM 2A RERA FORMATE for A 123.pdf19 Jun 2019
Proforma of Allotment letterFile: AMRUTDHARA ALLOTMENT LETTER (1) (2 files merged).pdf19 Jun 2019
Layout approvalFile: layout (1).pdf13 Jun 2019
Building plan approvalFile: even and odd floor plan (1).pdf13 Jun 2019
PAN CardFile: PAN CARD LGNC.pdf13 Jun 2019
Details of encumbrancesFile: Non encumbrances.pdf13 Jun 2019
Copy of Layout Approval (in case of layout)File: layout (1).pdf13 Jun 2019
Building Plan Approval (IOD)File: even and odd floor plan (1).pdf13 Jun 2019
Commencement Certificates / NA Order for plotted developmentFile: Commecement Certificate.pdf13 Jun 2019
Declaration in FORM BFile: Form B.pdf13 Jun 2019

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Amrutdhara A building on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Sai Mandir Wadmukhwadi13,700+ in Pune

2 kmAmrutdhara A buildingCompleted 116Lapsed / revoked 117Other 37Dot size: filed unitsN

Filed coordinates, straight-line distance. 270 registered projects within 2 km.

Builder: Lunkad Gruh Nirman Company

Lunkad Gruh Nirman Company has 5 registrations on MahaRERA, including Amrutdhara C and D1-D2 and AMRUTDHARA B BUILDING. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Amrutdhara A building is delayed beyond 30 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Amrutdhara A building?

The registered promoter entity is Lunkad Gruh Nirman Company, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Amrutdhara A building?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Amrutdhara A building?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Amrutdhara A building?

The professionals named in the filing: Architect: Rajendra Khire. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Amrutdhara A building?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Amrutdhara A building. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Amrutdhara A building to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.