Home / Browse projects / Bengaluru Urban, Karnataka / AMPLE LOTUS
AMPLE LOTUS
By AMPLE INFRA
RG-KA-01292 · RERA PRM/KA/RERA/1251/310/PR/160726/008814 · Last updated on RERA Karnataka portal: 14 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
AMPLE LOTUS is a Residential/Group Housing project by AMPLE INFRA in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/160726/008814 on 16 Jul 2026. Possession is promised by 31 May 2029. 0 of the 56 units on this registration are recorded sold or booked, and 3 of 16 construction stages are filed complete.
At a glance
Project
- NameAMPLE LOTUS
- TypeResidential/Group Housing
- Location
- Bengaluru South
- Bengaluru Urban
- 560068
- Pincode560068
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/310/PR/160726/008814
- ReraGenie IDRG-KA-01292
Builder
- NameAMPLE INFRA
- Entity typePartnership Firm
- GSTIN29ACEFA5428Q1ZT
- Authorized SignatoryR Bhuvanewari
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on16 Jul 2026
- Promised completion31 May 2029
- Revised completionNone
- Buildings1 building record
- Documents filed68 files
Current status
Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| AMPLE LOTUS | - | - | - | 56 | 0 | 56 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 16 construction stages are filed complete. The stage furthest along is Sub-structure flooring (Parking Floor, at 50%.
Building: 25% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 50% |
| Retaining wall (All types) | 0% |
| RCC or MS Framed structure | 25% |
| Masonry Construction | 15% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 10% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 15% |
| Sewage and Drainage System | Yes | 15% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Solid waste management and disposal | Yes | 10% |
| Emergency Evacuation services | Yes | 0% |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | Yes | 0% |
| Sewage Treatment Plant (STP) | No | Not applicable |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 10% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 10% |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | No | Not applicable |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 15% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 10% |
| Lifts | Yes | 10% |
| Corridor/Lobbies | Yes | 10% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 0% |
| Basement | No | Not applicable |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 0% |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| N Ramachandra Reddy | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 23.89 cr | Rs 3.37 cr |
| On-site expenditure-Consultants Fees | Rs 1.00 cr | Rs 5.19 lakh |
| On-site expenditure-Site Overhead | Rs 75.00 lakh | Rs 20.35 lakh |
| On-site expenditure-Salaries of workers | Rs 50.00 lakh | Rs 4.22 lakh |
| On-site expenditure-Cost Of Services(Water, Electricity, Sewage) | Rs 25.00 lakh | Rs 7.04 lakh |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DISHA K N |
| Engineer | ARUN KUMAR S R |
| Chartered Accountant | R Sambasiva Naidu |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed68
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/160726/008814 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: AMPLE LOTUS FORM-4 Q2 26-27.pdf | 14 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: AMPLE LOTUS-FORM-5 Q2 26-27.pdf | 14 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: AMPLE LOTUS-FORM-6 Q2 26-27.pdf | 14 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 14 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 14 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 14 Oct 2026 |
| Bank 100%, 70%, and 30% account LETTER From SBI, the bank account namesFile: BANK ACCOUNTS AMPLE LOTUS.pdf | 8 Jul 2026 |
| chartered accountant certificate (CA) in prescribed format form -01. (3 bank accounts)File: AMPLE INFRA- FORM 1.pdf | 8 Jul 2026 |
| bank affidavit in the prescribed format . (3 bank accounts as per bank Letter)File: BANK AFFIDAVIT AMPLE LOTUS.pdf | 8 Jul 2026 |
| Loan amount should be deposited into RERA designated account as per notification dated 19/07/2025File: Loan Amount Clarification.pdf | 8 Jul 2026 |
| chartered accountant COP ( Certificate of practice) Self attestedFile: CA Sambasivanaidu COP.pdf | 8 Jul 2026 |
| sources of funds to complete the projectFile: AMPLE INFRA- FORM 1.pdf | 8 Jul 2026 |
| profit and loss account and balance sheet for 2022-23, 2023-24 and 2024-25 clarificationFile: Financial statements Clarification.pdf | 8 Jul 2026 |
| Single Plot layout/Development plan Approved by the competent authorityFile: Single Plot Map AMPLE LOtus.pdf | 8 Jul 2026 |
| Single Plot layout/Development plan order Approved by the competent authorityFile: Single Plot approval Order Copy.pdf | 8 Jul 2026 |
| Building License from Local Authority Original CopyFile: BUILDING LICENSE.pdf | 8 Jul 2026 |
| Survey sketch Certifying the Boundary of the Proposed land-Original survey sketchFile: Survey Sketch Ample Lotus F.pdf | 8 Jul 2026 |
| original sanctioned drawings, floor plan, sectional drawings and elevation digitally signed copysFile: PLAN PRJ_5422_25-26.pdf | 8 Jul 2026 |
| commencement certificate ClarificationFile: Commencement Certificate Clarification.pdf | 8 Jul 2026 |
| Demarcation of proposed land in Approved Master plan Certified by the competent authorityFile: MASTER PLAN CDP SITE MARKED.pdf | 8 Jul 2026 |
| Demarcation of proposed land in original Village map certified by the competent authorityFile: VILLAGE MAP SITE MARKED.pdf | 8 Jul 2026 |
| Approval/NOC under section 14 of the KTCP Act clarificationFile: NOC Under Section 14 of KTCP Act.pdf | 8 Jul 2026 |
| Details of amenities and facilities provided as per plan.File: Project Amenities and Facilities Declaration.pdf | 8 Jul 2026 |
| Brochure of the project with amenities detailsFile: AMPLE INFRA- PROJECT SPECIFICATIONS.pdf | 8 Jul 2026 |
| amenities declarationFile: Project Amenities and Facilities Declaration.pdf | 8 Jul 2026 |
| Engineer license certificate, issued by the local Development AuthorityFile: Engineer ARUN KUMAR ReG Cert.pdf | 8 Jul 2026 |
| all pages of BESCOM NOCFile: NOC BESCOM AL f.pdf | 8 Jul 2026 |
| Land cost calculation sheet as per the guidance value (Self-attested copy)File: GUIDELINE VALUE CALCULATION Attested.pdf | 8 Jul 2026 |
| STP design drawing certified by the Engineer Clarification as per GO NotificationFile: STP Installation Explanation with Exemption Guidelines.pdf | 8 Jul 2026 |
| RTC, survey 111/2 | - |
| Mutation, survey 111/2 | - |
| Encumbrance Certificate, survey 111/2 | - |
| Conversion/Alienation Order, survey 111/2 | - |
| Sale/Title/Gift Deed, survey 111/2 | - |
| JDA, survey 111/2 | - |
| Khatha, survey 111/2 | - |
| Registration CertificateFile: Certificate of Registration of Firm.pdf | - |
| GST CertificateFile: Ample Infra GST Registration Certificate.pdf | - |
| Partnership DeedFile: Reconstitution of Partnership Deed.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: AMPLE INFRA- FORM 1.pdf | - |
| Certificate issued by Architect Form 2File: AMPLE INFRA-FORM 2.pdf | - |
| Certificate issued by Engineer Form 3File: Ample Infra Engineer Certificate With SealSignature.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: NON LITIGATION Affidavit.pdf | - |
| BUILDING LICENSE | - |
| PLAN PRJ_5422_25-26 | - |
| PLAN PRJ_5422_25-26 | - |
| AMPLE INFRA- STABILITY CERTIFICATE | - |
| AMPLE INFRA- PROJECT SPECIFICATIONS | - |
| PLAN PRJ_5422_25-26 | - |
| Agreement for Sale | - |
| Allotment Letter | - |
| FORM-B Affidavit | - |
| NON VIOLATION Affidavit | - |
| JDA Affidavit | - |
| Legal opinion | - |
| Bescom NOC | - |
| Water NOC | - |
| Pollution Control Board NOC | - |
| COST ESTIMATION AMPLE LOTUS | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep AMPLE LOTUS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 20 registered projects within 2 km.
MEMCO SKYLINE - JUTAKU
MEMCO SKYLINE PRIVATE LIMITED
SNN RAJ SERENITY
SNN Builders Private Limited
TVS Emerald Jardin
Emerald Haven Development Limited
CASAGRAND AMOR
CASA GRANDE GARDEN CITY BUILDERS PVT LTD
Assetz Mizumi Reserve Tower A1 A2 A4
APG COMMUNITY DEVELOPMENT PRIVATE LIMITED
Assetz Canvas & Cove 2.0 - Block B & C
APG HABITAT PRIVATE LIMITED
See every Bengaluru Urban project, with the district possession charts
Builder: AMPLE INFRA
AMPLE INFRA has 1 registration on RERA Karnataka, including AMPLE LOTUS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if AMPLE LOTUS is delayed beyond 31 May 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of AMPLE LOTUS?
The registered promoter entity is AMPLE INFRA, a partnership firm as per the filing. Its GSTIN 29ACEFA5428Q1ZT can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in AMPLE LOTUS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at AMPLE LOTUS?
The professionals named in the filing: Architect: DISHA K N; Engineer: ARUN KUMAR S R; Chartered Accountant: R Sambasiva Naidu. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AMPLE LOTUS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback