ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / AMPLE LOTUS

Registration approved No litigation declared Residential/Group Housing project

AMPLE LOTUS

By AMPLE INFRA

RG-KA-01292 · RERA PRM/KA/RERA/1251/310/PR/160726/008814 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
May 2029Possession promisedno revision filed
3 of 16Construction stages donefurthest along: Sub-structure flooring (Parking Floor, 50%
56 of 56Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 68 documents Report an error

AMPLE LOTUS is a Residential/Group Housing project by AMPLE INFRA in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/160726/008814 on 16 Jul 2026. Possession is promised by 31 May 2029. 0 of the 56 units on this registration are recorded sold or booked, and 3 of 16 construction stages are filed complete.

At a glance

Project

  • NameAMPLE LOTUS
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560068
  • Pincode560068
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/160726/008814
  • ReraGenie IDRG-KA-01292

Builder

  • NameAMPLE INFRA
  • Entity typePartnership Firm
  • GSTIN29ACEFA5428Q1ZT
  • Authorized SignatoryR Bhuvanewari

Key dates

this monthRegisteredJul 2026PromisedMay 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on16 Jul 2026
  • Promised completion31 May 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed68 files

Current status

0%0 of 56 units booked
14.2%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AMPLE LOTUS---56056

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 16 construction stages are filed complete. The stage furthest along is Sub-structure flooring (Parking Floor, at 50%.

Building: 25% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)50%
Retaining wall (All types)0%
RCC or MS Framed structure25%
Masonry Construction15%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing10%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes15%
Sewage and Drainage SystemYes15%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes10%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingYes0%
ElectricityYes10%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes10%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationYes15%
Air ConditioningNoNot applicable
StaircasesYes10%
LiftsYes10%
Corridor/LobbiesYes10%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementNoNot applicable
TerraceYes0%
Outer WallYes0%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,034 sq m
Named landowners1
LandownerVillageDistrict
N Ramachandra Reddy--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 26.39 cr
Cost incurredRs 3.74 cr
Spent of the estimate14.16%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 23.89 crRs 3.37 cr
On-site expenditure-Consultants FeesRs 1.00 crRs 5.19 lakh
On-site expenditure-Site OverheadRs 75.00 lakhRs 20.35 lakh
On-site expenditure-Salaries of workersRs 50.00 lakhRs 4.22 lakh
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 25.00 lakhRs 7.04 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDISHA K N
EngineerARUN KUMAR S R
Chartered AccountantR Sambasiva Naidu

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed68

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/160726/008814 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: AMPLE LOTUS FORM-4 Q2 26-27.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: AMPLE LOTUS-FORM-5 Q2 26-27.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: AMPLE LOTUS-FORM-6 Q2 26-27.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Bank 100%, 70%, and 30% account LETTER From SBI, the bank account namesFile: BANK ACCOUNTS AMPLE LOTUS.pdf8 Jul 2026
chartered accountant certificate (CA) in prescribed format form -01. (3 bank accounts)File: AMPLE INFRA- FORM 1.pdf8 Jul 2026
bank affidavit in the prescribed format . (3 bank accounts as per bank Letter)File: BANK AFFIDAVIT AMPLE LOTUS.pdf8 Jul 2026
Loan amount should be deposited into RERA designated account as per notification dated 19/07/2025File: Loan Amount Clarification.pdf8 Jul 2026
chartered accountant COP ( Certificate of practice) Self attestedFile: CA Sambasivanaidu COP.pdf8 Jul 2026
sources of funds to complete the projectFile: AMPLE INFRA- FORM 1.pdf8 Jul 2026
profit and loss account and balance sheet for 2022-23, 2023-24 and 2024-25 clarificationFile: Financial statements Clarification.pdf8 Jul 2026
Single Plot layout/Development plan Approved by the competent authorityFile: Single Plot Map AMPLE LOtus.pdf8 Jul 2026
Single Plot layout/Development plan order Approved by the competent authorityFile: Single Plot approval Order Copy.pdf8 Jul 2026
Building License from Local Authority Original CopyFile: BUILDING LICENSE.pdf8 Jul 2026
Survey sketch Certifying the Boundary of the Proposed land-Original survey sketchFile: Survey Sketch Ample Lotus F.pdf8 Jul 2026
original sanctioned drawings, floor plan, sectional drawings and elevation digitally signed copysFile: PLAN PRJ_5422_25-26.pdf8 Jul 2026
commencement certificate ClarificationFile: Commencement Certificate Clarification.pdf8 Jul 2026
Demarcation of proposed land in Approved Master plan Certified by the competent authorityFile: MASTER PLAN CDP SITE MARKED.pdf8 Jul 2026
Demarcation of proposed land in original Village map certified by the competent authorityFile: VILLAGE MAP SITE MARKED.pdf8 Jul 2026
Approval/NOC under section 14 of the KTCP Act clarificationFile: NOC Under Section 14 of KTCP Act.pdf8 Jul 2026
Details of amenities and facilities provided as per plan.File: Project Amenities and Facilities Declaration.pdf8 Jul 2026
Brochure of the project with amenities detailsFile: AMPLE INFRA- PROJECT SPECIFICATIONS.pdf8 Jul 2026
amenities declarationFile: Project Amenities and Facilities Declaration.pdf8 Jul 2026
Engineer license certificate, issued by the local Development AuthorityFile: Engineer ARUN KUMAR ReG Cert.pdf8 Jul 2026
all pages of BESCOM NOCFile: NOC BESCOM AL f.pdf8 Jul 2026
Land cost calculation sheet as per the guidance value (Self-attested copy)File: GUIDELINE VALUE CALCULATION Attested.pdf8 Jul 2026
STP design drawing certified by the Engineer Clarification as per GO NotificationFile: STP Installation Explanation with Exemption Guidelines.pdf8 Jul 2026
RTC, survey 111/2-
Mutation, survey 111/2-
Encumbrance Certificate, survey 111/2-
Conversion/Alienation Order, survey 111/2-
Sale/Title/Gift Deed, survey 111/2-
JDA, survey 111/2-
Khatha, survey 111/2-
Registration CertificateFile: Certificate of Registration of Firm.pdf-
GST CertificateFile: Ample Infra GST Registration Certificate.pdf-
Partnership DeedFile: Reconstitution of Partnership Deed.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: AMPLE INFRA- FORM 1.pdf-
Certificate issued by Architect Form 2File: AMPLE INFRA-FORM 2.pdf-
Certificate issued by Engineer Form 3File: Ample Infra Engineer Certificate With SealSignature.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: NON LITIGATION Affidavit.pdf-
BUILDING LICENSE-
PLAN PRJ_5422_25-26-
PLAN PRJ_5422_25-26-
AMPLE INFRA- STABILITY CERTIFICATE-
AMPLE INFRA- PROJECT SPECIFICATIONS-
PLAN PRJ_5422_25-26-
Agreement for Sale-
Allotment Letter-
FORM-B Affidavit-
NON VIOLATION Affidavit-
JDA Affidavit-
Legal opinion-
Bescom NOC-
Water NOC-
Pollution Control Board NOC-
COST ESTIMATION AMPLE LOTUS-

How this compares with Bengaluru Urban

0%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep AMPLE LOTUS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmAMPLE LOTUSOther 20Dot size: filed unitsN

Filed coordinates, straight-line distance. 20 registered projects within 2 km.

Builder: AMPLE INFRA

AMPLE INFRA has 1 registration on RERA Karnataka, including AMPLE LOTUS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if AMPLE LOTUS is delayed beyond 31 May 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of AMPLE LOTUS?

The registered promoter entity is AMPLE INFRA, a partnership firm as per the filing. Its GSTIN 29ACEFA5428Q1ZT can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in AMPLE LOTUS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AMPLE LOTUS?

The professionals named in the filing: Architect: DISHA K N; Engineer: ARUN KUMAR S R; Chartered Accountant: R Sambasiva Naidu. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AMPLE LOTUS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AMPLE LOTUS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AMPLE LOTUS to a free account