Alpine Woods
By Ashapura and Ratan Developers
RG-MH-27544 · RERA P52100033976 · Last updated on MahaRERA portal: 18 Dec 2024
Source: official MahaRERA filing
Red flags
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Alpine Woods is a Others project by Ashapura and Ratan Developers in Pune, Maharashtra, registered with MahaRERA as P52100033976 on 14 Mar 2022. The registration is recorded completed; possession was promised by 31 Dec 2023.
At a glance
Project
- NameAlpine Woods
- TypeOthers
- Location
- Tungarli
- Lonavala (M Cl)
- Mawal
- Pune
- 410403
- Pincode410403
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100033976
- ReraGenie IDRG-MH-27544
Builder
- NameAshapura and Ratan Developers
- Entity typePartnership
- PartnersRamnivas Ramratan Gupta, Minal Mohan Dama, Ronak Bharat Bhanushali, Jitendra Tharyabhai Bhadra, Mohit Ramnivas Gupta
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on14 Mar 2022
- Promised completion31 Dec 2023
- Revised completionNone
- Buildings15 building records
- Documents filed71 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| F - P24 - Bungalow | NA | 4 | 0 | 0 | 0 | 0 |
| F -P25 - Bungalow | NA | 4 | 0 | 0 | 0 | 0 |
| F -P26 -Bungalow | NA | 4 | 0 | 0 | 0 | 0 |
| F -P30 -Bungalow | NA | 4 | 0 | 0 | 0 | 0 |
| F -P31 -Bungalow | NA | 4 | 0 | 0 | 0 | 0 |
| F- P32 -Bungalow | NA | 4 | 0 | 0 | 0 | 0 |
| F -P33 -Bungalow | NA | 4 | 0 | 0 | 0 | 0 |
| F -P34 -Bungalow | NA | 4 | 0 | 0 | 0 | 0 |
| G -P27 -Bungalow | NA | 4 | 0 | 0 | 0 | 0 |
| H -P28 - Building | NA | 2 | 0 | 0 | 0 | 0 |
| I -P22 - Bungalow | NA | 4 | 0 | 0 | 0 | 0 |
| I -P23 -Bungalow | NA | 4 | 0 | 0 | 0 | 0 |
| J - P -21 -Bungalow | NA | 4 | 0 | 0 | 0 | 0 |
| K -P35 -Bungalow | NA | 4 | 0 | 0 | 0 | 0 |
| K -P36 -Bungalow | NA | 4 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building15
As on 18 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
165 of 165 construction stages are filed complete across 15 buildings.
F - P24 - Bungalow100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
F -P25 - Bungalow100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
F -P26 -Bungalow100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
F -P30 -Bungalow100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
F -P31 -Bungalow100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
F- P32 -Bungalow100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
F -P33 -Bungalow100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
F -P34 -Bungalow100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
G -P27 -Bungalow100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
H -P28 - Building100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
I -P22 - Bungalow100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
I -P23 -Bungalow100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
J - P -21 -Bungalow100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
K -P35 -Bungalow100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
K -P36 -Bungalow100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 18 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Parking filed48
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| F - P24 - Bungalow | 3 | 3 |
| F -P25 - Bungalow | 3 | 3 |
| F -P26 -Bungalow | 3 | 3 |
| F -P30 -Bungalow | 3 | 3 |
| F -P31 -Bungalow | 3 | 3 |
| F- P32 -Bungalow | 3 | 3 |
| F -P33 -Bungalow | 3 | 3 |
| F -P34 -Bungalow | 3 | 3 |
| G -P27 -Bungalow | 3 | 3 |
| I -P22 - Bungalow | 4 | 4 |
| I -P23 -Bungalow | 4 | 4 |
| J - P -21 -Bungalow | 3 | 3 |
| K -P35 -Bungalow | 5 | 5 |
| K -P36 -Bungalow | 5 | 5 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Kanhaiya Associates |
| Engineer | G A Bhilare Consultants |
| Engineer | SK Consultants & Engineers |
| Chartered Accountant | Rutuja Narsingh & Associates |
| Chartered Accountant | M/s. Pratiksha Tulshyan & Associates |
| Partner | Role in project |
|---|---|
| Ashapura and Ratan Developers | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Mar 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Feb 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Feb 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 18 Dec 2024
Documents filed71
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: 4.PDF | 18 Dec 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC_11zon.pdf | 18 Dec 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC PHS-2 PDF.pdf | 16 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Alpine Woods Sep 2024.pdf | 18 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Alpine Woods as on 30-09-2024.pdf | 17 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Alpine Woods as on Sept 2024.pdf | 17 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Alpine Woods Sep 2024.pdf | 8 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 of Alpine Woods as on 31-03-2024.pdf | 8 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Alpine Woods as on June 2024.pdf | 10 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Alpine Woods 30-06-2024.pdf | 10 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Alpine Woods as on June 2024.pdf | 5 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: CIRCULAR 29 - Alpine Woods as on March 2024.PDF | 27 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Alpine Woods as on March 2024.pdf | 24 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Alpine Woods as on March 2024.pdf | 20 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Alpine Woods as on March 2024.pdf | 20 Apr 2024 |
| Declaration in FORM BFile: Form B.PDF | 15 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec.PDF | 15 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec.PDF | 15 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22_11zon.pdf | 15 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.PDF | 15 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec_11zon.pdf | 15 Mar 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.PDF | 15 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.PDF | 15 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.PDF | 15 Mar 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.PDF | 15 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: CIRCULAR 29 - Alpine Woods as on Dec 2023.PDF | 29 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Alpine Woods as on Dec 2023.pdf | 19 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New format- Form 3 Alpine Woods 31-12-2023.pdf | 19 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Alpine Woods as on Dec 2023.pdf | 10 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Alpine Woods as on 03-10-2023.pdf | 12 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Alpine Woods as on September 2023.pdf | 12 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Alpine Woods as on September 2023.pdf | 12 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5- Alpine Woods FY 2022-23.pdf | 26 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Alpine Woods - Form - 2A (2021-22).pdf | 9 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: Circular 29- Alpine Woods as on 30-06-2023.pdf | 4 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Alpine Woods as on June 2023.pdf | 12 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Alpine Woods as on June 2023.pdf | 12 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arc Certificate Up To June 2023_organized.pdf | 3 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Alpine Woods Mar 23 - Form 2.pdf | 18 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Alpine woods.pdf | 18 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Alpine Woods_organized.pdf | 5 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Circular 29- Alpine Woods.pdf | 10 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Alpine Woods as on December 2022.pdf | 20 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Alpine Woods as on December 2022.pdf | 20 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Alpine Woods.pdf | 7 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Alpine Woods Form 1.pdf | 6 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Alpine Woods Form 2- September 2022.pdf | 6 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New format- Form 3 Alpine Woods_September 2022.pdf | 6 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Certificate 107.pdf | 30 Sep 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Alpine Woods Form 2- 30 June 2022.pdf | 20 Jul 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New format- Form 3 Alpine Woods_June 2022_compressed.pdf | 20 Jul 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Alpine Woods Form 1 March 2022.pdf | 13 May 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Alpine Woods Form 2- 31st March 2022.pdf | 13 May 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Alpine Woods Form 2A.pdf | 13 May 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New format- Form 3 Alpine Woods_March 2022_11zon.pdf | 13 May 2022 |
| Copy of the legal title reportFile: output (3).pdf | 5 Mar 2022 |
| Declaration in FORM BFile: Alpine Woods -Notarised Form B.pdf | 4 Mar 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Alpine wood_organized.pdf | 1 Mar 2022 |
| Building plan approvalFile: Merged 6 ,7,8,9.pdf | 26 Feb 2022 |
| Building plan approvalFile: Page 10_11.pdf | 26 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Merged 6 ,7,8,9.pdf | 26 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Page 10_11.pdf | 26 Feb 2022 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 26 Feb 2022 |
| Proforma of Allotment letterFile: Final RERA Agreement as on 25-02-2022.pdf | 26 Feb 2022 |
| Layout approvalFile: Page -1_11zon.pdf | 25 Feb 2022 |
| PAN CardFile: Ashapura Ratan Pan.pdf | 25 Feb 2022 |
| Details of encumbrancesFile: Encumbrance -Alpine Woods.pdf | 25 Feb 2022 |
| Copy of Layout Approval (in case of layout)File: Page -1_11zon.pdf | 25 Feb 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: CC Phase 2 Page 1 (5 files merged).pdf | 25 Feb 2022 |
| Declaration about Commencement CertificateFile: Rera Declaration Of CC.pdf | 25 Feb 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200231117975_For_Asset_Based_Search_25_02_2022_13_17_37_792.pdf | 25 Feb 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 71 filed documents as one ZIP, foldered, with a manifest
Keep Alpine Woods on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Tungarli13,700+ in Pune
Filed coordinates, straight-line distance. 13 registered projects within 2 km.
MARIGOLD VILLAS
SHRI NARAYANI DEVELOPERS
Raindrop
Sadguru Developers
PARK LA WISH
JAINAM REALTORS
SHANTI HEIGHTS APPARTMENT
SHAASHWAT BUILDERS PROMOTERSAND DEVELOPOER
Godrej Ivara
Manjari Housing Projects LLP
CANARY FARMS
CANARY FARMS
Builder: Ashapura and Ratan Developers
Ashapura and Ratan Developers has 1 registration on MahaRERA, including Alpine Woods. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Alpine Woods is delayed beyond 31 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Alpine Woods?
The registered promoter entity is Ashapura and Ratan Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Alpine Woods?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Alpine Woods?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Alpine Woods?
The professionals named in the filing: Architect: Kanhaiya Associates; Engineer: G A Bhilare Consultants; Engineer: SK Consultants & Engineers; Chartered Accountant: Rutuja Narsingh & Associates; Chartered Accountant: M/s. Pratiksha Tulshyan & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Alpine Woods?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback