Home / Browse projects / Dakshina Kannada, Karnataka / AMITY

Registration approved No litigation declared Residential/Group Housing project

AMITY

By MOHTISHAM COMPLEXES PVT LTD

RG-KA-61165 · RERA PRM/KA/RERA/1257/334/PR/230522/004895 · Last updated on RERA Karnataka portal: 16 Mar 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Feb 2026Possession promisedmoved 12 months from the original
16 of 16Construction stages doneevery applicable stage filed complete
19 of 107Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 191 documents Report an error

AMITY is a Residential/Group Housing project by MOHTISHAM COMPLEXES PVT LTD in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/230522/004895 on 23 May 2022. Possession is promised by 28 Feb 2026. The completion date has moved by 12 months from the original filing. 88 of the 107 units on this registration are recorded sold or booked, and 16 of 16 construction stages are filed complete.

At a glance

Project

  • NameAMITY
  • TypeResidential/Group Housing
  • Location
    • Mangalore
    • Dakshina Kannada
    • 575001
  • Pincode575001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/230522/004895
  • ReraGenie IDRG-KA-61165

Builder

  • NameMOHTISHAM COMPLEXES PVT LTD
  • Entity typeCompany
  • GSTIN29AABCM3814A1ZX
  • Authorized SignatorySYED MOHAMMED ARSHAD
  • MdSYED MOHAMMED ARSHAD
  • DirectorsSYED MOHAMMED ARSHAD, SYED MOHAMMED SAWOOD
  • Project HeadPRAVEEN KUMAR
  • Other registrations1 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredMay 2022First promiseFeb 2025Revised toFeb 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on23 May 2022
  • Promised completion28 Feb 2026
  • Revised completionRevised to 28 Feb 2026 (originally 28 Feb 2025)
  • Buildings1 building record
  • Documents filed191 files

Current status

82%88 of 107 units booked
91.9%Of the estimated cost spent so far

Figures as on 16 Mar 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AMITY---1070107

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 16 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 16 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities33

As on 16 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Solid waste management and disposalYes100%
Emergency Evacuation servicesYes100%
Internal Roads & FootpathsYes100%
Electricity supply transformer and substationYes100%
Storm water drainsYes100%
Use of renewable energyYes100%
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes100%
Street LightingYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseYes100%
Community HallNoNot applicable
Outdoor Sports facilityYes100%
Indoor Sports facilityYes100%
Swimming PoolYes100%
GymYes100%
ParksYes100%
Power BackupYes100%
Piped GasYes100%
Water and SanitationYes100%
Air ConditioningYes0%
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesYes100%
Common entrance and exit for the building/common portico/foyer/verandahYes100%

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,816 sq m
Named landowners1
LandownerVillageDistrict
MOHTISHAM COMPLEXES PVT LTD--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 48.00 cr
Cost incurredRs 44.11 cr
Spent of the estimate91.89%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 45.80 crRs 32.71 cr
On-site expenditure-Consultants FeesRs 90.00 lakhRs 1.58 cr
Payment of feesRs 50.00 lakh-
On-site expenditure-Salaries of workersRs 30.00 lakhRs 12.97 lakh
On-site expenditure-Site OverheadRs 25.00 lakh-
Payment of cessRs 20.00 lakh-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 5.00 lakhRs 3.47 cr
Payment of taxes-Rs 91.77 lakh
Payment of charges-Rs 3.11 cr
Principal sum and interest payable to financial institutions-Scheduled Banks-Rs 2.19 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDHARMARAJ ASSOCIATES
EngineerN MANOHAR
Chartered AccountantR KRISHNAN

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1257/334/PR/260428/004895Feb 2025 → Feb 2026

Reason as filed by the promoterAwaiting Approvals

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed191

As listed on the registration, under the names the promoter filed them with; the newest 80 of 191 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/230522/004895 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA CERTIFICATE.pdf16 Mar 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Amity Architecture Certificate.pdf16 Mar 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: AMITY - FORM 6.pdf16 Mar 2026
Q3 2025-26 Water supply and sewage board16 Mar 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)16 Mar 2026
Q3 2025-26 KPTCL- BESCOM16 Mar 2026
Q3 2025-26 Fire and Safety16 Mar 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA CERTIFICATE.pdf16 Mar 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Amity Architecture Certificate.pdf16 Mar 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: AMITY - FORM 6.pdf16 Mar 2026
Q4 2025-26 Water supply and sewage board16 Mar 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)16 Mar 2026
Q4 2025-26 KPTCL- BESCOM16 Mar 2026
Q4 2025-26 Fire and Safety16 Mar 2026
CANOPY OCCUPANCY CERTIFICATEFile: CANOPY OCCUPANCY CERTIFICATE.pdf29 Apr 2022
FERNHILL OCCUPANCY CERTIFICATEFile: FERNHILL OCCUPANCY CERTIFICATE.pdf29 Apr 2022
SALE AGREEMENT FORMATFile: SALE AGREEMENT RERA FORMAT AMITY.pdf29 Apr 2022
SCHEDULE AFile: SCHEDULE 'A'.pdf29 Apr 2022
SCHEDULE BFile: SCHEDULE 'B'.pdf29 Apr 2022
SCHEDULE B1File: SCHEDULE 'B1'.pdf29 Apr 2022
SCHEDULE CFile: SCHEDULE 'C'.pdf29 Apr 2022
ATTACHEMENT A TO SCHEDULE CFile: Attchement 'A' to schedule - C.pdf29 Apr 2022
SCHEDULE DFile: SCHEDULE 'D'.pdf29 Apr 2022
SCHEDULE EFile: SCHEDULE 'E'.pdf29 Apr 2022
SCHEDULE FFile: SCHEDULE 'F'.pdf29 Apr 2022
SCHEDULE GFile: SCHEDULE 'G'.pdf29 Apr 2022
SCHEDULE HFile: SCHEDULE 'H'.pdf29 Apr 2022
SCHEDULE IFile: SCHEDULE 'I'.pdf29 Apr 2022
SCHEDULE JFile: SCHEDULE 'J'.pdf29 Apr 2022
SCHEDULE KFile: SCHEDULE 'K'.pdf29 Apr 2022
SCHEDULE LFile: SCHEDULE 'L'.pdf29 Apr 2022
SCHEDULE MFile: SCHEDULE 'M'.pdf29 Apr 2022
SCHEDULE NFile: SCHEDULE 'N'.pdf29 Apr 2022
SCHEDULE OFile: SCHEDULE 'O'.pdf29 Apr 2022
SCHEDULE PFile: SCHEDULE 'P'.pdf29 Apr 2022
CANOPY COMPLETION CERTIFICATEFile: 1 CANOPY COMPLETION CERTIFICATE DATEED 19122020.pdf19 Mar 2022
CANOPY KSPCB CFO DATED 09122020File: 2 CANOPY KSPCB CFO DATED 09122020.pdf19 Mar 2022
CANOPY FIRE CLEARANCE CERTIFICATE REIVSED DATE 29102020File: 3 CANOPY FIRE CLEARANCE CERTIFICATE REIVSED DATE 29102020.pdf19 Mar 2022
CANOPY POWER SANCTION PERMANENTFile: 4 CANOPY POWER SANCTION PERMANENT.pdf19 Mar 2022
CANOPY WATER CONNECTION ISSUED BY MCC DATED 15032021File: 5 CANOPY WATER CONNECTION ISSUED BY MCC DATED 15032021.pdf19 Mar 2022
CANOPY AFFIDAVITFile: 6 CANOPY AFFIDAVIT.pdf19 Mar 2022
CANOPY ENGINEERS CERTIFICATEFile: 7 CANOPY ENGINEERS CERTIFICATE.pdf19 Mar 2022
CANOPY ARCHITECTS CERTIFICATEFile: 8 CANOPY ARCHITECT'S CERTIFICATE.pdf19 Mar 2022
CANOPY CA CERTIFICATEFile: 9 CANOPY -Form 4CC.pdf19 Mar 2022
FERNHILL COMPLETION CERTIFICATEFile: 10 FERNHILL COMPLETION CERTIFICATE DATED 12012021.pdf19 Mar 2022
FERNHILL KSPCB CFO DATED 04122020File: 11 FERNHILL CFO from KSPCB dated 04122020.pdf19 Mar 2022
FERNHILL FIRE CLEARANCE CERTIFICATE REIVSED DATE 17122020File: 12 FERNHILL FIRE CLEARANCE CERTIFICATE dated 17122020.pdf19 Mar 2022
FERNHILL POWER SANCTION PERMANENTFile: 13 FERNHILL POWER SANCTION PERMANENT.pdf19 Mar 2022
FERNHILL WATER SANCTION PERMANENTFile: 14 FERNHILL PERMANENT WATER CONNECTION.pdf19 Mar 2022
FERNHILL WATER SANCTION PERMANENTFile: 15 FERNHILL PERMANENT WATER CONNECTION 2.pdf19 Mar 2022
CANOPY AFFIDAVITFile: 16 FERNHILL AFFIDAVIT.pdf19 Mar 2022
FERNHILL ENGINEERS CERTIFICATEFile: 17 ENGINEERS CERTIFICATE FERNHILL.pdf19 Mar 2022
FERNHILL ARCHITECTS CERTIFICATEFile: 18 FERNHILL ARCHITECT'S CERTIFICATE.pdf19 Mar 2022
FERNHILL CA CERTIFICATEFile: 19 FERNHILL FORM 4CC.pdf19 Mar 2022
CANOPY FORM 4File: 20 Canopy FORM 4 CA CERTIFICATE.pdf19 Mar 2022
FERNHILL FORM 4File: 21 FERNHILL FORM 4 CA CERTIFICATE.pdf19 Mar 2022
CANOPY SCREENSHOTSFile: 22 SCREENSHOT CANOPY.pdf19 Mar 2022
FERNHILL SCREENSHOTSFile: 23 FERNHILL SCREENSHOTS.pdf19 Mar 2022
TEMPORARY ELECTRICITY BILLFile: Amity Apartment 140422.pdf17 Feb 2022
TEMPERORARY CONNECTION LETTERFile: MESCOM LETTER.pdf17 Feb 2022
Mangalore ZRFile: Mangalore ZR.pdf17 Feb 2022
RERA BANK ACCOUNTFile: RERA BANK ACCOUNT.pdf3 Feb 2022
NON LITIGATION AFFIDAVITFile: NON LITIGATION AFFIDAVIT.pdf3 Feb 2022
FORM BFile: FORM B.pdf3 Feb 2022
DRAFT AOSFile: SALE AGREEMENT DRAFT.pdf3 Feb 2022
SCHEDUE AFile: SCHEDULE A.pdf3 Feb 2022
SCHEDULE BFile: SCHEDULE B floor plan sample.pdf3 Feb 2022
SCHEDULE BAFile: SCHEDULE BA parking plan sample.pdf3 Feb 2022
SCHEDULE CFile: SCHEDULE C.pdf3 Feb 2022
SCHEDULE DFile: SCHEDULE D.pdf3 Feb 2022
SCHEDULE EFile: SCHEDULE E.pdf3 Feb 2022
SCHEDULE FFile: SCHEDULE F.pdf3 Feb 2022
SCHEDULE GFile: SCHEDULE G.pdf3 Feb 2022
SCHEDULE HFile: SCHEDULE H.pdf3 Feb 2022
SCHEDULE IFile: SCHEDULE I.pdf3 Feb 2022
SCHEDULE JFile: SCHEDULE J.pdf3 Feb 2022
SCHEDULE KFile: SCHEDULE K.pdf3 Feb 2022
SCHEDULE LFile: SCHEDULE L.pdf3 Feb 2022
SCHEDULE MFile: SCHEDULE M.pdf3 Feb 2022
SCHEDULE NFile: SCHEDULE N.pdf3 Feb 2022

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
FERNHILLNANTOOR, MANGALORECompleted-No date filed
CANOPYURWASTORE MANGALORECompleted-No date filed

How this compares with Dakshina Kannada

82%of this project is bookeddistrict median 38%
30%of Dakshina Kannada projects moved their completion datethis one moved by 12 months
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep AMITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmAMITYOther 63Dot size: filed unitsN

Filed coordinates, straight-line distance. 63 registered projects within 2 km.

Builder: MOHTISHAM COMPLEXES PVT LTD

Mohtisham Complexes Pvt Ltd has 2 registrations on RERA Karnataka, including FERNHILL and AMITY. Its filings declare 2 earlier projects, 1 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if AMITY is delayed beyond 28 Feb 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of AMITY?

The registered promoter entity is MOHTISHAM COMPLEXES PVT LTD, a company as per the filing. Its GSTIN 29AABCM3814A1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in AMITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AMITY?

The professionals named in the filing: Architect: DHARMARAJ ASSOCIATES; Engineer: N MANOHAR; Chartered Accountant: R KRISHNAN. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AMITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AMITY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AMITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.